4517 N ST CLAIR AVE 91604
Certificate Information: 4517 N ST CLAIR AVE 91604
- Application / Permit
- 19016-20000-11627
- Plan Check / Job No.
- B19VN06447
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DETACHED GARAGE/STORAGE BUILDING TO ACCESSORY DWELLING UNIT PER AB494 AND SB229. Comply with department order effective date 3/14/2019, permit will expire 30 days from issuace date
- Permit Issued
- Issued on 1/28/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/1/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/22/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 4/22/2019 | ALDOUS CHIC |
| Corrections Issued | 10/29/2019 | ALDOUS CHIC |
| Plan Check Approved | 11/8/2019 | ARTIN ZARUKIAN |
| Issued | 1/28/2020 | LADBS |
| CofO in Progress | 12/3/2020 | ARAM AVEDISIAN |
| No Progress | 2/23/2021 | ARAM AVEDISIAN |
| CofO in Progress | 2/23/2021 | ARAM AVEDISIAN |
| CofO in Progress | 5/1/2021 | DANIEL ORRANTE |
| Permit Finaled | 5/1/2021 | MICHAEL SMITH |
| CofO Issued | 5/1/2021 | MICHAEL SMITH |
| Permit Finaled | 5/1/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 4/22/2019 | ISRAEL TAMIRU |
| Eng Process Fee Ord 176,300 | Cleared | 4/22/2019 | ISRAEL TAMIRU |
| Sewer availability | Cleared | 4/22/2019 | ISRAEL TAMIRU |
| Construction near power lines | Cleared | 9/21/2019 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/22/2020 | Partial Approval | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 10/2/2020 | Partial Approval | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 10/2/2020 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/14/2020 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 10/14/2020 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 10/14/2020 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 10/19/2020 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 11/20/2020 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 11/20/2020 | Approved | ARAM AVEDISIAN |
| Final | 11/20/2020 | Corrections Issued | ARAM AVEDISIAN |
| Green Building Final | 11/20/2020 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 11/20/2020 | Approved | ARAM AVEDISIAN |
| HVAC-Final | 11/20/2020 | Approved | ARAM AVEDISIAN |
| MERV13>=Final | 11/20/2020 | Approved | ARAM AVEDISIAN |
| MERV13>=Rough | 11/20/2020 | Approved | ARAM AVEDISIAN |
| PLUMBING-Final | 11/20/2020 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 11/20/2020 | SGSOV Approved | ARAM AVEDISIAN |
| Smoke Detectors | 11/20/2020 | Approved | ARAM AVEDISIAN |
| Final | 12/3/2020 | Not Ready for Inspection | ARAM AVEDISIAN |
| Final | 2/23/2021 | Corrections Issued | ARAM AVEDISIAN |
| Final | 5/1/2021 | OK to Issue CofO | DANIEL ORRANTE |