26207 S ZEPHYR AVE 90710
Certificate Information: 26207 S ZEPHYR AVE 90710
- Application / Permit
- 19016-20000-10433
- Plan Check / Job No.
- B19VN05781
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 24' x 24' DET. GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK PER ENG.
- Permit Issued
- Issued on 5/3/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/10/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 4/10/2019 | JEFFREY TANGONAN |
| Corrections Issued | 4/10/2019 | JEFFREY TANGONAN |
| Building Plans Picked Up | 4/12/2019 | APPLICANT |
| Plan Check Approved | 5/2/2019 | JEFFREY TANGONAN |
| Issued | 5/3/2019 | LADBS |
| Refund Closed | 7/13/2021 | TERENCE SHIA |
| Issued | 7/13/2021 | TERENCE SHIA |
| Refund in Progress-Status Void | 7/19/2021 | EMILY HU |
| Re-Activate Permit | 7/22/2021 | MARY SUM |
| CofO in Progress | 1/20/2022 | ANSON MAGLASANG |
| Permit Finaled | 1/22/2022 | DEROLD HAUFF |
| CofO Issued | 1/22/2022 | DEROLD HAUFF |
| Permit Finaled | 1/22/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/12/2019 | GUILLERMO PETRA |
| ZA Case | Cleared | 4/12/2019 | HERMINIGILDO AGUSTIN |
| Grading Pre-Inspection | Cleared | 4/15/2019 | PATRICK MISCHLICH |
| Construction near power lines | Cleared | 4/17/2019 | NADER ISKANDER |
| Eng Process Fee Ord 176,300 | Cleared | 4/24/2019 | GUILLERMO PETRA |
| Sewer availability | Cleared | 4/24/2019 | GUILLERMO PETRA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Li,, Dacheng David; Lic. No.: C58075 | 3129 S HACIENDA BL STE 524 HACIENDA HEIGHTS, CA 91745 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/17/2019 | Partial Inspection | JOHN KLARIN |
| PLUMBING-Rough | 9/5/2019 | Partial Inspection | JOHN KLARIN |
| Footing/Foundation/Slab | 9/9/2019 | Not Ready for Inspection | JOHN KLARIN |
| Footing/Foundation/Slab | 9/12/2019 | Approved | JOHN KLARIN |
| Pre-Inspection | 6/12/2020 | Not Ready for Inspection | BRIAN CHRISTIAN |
| ELECTRICAL-Rough | 11/30/2020 | Corrections Issued | JOHN KLARIN |
| HVAC-Rough | 11/30/2020 | Corrections Issued | JOHN KLARIN |
| PLUMBING-Rough | 11/30/2020 | Corrections Issued | JOHN KLARIN |
| Rough-Elec/Plmb/HVAC | 12/16/2020 | Approved | JOHN KLARIN |
| Insulation | 7/1/2021 | Corrections Issued | JOHN KLARIN |
| Insulation | 7/8/2021 | Corrections Issued | JESUS RODRIGUEZ |
| Insulation | 7/13/2021 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 7/13/2021 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 7/15/2021 | Corrections Issued | JOHN KLARIN |
| Drywall Nailing | 7/26/2021 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 7/26/2021 | Approved | JOHN KLARIN |
| ELECTRICAL-Rough | 8/2/2021 | Approved | JOHN KLARIN |
| Service/Power Release | 8/13/2021 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 10/5/2021 | Not Ready for Inspection | JOHN KLARIN |
| Final | 10/5/2021 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 10/5/2021 | Not Ready for Inspection | JOHN KLARIN |
| Green Building Rough | 10/5/2021 | Not Ready for Inspection | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 10/5/2021 | SGSOV Not Ready | JOHN KLARIN |
| Smoke Detectors | 10/5/2021 | Not Ready for Inspection | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 10/20/2021 | SGSOV Not Ready | JOHN KLARIN |
| BUILDING-Rough-Frame | 10/26/2021 | Not Ready for Inspection | JOHN KLARIN |
| Final | 10/26/2021 | Not Ready for Inspection | JOHN KLARIN |
| Green Building Final | 10/26/2021 | Not Ready for Inspection | JOHN KLARIN |
| Green Building Rough | 10/26/2021 | Not Ready for Inspection | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 10/26/2021 | SGSOV Not Required | JOHN KLARIN |
| Smoke Detectors | 10/26/2021 | Not Ready for Inspection | JOHN KLARIN |
| BUILDING-Rough-Frame | 11/9/2021 | Approved | JOHN KLARIN |
| Final | 11/9/2021 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 11/9/2021 | Approved | JOHN KLARIN |
| Green Building Rough | 11/9/2021 | Approved | JOHN KLARIN |
| Smoke Detectors | 11/9/2021 | Approved | JOHN KLARIN |
| Final | 11/15/2021 | Not Ready for Inspection | JOHN KLARIN |
| Final | 11/22/2021 | Corrections Issued | JOHN KLARIN |
| ELECTRICAL-Final | 12/7/2021 | Approved | JOHN KLARIN |
| Final | 12/7/2021 | Corrections Issued | JOHN KLARIN |
| HVAC-Final | 12/7/2021 | Approved | JOHN KLARIN |
| PLUMBING-Final | 12/7/2021 | Approved | JOHN KLARIN |
| Final | 1/20/2022 | OK to Issue CofO | ANSON MAGLASANG |