5275 N CRANER AVE 91601

Certificate Information: 5275 N CRANER AVE 91601

Application / Permit
19016-20000-12126
Plan Check / Job No.
B19VN06727
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
EXPAND (E) MEZZANINE BY (IRR 100' X 20'-9") OF (E) 1-STORY OFFICE & WAREHOUSE CREATING A 2-STORY OFFICE/WAREHOUSE BLDG (SEE COMMENTS); INTERIOR REMODEL
Permit Issued
Issued on 6/26/2019
Issuing Office
Valley
Current Status
CofO Issued on 7/30/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/25/2019 APPLICANT
Assigned to Plan Check Engineer 5/9/2019 NILOOFAR MEHRAIN
Corrections Issued 5/13/2019 NILOOFAR MEHRAIN
Disabled Access Plans Picked Up 5/13/2019 APPLICANT
Quality Review Completed 5/15/2019 CHON CHIO KUO
Building Plans Picked Up 5/17/2019 APPLICANT
Plan Check Approved 6/13/2019 NILOOFAR MEHRAIN
Issued 6/26/2019 LADBS
CofO in Progress 6/30/2020 ROBERT DAVIS
CofO Issued 7/30/2020 JEFFREY DURAN
Permit Finaled 7/30/2020 JEFFREY DURAN

Permit Application Clearance Information

Hydrant and Access approval Cleared 5/17/2019 GEORGE SUCHAND
CPC Cleared 5/20/2019 ANNA VIDAL
ZI Cleared 5/20/2019 ANNA VIDAL
Project located in CRA area Cleared 5/21/2019 JIM URQUHART
Eng Process Fee Ord 176,300 Cleared 5/22/2019 ELENA LOPEZ
Low Impact Development Cleared 5/22/2019 SEAN SHAHMIRI
Permit Cleared 5/22/2019 ELENA LOPEZ
Roof/Waste drainage to street Cleared 5/22/2019 ELENA LOPEZ
Sewer availability Cleared 5/22/2019 ELENA LOPEZ
Trees in Parkway Cleared 5/22/2019 JOHN KIM
DAS Clearance Cleared 6/11/2019 NORLITO MEDRANO
Highway dedication Cleared 6/12/2019 JOHN LIN
Green Code Cleared 6/13/2019 MICHAEL AYERS

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia,, Francisco Diaz; Lic. No.: C88029 7333 RANCHITO AVE      VAN NUYS, CA 91405

Inspector Information

JEFFREY FULTON, (818) 374-1132 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/17/2019 Corrections Issued ROBERT DAVIS
METHANE-Barrier 7/17/2019 Approved ROBERT DAVIS
METHANE-Subgrade 7/17/2019 Approved ROBERT DAVIS
Pre-Inspection 8/29/2019 Approved ROBERT DAVIS
Wood Frame 9/5/2019 Conditional Approval ROBERT DAVIS
Deputy Drilled-In Anchors 9/19/2019 Approved ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 9/24/2019 Approved ROBERT DAVIS
Drywall Nailing 11/8/2019 Partial Approval ROBERT DAVIS
Drywall Nailing 12/10/2019 Partial Approval ROBERT DAVIS
Final 6/8/2020 OK to Issue CofO ROBERT DAVIS
Footing/Foundation/Slab 6/8/2020 Approved ROBERT DAVIS
Green Building Final 6/8/2020 Approved ROBERT DAVIS
METHANE-Final 6/8/2020 Approved ROBERT DAVIS
SGSOV-Seismic Gas S/O Valve 6/8/2020 SGSOV No Gas ROBERT DAVIS
Smoke Detectors 6/8/2020 Approved ROBERT DAVIS