22706-22708 W CRISWELL ST 91307

Certificate Information: 22706-22708 W CRISWELL ST 91307

Application / Permit
19016-20000-12969
Plan Check / Job No.
B19VN07199
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ECPC WALK IN: CONVERT THE (E) ATTACHED GARAGE INTO A (N) ADU PER AB 494 AND SB 229 FOR ACCESSORY DWELLING UNITS. "COMPLY WITH DEPARTMENT ORDER effective date 02/13/2019. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 5/10/2019
Issuing Office
Valley
Current Status
CofO Issued on 3/20/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/2/2019 APPLICANT
Assigned to Plan Check Engineer 5/2/2019 MARVEL DELACRUZ
Corrections Issued 5/2/2019 MARVEL DELACRUZ
Plan Check Approved 5/10/2019 YAQUB MIRZA
Issued 5/10/2019 LADBS
CofO in Progress 3/20/2020 ROBERT GOLD
No Progress 3/20/2020 ROBERT GOLD
CofO in Progress 3/20/2020 ROBERT GOLD
Permit Finaled 3/20/2020 ROBERT GOLD
CofO Issued 3/20/2020 ROBERT GOLD
Permit Finaled 3/20/2020 ROBERT GOLD

Permit Application Clearance Information

Address approval Cleared 5/3/2019 APEKSHYA BAJRACHARYA
Eng Process Fee Ord 176,300 Cleared 5/3/2019 APEKSHYA BAJRACHARYA
Sewer availability Cleared 5/3/2019 APEKSHYA BAJRACHARYA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARA SINANIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HASANTHA WEERASEKARA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
SCOTT SHUSTER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOEL GUARDADO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARIYA MIHALEVA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOSE RUBIO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID JAMES, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID HICKMAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN HAMILTON, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN STEPHENS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
PIERRE VEGA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK VAN SLOOTEN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MICKEY YAMASHITA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
RICHARD ROBLES, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HAGOP BADOSSIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
KIM BEAUCHAMP, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK DOVICO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
THOMAS WOODS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
RAUL VASQUEZ, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
AUGUSTUS ALBAS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
FELIPE PENICHE, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
LEO MILBAUER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/30/2019 Approved HAGOP BADOSSIAN
Pre-Inspection 12/30/2019 Not Ready for Inspection HAGOP BADOSSIAN
Footing/Foundation/Slab 1/7/2020 Not Ready for Inspection HAGOP BADOSSIAN
Footing/Foundation/Slab 1/22/2020 Not Ready for Inspection HAGOP BADOSSIAN
Footing/Foundation/Slab 1/29/2020 Approved HAGOP BADOSSIAN
BUILDING-Rough-Frame 2/4/2020 Corrections Issued ROBERT GOLD
Green Building Rough 2/4/2020 Not Ready for Inspection ROBERT GOLD
PLUMBING-Final 2/4/2020 Corrections Issued ROBERT GOLD
PLUMBING-Rough 2/6/2020 Approved ROBERT GOLD
BUILDING-Rough-Frame 2/11/2020 Corrections Issued ROBERT GOLD
ELECTRICAL-Rough 2/11/2020 Not Ready for Inspection ROBERT GOLD
Green Building Rough 2/11/2020 Not Ready for Inspection ROBERT GOLD
Shower Pan 2/11/2020 Corrections Issued ROBERT GOLD
ELECTRICAL-Rough 2/14/2020 Corrections Issued ROBERT GOLD
Shower Pan 2/14/2020 Approved ROBERT GOLD
ELECTRICAL-Rough 2/19/2020 Partial Approval ROBERT GOLD
Interior/Exterior Lathing 2/19/2020 Partial Approval ROBERT GOLD
ELECTRICAL-Final 2/28/2020 Partial Approval EMIL OPFFER
Floor/Roof Diaphrgm/Shear Wall 2/28/2020 Partial Approval EMIL OPFFER
ELECTRICAL-Final 3/3/2020 Conditional Approval EMIL OPFFER
Interior/Exterior Lathing 3/3/2020 Not Ready for Inspection EMIL OPFFER
ELECTRICAL-Final 3/4/2020 Partial Approval EMIL OPFFER
Interior/Exterior Lathing 3/4/2020 Approved EMIL OPFFER
BUILDING-Rough-Frame 3/6/2020 Approved EMIL OPFFER
Final 3/6/2020 Not Ready for Inspection EMIL OPFFER
Green Building Final 3/6/2020 Not Ready for Inspection EMIL OPFFER
Green Building Rough 3/6/2020 Approved EMIL OPFFER
SGSOV-Seismic Gas S/O Valve 3/6/2020 SGSOV Not Ready EMIL OPFFER
Smoke Detectors 3/6/2020 Approved EMIL OPFFER
Pre-Inspection 3/10/2020 Corrections Issued ROBERT GOLD
Final 3/13/2020 Conditional Approval ROBERT GOLD
Green Building Final 3/13/2020 Approved ROBERT GOLD
SGSOV-Seismic Gas S/O Valve 3/13/2020 SGSOV Approved ROBERT GOLD
Final 3/20/2020 OK to Issue CofO ROBERT GOLD
Service/Power Release 3/20/2020 Approved ROBERT GOLD