14131 W LEMAY ST 91405
Certificate Information: 14131 W LEMAY ST 91405
- Application / Permit
- 19016-20000-12778
- Plan Check / Job No.
- B19VN07093
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) REC ROOM AND STORAGE ROOM TO ACCESSORY DWELLING UNIT (617 SQ FT) PER AB 494 AND SB 229
- Permit Issued
- Issued on 5/13/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/1/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/1/2019 | JEROME MAGAT PALMA |
| Corrections Issued | 5/2/2019 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 5/2/2019 | APPLICANT |
| Plan Check Approved | 5/8/2019 | JEROME MAGAT PALMA |
| Issued | 5/13/2019 | LADBS |
| CofO in Progress | 6/24/2025 | RYAN SALAZAR |
| Permit Finaled | 7/10/2025 | RUBEN SALAS |
| CofO Issued | 7/10/2025 | RUBEN SALAS |
| Permit Finaled | 7/10/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 5/6/2019 | APEKSHYA BAJRACHARYA |
| Eng Process Fee Ord 176,300 | Cleared | 5/6/2019 | APEKSHYA BAJRACHARYA |
| Miscellaneous | Cleared | 5/6/2019 | HERMINIGILDO AGUSTIN |
| Miscellaneous | Cleared | 5/6/2019 | HERMINIGILDO AGUSTIN |
| Sewer availability | Cleared | 5/6/2019 | APEKSHYA BAJRACHARYA |
| HPOZ | Cleared | 5/7/2019 | SUKI GERSHENHORN |
| ZI | Cleared | 5/7/2019 | SUKI GERSHENHORN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/22/2020 | Approved | ARAM AVEDISIAN |
| Pre-Inspection | 2/3/2020 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 3/3/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 3/3/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| Underground Mechanical | 3/3/2020 | Partial Approval | MISAEL ESPARZA |
| Rough-Elec/Plmb/HVAC | 3/9/2020 | Approved | MISAEL ESPARZA |
| Insulation | 5/1/2020 | Approved | GREGG CUMMINGS |
| Drywall Nailing | 5/8/2020 | Partial Approval | MISAEL ESPARZA |
| Shower Pan | 5/8/2020 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 5/12/2020 | Partial Inspection | MISAEL ESPARZA |
| Drywall Nailing | 6/22/2020 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 7/22/2020 | Partial Inspection | WILLIAM KUEHN |
| BUILDING-Rough-Frame | 6/12/2025 | Approved | RYAN SALAZAR |
| Final | 6/12/2025 | Corrections Issued | RYAN SALAZAR |
| Green Building Final | 6/12/2025 | Not Ready for Inspection | RYAN SALAZAR |
| Green Building Rough | 6/12/2025 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 6/12/2025 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 6/12/2025 | Approved | RYAN SALAZAR |
| Final | 6/23/2025 | OK to Issue CofO | RYAN SALAZAR |
| Green Building Final | 6/23/2025 | Approved | RYAN SALAZAR |
| Service/Power Release | 6/23/2025 | Approved | RYAN SALAZAR |