11723 W PENDLETON ST 91352

Certificate Information: 11723 W PENDLETON ST 91352

Application / Permit
19016-20000-08591
Plan Check / Job No.
B19VN04749
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 40' X 20' 2-STORY RECREATION ROOM & GARAGE TO ACCESSORY DWELLING UNIT PER AB494 AND SB229
Permit Issued
Issued on 1/17/2020
Issuing Office
Valley
Current Status
CofO Issued on 1/29/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/26/2019 APPLICANT
Assigned to Plan Check Engineer 4/25/2019 ROSENDO MEDINA
Green Plans Picked Up 4/26/2019 APPLICANT
Corrections Issued 4/30/2019 ROSENDO MEDINA
Quality Review Completed 5/3/2019 OMID HEDAYAT
Building Plans Picked Up 5/8/2019 APPLICANT
Applicant returned to address corrections 11/7/2019 ROSENDO MEDINA
Plan Check Approved 1/17/2020 ROSENDO MEDINA
Issued 1/17/2020 LADBS
CofO in Progress 12/2/2021 CHRISTOPHER DELLEFIELD
No Progress 1/15/2022 MICHAEL SMITH
CofO in Progress 1/29/2022 MICHAEL SMITH
CofO Issued 1/29/2022 MICHAEL SMITH
Permit Finaled 1/29/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 11/7/2019 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 11/7/2019 ADRIAN CASTRO
Permit Cleared 11/7/2019 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 11/7/2019 ADRIAN CASTRO
Sewer availability Cleared 11/7/2019 ADRIAN CASTRO
Green Code Cleared 1/15/2020 MICHAEL AYERS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/28/2020 Not Ready for Inspection JOHN HAYES
Excavation/Setback/Form/Re-Bar 4/29/2020 Not Ready for Inspection JOHN HAYES
Footing/Foundation/Slab 4/29/2020 Not Ready for Inspection JOHN HAYES
Footing/Foundation/Slab 5/11/2020 Approved JOHN HAYES
Wood Frame 9/3/2020 Not Ready for Inspection MATTHEW NELSON
PLUMBING-Rough 10/14/2020 Approved JOHN HAYES
Underground Mechanical 10/14/2020 Approved JOHN HAYES
ELECTRICAL-Rough 11/5/2020 Not Ready for Inspection JOHN HAYES
ELECTRICAL-Rough 11/13/2020 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 1/25/2021 Approved JOHN HAYES
ELECTRICAL-Rough 1/25/2021 Approved JOHN HAYES
Green Building Rough 1/25/2021 Approved JOHN HAYES
MERV13>=Rough 1/25/2021 Approved JOHN HAYES
Rough-Elec/Plmb/HVAC 1/25/2021 Approved JOHN HAYES
Insulation 3/4/2021 Approved JOHN HAYES
Shower Pan 3/4/2021 Approved JOHN HAYES
Drywall Nailing 4/1/2021 Approved JOHN HAYES
ELECTRICAL-Final 10/20/2021 Corrections Issued CHRISTOPHER DELLEFIELD
Final 10/20/2021 Corrections Issued CHRISTOPHER DELLEFIELD
Green Building Final 10/20/2021 Corrections Issued CHRISTOPHER DELLEFIELD
HVAC-Final 10/20/2021 Corrections Issued CHRISTOPHER DELLEFIELD
MERV13>=Final 10/20/2021 Not Ready for Inspection CHRISTOPHER DELLEFIELD
PLUMBING-Final 10/20/2021 Corrections Issued CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 10/20/2021 SGSOV Not Ready CHRISTOPHER DELLEFIELD
Smoke Detectors 10/20/2021 Corrections Issued CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 11/15/2021 Corrections Issued CHRISTOPHER DELLEFIELD
Final 11/15/2021 Corrections Issued CHRISTOPHER DELLEFIELD
Green Building Final 11/15/2021 Approved CHRISTOPHER DELLEFIELD
HVAC-Final 11/15/2021 Approved CHRISTOPHER DELLEFIELD
MERV13>=Final 11/15/2021 Approved CHRISTOPHER DELLEFIELD
PLUMBING-Final 11/15/2021 Corrections Issued CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 11/15/2021 SGSOV Approved CHRISTOPHER DELLEFIELD
Smoke Detectors 11/15/2021 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 12/2/2021 Approved CHRISTOPHER DELLEFIELD
Final 12/2/2021 OK to Issue CofO CHRISTOPHER DELLEFIELD
PLUMBING-Final 12/2/2021 Approved CHRISTOPHER DELLEFIELD