1302 E 104TH ST 90002
Certificate Information: 1302 E 104TH ST 90002
- Application / Permit
- 19016-20000-11995
- Plan Check / Job No.
- B19VN06659
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK PER WFPP
- Permit Issued
- Issued on 5/3/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/27/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/24/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 4/24/2019 | MARVEL DELACRUZ |
| Corrections Issued | 4/24/2019 | MARVEL DELACRUZ |
| Plan Check Approved | 5/3/2019 | ANGELICA MARTINEZ |
| Issued | 5/3/2019 | LADBS |
| CofO in Progress | 6/27/2023 | JOHN KLARIN |
| Permit Finaled | 6/27/2023 | ANSON MAGLASANG |
| CofO Issued | 6/27/2023 | ANSON MAGLASANG |
| Permit Finaled | 6/27/2023 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 4/24/2019 | JOSHUA DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/24/2019 | JOSHUA DIAZ |
| Permit | Cleared | 4/24/2019 | JOSHUA DIAZ |
| Sewer availability | Cleared | 4/24/2019 | JOSHUA DIAZ |
| Construction near power lines | Cleared | 4/25/2019 | OSCAR CASTRO |
| Trees in Parkway | Cleared | 5/2/2019 | MARVEL DELACRUZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/11/2019 | Corrections Issued | DAVID FEILER |
| Deputy Drilled-In Anchors | 6/12/2019 | Conditional Approval | PAUL BECKER |
| Footing/Foundation/Slab | 6/17/2019 | Corrections Issued | DAVID FEILER |
| Footing/Foundation/Slab | 6/21/2019 | Approved | DAVID FEILER |
| BUILDING-Rough-Frame | 8/5/2019 | Corrections Issued | WILLIAM ROSE |
| ELECTRICAL-Rough | 8/5/2019 | Not Ready for Inspection | WILLIAM ROSE |
| Green Building Rough | 8/5/2019 | Not Ready for Inspection | WILLIAM ROSE |
| PLUMBING-Rough | 8/5/2019 | Corrections Issued | WILLIAM ROSE |
| BUILDING-Rough-Frame | 9/6/2019 | Approved | WILLIAM ROSE |
| ELECTRICAL-Rough | 9/6/2019 | Approved | WILLIAM ROSE |
| Green Building Rough | 9/6/2019 | Approved | WILLIAM ROSE |
| Insulation | 9/17/2019 | Corrections Issued | WILLIAM ROSE |
| Insulation | 10/1/2019 | Corrections Issued | EUGENE CASSIDY |
| Insulation | 10/8/2019 | Approved | WILLIAM ROSE |
| Drywall Nailing | 10/16/2019 | Not Ready for Inspection | WILLIAM ROSE |
| Drywall Nailing | 10/18/2019 | Approved | WILLIAM ROSE |
| Interior/Exterior Lathing | 10/18/2019 | Not Ready for Inspection | WILLIAM ROSE |
| ELECTRICAL-Final | 11/12/2019 | Not Ready for Inspection | WILLIAM ROSE |
| Green Building Final | 11/12/2019 | Not Ready for Inspection | WILLIAM ROSE |
| HVAC-Final | 11/12/2019 | Not Ready for Inspection | WILLIAM ROSE |
| Interior/Exterior Lathing | 11/12/2019 | Partial Approval | WILLIAM ROSE |
| PLUMBING-Final | 11/12/2019 | Not Ready for Inspection | WILLIAM ROSE |
| SGSOV-Seismic Gas S/O Valve | 11/12/2019 | SGSOV Not Ready | WILLIAM ROSE |
| Smoke Detectors | 11/12/2019 | Not Ready for Inspection | WILLIAM ROSE |
| Underground Mechanical | 2/25/2020 | Corrections Issued | EUGENE CASSIDY |
| Underground Mechanical | 2/27/2020 | Corrections Issued | WILLIAM ROSE |
| PLUMBING-Rough | 3/9/2020 | Corrections Issued | WILLIAM ROSE |
| PLUMBING-Rough | 3/17/2020 | Not Ready for Inspection | WILLIAM ROSE |
| PLUMBING-Rough | 3/26/2020 | Approved | BRIAN CHRISTIAN |
| Underground Mechanical | 3/26/2020 | Approved | BRIAN CHRISTIAN |
| ELECTRICAL-Final | 4/10/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 4/10/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Green Building Final | 4/10/2020 | Corrections Issued | EUGENE CASSIDY |
| HVAC-Final | 4/10/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Final | 4/10/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 4/10/2020 | SGSOV Approved | EUGENE CASSIDY |
| Smoke Detectors | 4/10/2020 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 5/22/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 5/22/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Green Building Final | 5/22/2020 | Corrections Issued | EUGENE CASSIDY |
| HVAC-Final | 5/22/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Final | 5/22/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| ELECTRICAL-Final | 6/11/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 6/11/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Green Building Final | 6/11/2020 | Corrections Issued | EUGENE CASSIDY |
| HVAC-Final | 6/11/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Final | 6/11/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| ELECTRICAL-Final | 6/26/2020 | Approved | EUGENE CASSIDY |
| Final | 6/26/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Green Building Final | 6/26/2020 | Corrections Issued | EUGENE CASSIDY |
| HVAC-Final | 6/26/2020 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 6/26/2020 | Approved | EUGENE CASSIDY |
| Final | 6/27/2023 | OK to Issue CofO | JOHN KLARIN |
| Green Building Final | 6/27/2023 | Approved | JOHN KLARIN |