13250-13252 W GOLETA ST 91331
Certificate Information: 13250-13252 W GOLETA ST 91331
- Application / Permit
- 19016-20000-09308
- Plan Check / Job No.
- B19VN05155
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) 18'-0" X 22'-0" ATTACHED GARAGE AND 18' X 24' SECOND STORY ADDTION OF (N) ACCESSORY DWELLING UNIT. ALL WORK PER ENGINEER.
- Permit Issued
- Issued on 5/21/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/15/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/2/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 4/8/2019 | JENNIFER LEE |
| Corrections Issued | 4/8/2019 | JENNIFER LEE |
| Plan Check Approved | 5/1/2020 | PINANK PATEL |
| Issued | 5/21/2020 | LADBS |
| CofO in Progress | 9/23/2020 | MICHEL ABAJAN |
| Permit Finaled | 10/15/2020 | MICHAEL SMITH |
| CofO Issued | 10/15/2020 | MICHAEL SMITH |
| Permit Finaled | 10/15/2020 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 4/9/2019 | APEKSHYA BAJRACHARYA |
| Eng Process Fee Ord 176,300 | Cleared | 4/9/2019 | APEKSHYA BAJRACHARYA |
| Sewer availability | Cleared | 4/9/2019 | APEKSHYA BAJRACHARYA |
| Certificate of Compliance | Cleared | 2/12/2020 | MARC WOERSCHING |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Van, Valkenburg, John Marshall; Lic. No.: C74939 | 13259 KISMET AVE SYLMAR, CA 91342 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 6/18/2020 | Approved | MICHEL ABAJAN |
| Footing/Foundation/Slab | 6/24/2020 | Approved | MICHEL ABAJAN |
| METHANE-Barrier | 6/24/2020 | Approved | MICHEL ABAJAN |
| METHANE-Subgrade | 6/24/2020 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 7/3/2020 | Partial Approval | MATTHEW NUCKOLLS |
| Green Building Rough | 7/3/2020 | Not Ready for Inspection | MATTHEW NUCKOLLS |
| METHANE-Rough | 7/3/2020 | Not Ready for Inspection | MATTHEW NUCKOLLS |
| Floor/Roof Diaphrgm/Shear Wall | 7/22/2020 | Partial Approval | MICHEL ABAJAN |
| ELECTRICAL-Rough | 8/6/2020 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 8/6/2020 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 8/6/2020 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 8/11/2020 | Approved | MICHEL ABAJAN |
| Green Building Rough | 8/11/2020 | Approved | MICHEL ABAJAN |
| METHANE-Rough | 8/11/2020 | Approved | MICHEL ABAJAN |
| Insulation | 8/14/2020 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 8/14/2020 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 8/21/2020 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 9/17/2020 | Approved | MICHEL ABAJAN |
| Final | 9/17/2020 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 9/17/2020 | Approved | MICHEL ABAJAN |
| HVAC-Final | 9/17/2020 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 9/17/2020 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 9/17/2020 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 9/17/2020 | Approved | MICHEL ABAJAN |
| Final | 9/23/2020 | OK to Issue CofO | MICHEL ABAJAN |