11594 W CUMPSTON ST 91601

Certificate Information: 11594 W CUMPSTON ST 91601

Application / Permit
19016-20000-08791
Plan Check / Job No.
B19VN04848
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
18'-3" X 8'-6" ADDITION TO AND CONVERT EXISTING DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 & SB 229
Permit Issued
Issued on 1/16/2020
Issuing Office
Valley
Current Status
CofO Issued on 7/9/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/27/2019 APPLICANT
Assigned to Plan Check Engineer 3/28/2019 JEROME MAGAT PALMA
Corrections Issued 3/29/2019 JEROME MAGAT PALMA
Building Plans Picked Up 4/3/2019 APPLICANT
Plan Check Approved 1/16/2020 JEROME MAGAT PALMA
Issued 1/16/2020 LADBS
CofO in Progress 6/20/2020 DANIEL ORRANTE
CofO in Progress 7/9/2020 DANIEL ORRANTE
Permit Finaled 7/9/2020 MICHAEL SMITH
CofO Issued 7/9/2020 MICHAEL SMITH
Permit Finaled 7/9/2020 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 5/2/2019 JOSHUA DIAZ
Eng Process Fee Ord 176,300 Cleared 5/2/2019 JOSHUA DIAZ
Roof/Waste drainage to street Cleared 5/2/2019 JOSHUA DIAZ
Sewer availability Cleared 5/2/2019 JOSHUA DIAZ
Construction near power lines Cleared 1/7/2020 RIDWAN HARDY

Contact Information

Contractor Future Home Builders Inc; Lic. No.: 870227-B 6860 CANBY AVE #111      RESEDA, CA 91335

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/24/2020 No Access for Inspection JEFFREY PARD
PLUMBING-Rough 2/24/2020 No Access for Inspection JEFFREY PARD
Excavation/Setback/Form/Re-Bar 2/25/2020 Not Ready for Inspection JEFFREY PARD
PLUMBING-Rough 2/25/2020 Not Ready for Inspection JEFFREY PARD
Footing/Foundation/Slab 2/28/2020 Approved JEFFREY PARD
PLUMBING-Rough 2/28/2020 Partial Approval JEFFREY PARD
Underground Mechanical 2/28/2020 Partial Approval JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 3/27/2020 Not Ready for Inspection JEFFREY PARD
BUILDING-Rough-Frame 3/31/2020 Approved JEFFREY PARD
ELECTRICAL-Rough 3/31/2020 Approved JEFFREY PARD
Green Building Rough 3/31/2020 Approved JEFFREY PARD
HVAC-Rough 3/31/2020 Not Ready for Inspection JEFFREY PARD
MERV13>=Rough 3/31/2020 Approved JEFFREY PARD
PLUMBING-Rough 3/31/2020 Approved JEFFREY PARD
Insulation 4/3/2020 Not Ready for Inspection JEFFREY PARD
Interior/Exterior Lathing 4/3/2020 Not Ready for Inspection JEFFREY PARD
Interior/Exterior Lathing 4/6/2020 Corrections Issued JEFFREY PARD
Special/Order Compliance 4/6/2020 Approved GREGG CUMMINGS
Insulation 4/13/2020 Approved JEFFREY PARD
Interior/Exterior Lathing 4/13/2020 Not Ready for Inspection JEFFREY PARD
Special/Order Compliance 4/13/2020 Approved GREGG CUMMINGS
Drywall Nailing 4/22/2020 Approved JEFFREY PARD
Interior/Exterior Lathing 4/22/2020 Approved JEFFREY PARD
Service/Power Release 5/12/2020 Partial Inspection THOMAS FINNILA
Final 5/26/2020 Corrections Issued JEFFREY PARD
Green Building Final 5/26/2020 Approved JEFFREY PARD
MERV13>=Final 5/26/2020 Approved JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 5/26/2020 SGSOV Approved JEFFREY PARD
Smoke Detectors 5/26/2020 Approved JEFFREY PARD
Final 6/2/2020 OK to Issue CofO JEFFREY PARD