11594 W CUMPSTON ST 91601
Certificate Information: 11594 W CUMPSTON ST 91601
- Application / Permit
- 19016-20000-08791
- Plan Check / Job No.
- B19VN04848
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 18'-3" X 8'-6" ADDITION TO AND CONVERT EXISTING DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 & SB 229
- Permit Issued
- Issued on 1/16/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/9/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/27/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 3/28/2019 | JEROME MAGAT PALMA |
| Corrections Issued | 3/29/2019 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 4/3/2019 | APPLICANT |
| Plan Check Approved | 1/16/2020 | JEROME MAGAT PALMA |
| Issued | 1/16/2020 | LADBS |
| CofO in Progress | 6/20/2020 | DANIEL ORRANTE |
| CofO in Progress | 7/9/2020 | DANIEL ORRANTE |
| Permit Finaled | 7/9/2020 | MICHAEL SMITH |
| CofO Issued | 7/9/2020 | MICHAEL SMITH |
| Permit Finaled | 7/9/2020 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 5/2/2019 | JOSHUA DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/2/2019 | JOSHUA DIAZ |
| Roof/Waste drainage to street | Cleared | 5/2/2019 | JOSHUA DIAZ |
| Sewer availability | Cleared | 5/2/2019 | JOSHUA DIAZ |
| Construction near power lines | Cleared | 1/7/2020 | RIDWAN HARDY |
Contact Information
| Contractor | Future Home Builders Inc; Lic. No.: 870227-B | 6860 CANBY AVE #111 RESEDA, CA 91335 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/24/2020 | No Access for Inspection | JEFFREY PARD |
| PLUMBING-Rough | 2/24/2020 | No Access for Inspection | JEFFREY PARD |
| Excavation/Setback/Form/Re-Bar | 2/25/2020 | Not Ready for Inspection | JEFFREY PARD |
| PLUMBING-Rough | 2/25/2020 | Not Ready for Inspection | JEFFREY PARD |
| Footing/Foundation/Slab | 2/28/2020 | Approved | JEFFREY PARD |
| PLUMBING-Rough | 2/28/2020 | Partial Approval | JEFFREY PARD |
| Underground Mechanical | 2/28/2020 | Partial Approval | JEFFREY PARD |
| Floor/Roof Diaphrgm/Shear Wall | 3/27/2020 | Not Ready for Inspection | JEFFREY PARD |
| BUILDING-Rough-Frame | 3/31/2020 | Approved | JEFFREY PARD |
| ELECTRICAL-Rough | 3/31/2020 | Approved | JEFFREY PARD |
| Green Building Rough | 3/31/2020 | Approved | JEFFREY PARD |
| HVAC-Rough | 3/31/2020 | Not Ready for Inspection | JEFFREY PARD |
| MERV13>=Rough | 3/31/2020 | Approved | JEFFREY PARD |
| PLUMBING-Rough | 3/31/2020 | Approved | JEFFREY PARD |
| Insulation | 4/3/2020 | Not Ready for Inspection | JEFFREY PARD |
| Interior/Exterior Lathing | 4/3/2020 | Not Ready for Inspection | JEFFREY PARD |
| Interior/Exterior Lathing | 4/6/2020 | Corrections Issued | JEFFREY PARD |
| Special/Order Compliance | 4/6/2020 | Approved | GREGG CUMMINGS |
| Insulation | 4/13/2020 | Approved | JEFFREY PARD |
| Interior/Exterior Lathing | 4/13/2020 | Not Ready for Inspection | JEFFREY PARD |
| Special/Order Compliance | 4/13/2020 | Approved | GREGG CUMMINGS |
| Drywall Nailing | 4/22/2020 | Approved | JEFFREY PARD |
| Interior/Exterior Lathing | 4/22/2020 | Approved | JEFFREY PARD |
| Service/Power Release | 5/12/2020 | Partial Inspection | THOMAS FINNILA |
| Final | 5/26/2020 | Corrections Issued | JEFFREY PARD |
| Green Building Final | 5/26/2020 | Approved | JEFFREY PARD |
| MERV13>=Final | 5/26/2020 | Approved | JEFFREY PARD |
| SGSOV-Seismic Gas S/O Valve | 5/26/2020 | SGSOV Approved | JEFFREY PARD |
| Smoke Detectors | 5/26/2020 | Approved | JEFFREY PARD |
| Final | 6/2/2020 | OK to Issue CofO | JEFFREY PARD |