21223 W VELICATA ST 91364
Certificate Information: 21223 W VELICATA ST 91364
- Application / Permit
- 19016-20000-08900
- Plan Check / Job No.
- B19VN04917
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO (N) ACCESSORY DWELLING UNIT.
- Permit Issued
- Issued on 2/23/2022
- Issuing Office
- Current Status
- CofO Issued on 8/11/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/28/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 3/28/2019 | ALDOUS CHIC |
| Corrections Issued | 3/29/2019 | ALDOUS CHIC |
| Applicant returned to address corrections | 12/13/2021 | JENNIFER LEE |
| Applicant returned to address corrections | 1/14/2022 | PINANK PATEL |
| Plan Check Approved | 2/10/2022 | PINANK PATEL |
| Building Plans Picked Up | 2/10/2022 | APPLICANT |
| Issued | 2/23/2022 | APPLICANT |
| CofO in Progress | 7/26/2022 | PETER FOLLING |
| Permit Finaled | 8/11/2022 | JOHN JANSON |
| CofO Issued | 8/11/2022 | JOHN JANSON |
| Permit Finaled | 8/11/2022 | JOHN JANSON |
Permit Application Clearance Information
| Construction within easement | Cleared | 10/18/2019 | RIDWAN HARDY |
| Address approval | Cleared | 11/19/2019 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 11/19/2019 | LEE GUILBEAUX |
| Sewer availability | Cleared | 11/19/2019 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 11/19/2019 | LEE GUILBEAUX |
| Grading Pre-Inspection | Cleared | 1/26/2022 | PATRICK MISCHLICH |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/23/2022 | Not Ready for Inspection | PETER FOLLING |
| Deputy Drilled-In Anchors | 4/4/2022 | Approved | PETER FOLLING |
| Footing/Foundation/Slab | 4/4/2022 | Approved | PETER FOLLING |
| ELECTRICAL-Rough | 4/21/2022 | Not Ready for Inspection | PETER FOLLING |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2022 | Approved | PETER FOLLING |
| Green Building Rough | 4/21/2022 | Not Ready for Inspection | PETER FOLLING |
| PLUMBING-Rough | 4/21/2022 | Corrections Issued | PETER FOLLING |
| ELECTRICAL-Rough | 5/2/2022 | Approved | PETER FOLLING |
| HVAC-Rough | 5/2/2022 | Approved | PETER FOLLING |
| Interior/Exterior Lathing | 5/2/2022 | Partial Approval | PETER FOLLING |
| PLUMBING-Rough | 5/2/2022 | Approved | PETER FOLLING |
| BUILDING-Rough-Frame | 5/4/2022 | Approved | PETER FOLLING |
| Drywall Nailing | 5/4/2022 | Approved | PETER FOLLING |
| Green Building Rough | 5/4/2022 | Approved | PETER FOLLING |
| Interior/Exterior Lathing | 5/4/2022 | Approved | PETER FOLLING |
| Shower Pan | 5/4/2022 | Approved | PETER FOLLING |
| Final | 5/10/2022 | Not Ready for Inspection | PETER FOLLING |
| Green Building Final | 5/10/2022 | Not Ready for Inspection | PETER FOLLING |
| SGSOV-Seismic Gas S/O Valve | 5/10/2022 | SGSOV Not Ready | PETER FOLLING |
| Smoke Detectors | 5/10/2022 | Not Ready for Inspection | PETER FOLLING |
| Final | 5/16/2022 | Not Ready for Inspection | PETER FOLLING |
| SGSOV-Seismic Gas S/O Valve | 5/23/2022 | SGSOV Not Ready | PETER FOLLING |
| Final | 6/30/2022 | Corrections Issued | PETER FOLLING |
| Green Building Final | 6/30/2022 | Approved | PETER FOLLING |
| SGSOV-Seismic Gas S/O Valve | 6/30/2022 | SGSOV Approved | PETER FOLLING |
| Smoke Detectors | 6/30/2022 | Approved | PETER FOLLING |
| Final | 7/12/2022 | Not Ready for Inspection | PETER FOLLING |
| Final | 7/22/2022 | OK to Issue CofO | PETER FOLLING |