12149 W CALVERT ST 91606

Certificate Information: 12149 W CALVERT ST 91606

Application / Permit
19016-20000-09771
Plan Check / Job No.
B19VN05410
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 19'-10" X 29'-7" DETACHED GARAGE / STORAGE TO (N) ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK PER DESIGN.
Permit Issued
Issued on 9/11/2019
Issuing Office
Valley
Current Status
CofO Issued on 6/25/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/5/2019 APPLICANT
Assigned to Plan Check Engineer 4/9/2019 JENNIFER LEE
Corrections Issued 4/9/2019 JENNIFER LEE
Plan Check Approved 4/12/2019 RARES BODEA
Issued 9/11/2019 LADBS
CofO in Progress 6/11/2020 BRENDAN LOONEY
No Progress 9/1/2020 BRENDAN LOONEY
Refund in Progress 9/1/2020 MARY SUM
Refund Closed 9/1/2020 MARY SUM
Reactivate - Status Void 9/1/2020 MARY SUM
CofO in Progress 6/12/2021 DANIEL ORRANTE
CofO Issued 6/25/2021 MICHAEL SMITH
Permit Finaled 6/25/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 4/10/2019 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 4/10/2019 GUILLERMO PETRA
Permit Cleared 4/10/2019 GUILLERMO PETRA
Sewer availability Cleared 4/10/2019 GUILLERMO PETRA
ZA Case Cleared 4/10/2019 SHEILA GERSHON
ZA Case Cleared 4/10/2019 SHEILA GERSHON
Trees in Parkway Cleared 4/11/2019 JOHN KIM

Contact Information

Architect Miller,, Michael; Lic. No.: C26956 12756 MITCHELL AVE      LOS ANGELES, CA 90066
Contractor Your Favorite Contractor Inc; Lic. No.: 851344-B 18375 VENTURA BLVD #402      TARZANA, CA 91356

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/23/2019 Partial Approval GREG ALLTON
PLUMBING-Rough 9/23/2019 Partial Approval GREG ALLTON
Footing/Foundation/Slab 9/25/2019 Approved GREG ALLTON
ELECTRICAL-Rough 10/8/2019 Partial Approval CHRISTOPHE COCHRAN
Insulation 10/8/2019 Partial Approval CHRISTOPHE COCHRAN
PLUMBING-Rough 10/8/2019 Partial Approval CHRISTOPHE COCHRAN
ELECTRICAL-Rough 10/11/2019 Conditional Approval GREG ALLTON
HVAC-Rough 10/11/2019 Approved GREG ALLTON
Insulation 10/11/2019 Partial Approval GREG ALLTON
PLUMBING-Rough 10/11/2019 Conditional Approval GREG ALLTON
BUILDING-Rough-Frame 10/15/2019 Not Ready for Inspection GREG ALLTON
ELECTRICAL-Rough 10/15/2019 Partial Inspection GREG ALLTON
Green Building Rough 10/15/2019 Not Ready for Inspection GREG ALLTON
Interior/Exterior Lathing 10/15/2019 Not Ready for Inspection GREG ALLTON
MERV13>=Rough 10/15/2019 Not Ready for Inspection GREG ALLTON
PLUMBING-Rough 10/15/2019 Partial Approval GREG ALLTON
Interior/Exterior Lathing 10/17/2019 Partial Approval GREG ALLTON
Drywall Nailing 10/29/2019 Approved GREG ALLTON
Green Building Rough 10/29/2019 Approved GREG ALLTON
Interior/Exterior Lathing 10/29/2019 Approved GREG ALLTON
Special/Order Compliance 12/9/2019 Partial Inspection DANIEL ORRANTE
BUILDING-Rough-Frame 3/5/2020 Approved GREG ALLTON
Final 3/5/2020 Not Ready for Inspection GREG ALLTON
Green Building Final 3/5/2020 Approved GREG ALLTON
MERV13>=Final 3/5/2020 Approved GREG ALLTON
MERV13>=Rough 3/5/2020 Approved GREG ALLTON
SGSOV-Seismic Gas S/O Valve 3/5/2020 SGSOV Approved GREG ALLTON
Smoke Detectors 3/5/2020 Approved GREG ALLTON
Final 3/11/2020 Partial Inspection GREG ALLTON
Special/Order Compliance 3/11/2020 Partial Inspection DANIEL ORRANTE
ELECTRICAL-Rough 4/7/2020 Corrections Issued MATTHEW NELSON
HVAC-Rough 4/7/2020 Approved MATTHEW NELSON
ELECTRICAL-Final 4/14/2020 Corrections Issued RAYMOND KEHOE
Final 4/14/2020 Corrections Issued RAYMOND KEHOE
HVAC-Final 4/14/2020 Corrections Issued RAYMOND KEHOE
PLUMBING-Final 4/14/2020 Corrections Issued RAYMOND KEHOE
Special/Order Compliance 4/14/2020 Corrections Issued DANIEL ORRANTE
Final 6/3/2020 Not Ready for Inspection BRENDAN LOONEY
Final 6/10/2020 OK to Issue CofO BRENDAN LOONEY