2006 N SERRANO AVE 90027

Certificate Information: 2006 N SERRANO AVE 90027

Application / Permit
19016-20000-11637
Plan Check / Job No.
B19VN06452
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 17'-9" X 19'-5" DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 & SB 229. ------- Comply with department order effective date 01/30/2019, permit will expire 30 days from issuance date. All works are per WFPP
Permit Issued
Issued on 9/6/2019
Issuing Office
Valley
Current Status
CofO Issued on 9/23/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/22/2019 APPLICANT
Assigned to Plan Check Engineer 4/22/2019 NIKTA MOUSAVI
Corrections Issued 4/22/2019 NIKTA MOUSAVI
Applicant returned to address corrections 5/8/2019 JENNIFER LEE
Applicant returned to address corrections 6/19/2019 ALDOUS CHIC
Plan Check Approved 9/5/2019 RAPHAEL ROSAS
Issued 9/6/2019 LADBS
CofO in Progress 9/1/2021 JOHN TCHANG
No Progress 9/1/2021 JOHN TCHANG
CofO in Progress 9/1/2021 JOHN TCHANG
Permit Finaled 9/23/2021 DANIEL SANCHEZ
CofO Issued 9/23/2021 DANIEL SANCHEZ
Permit Finaled 9/23/2021 DANIEL SANCHEZ

Permit Application Clearance Information

Grading Pre-Inspection Cleared 5/8/2019 NIKTA MOUSAVI
Address approval Cleared 6/19/2019 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 6/19/2019 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 6/19/2019 LEE GUILBEAUX
Sewer availability Cleared 6/19/2019 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 6/19/2019 LEE GUILBEAUX
Public Works-Sewers Cleared 6/19/2019 LEE GUILBEAUX
Construction within easement Cleared 8/21/2019 RIDWAN HARDY

Contact Information

Contractor Ground Up Builders And Design Inc; Lic. No.: 911849-B 14545 VICTORY BLVD STE 601      VAN NUYS, CA 91411

Inspector Information

JOEL ORDAZ, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
PTOLEMY HILL, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
JONATHAN FRANCHINI, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVAKIAN, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
EDMOND DECKERT, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
TIMOTHY KEY, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT CHAVEZ, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 9/13/2019 Corrections Issued JOHN TCHANG
Green Building Final 9/13/2019 Not Ready for Inspection JOHN TCHANG
Green Building Rough 9/13/2019 Not Ready for Inspection JOHN TCHANG
Pre-Inspection 9/13/2019 Approved JOHN TCHANG
SGSOV-Seismic Gas S/O Valve 9/13/2019 SGSOV Not Ready JOHN TCHANG
Smoke Detectors 9/13/2019 Not Ready for Inspection JOHN TCHANG
BUILDING-Rough-Frame 12/2/2019 Corrections Issued JOHN TCHANG
ELECTRICAL-Rough 12/2/2019 Corrections Issued JOHN TCHANG
Final 12/2/2019 Not Ready for Inspection JOHN TCHANG
Green Building Final 12/2/2019 Not Ready for Inspection JOHN TCHANG
Green Building Rough 12/2/2019 Not Ready for Inspection JOHN TCHANG
PLUMBING-Rough 12/2/2019 Corrections Issued JOHN TCHANG
SGSOV-Seismic Gas S/O Valve 12/2/2019 SGSOV Not Ready JOHN TCHANG
Smoke Detectors 12/2/2019 Not Ready for Inspection JOHN TCHANG
Gas Test 6/24/2021 Not Ready for Inspection JOHN TCHANG
PLUMBING-Rough 6/24/2021 Approved JOHN TCHANG
BUILDING-Rough-Frame 9/1/2021 Approved JOHN TCHANG
Final 9/1/2021 OK to Issue CofO JOHN TCHANG
Green Building Final 9/1/2021 Approved JOHN TCHANG
Green Building Rough 9/1/2021 Approved JOHN TCHANG
SGSOV-Seismic Gas S/O Valve 9/1/2021 SGSOV Approved JOHN TCHANG
Smoke Detectors 9/1/2021 Approved JOHN TCHANG