11723 W PENDLETON ST 91352
Certificate Information: 11723 W PENDLETON ST 91352
- Application / Permit
- 19016-20000-08591
- Plan Check / Job No.
- B19VN04749
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 40' X 20' 2-STORY RECREATION ROOM & GARAGE TO ACCESSORY DWELLING UNIT PER AB494 AND SB229
- Permit Issued
- Issued on 1/17/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/29/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/26/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 4/25/2019 | ROSENDO MEDINA |
| Green Plans Picked Up | 4/26/2019 | APPLICANT |
| Corrections Issued | 4/30/2019 | ROSENDO MEDINA |
| Quality Review Completed | 5/3/2019 | OMID HEDAYAT |
| Building Plans Picked Up | 5/8/2019 | APPLICANT |
| Applicant returned to address corrections | 11/7/2019 | ROSENDO MEDINA |
| Plan Check Approved | 1/17/2020 | ROSENDO MEDINA |
| Issued | 1/17/2020 | LADBS |
| CofO in Progress | 12/2/2021 | CHRISTOPHER DELLEFIELD |
| No Progress | 1/15/2022 | MICHAEL SMITH |
| CofO in Progress | 1/29/2022 | MICHAEL SMITH |
| CofO Issued | 1/29/2022 | MICHAEL SMITH |
| Permit Finaled | 1/29/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 11/7/2019 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 11/7/2019 | ADRIAN CASTRO |
| Permit | Cleared | 11/7/2019 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 11/7/2019 | ADRIAN CASTRO |
| Sewer availability | Cleared | 11/7/2019 | ADRIAN CASTRO |
| Green Code | Cleared | 1/15/2020 | MICHAEL AYERS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/28/2020 | Not Ready for Inspection | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 4/29/2020 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 4/29/2020 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 5/11/2020 | Approved | JOHN HAYES |
| Wood Frame | 9/3/2020 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 10/14/2020 | Approved | JOHN HAYES |
| Underground Mechanical | 10/14/2020 | Approved | JOHN HAYES |
| ELECTRICAL-Rough | 11/5/2020 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Rough | 11/13/2020 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 1/25/2021 | Approved | JOHN HAYES |
| ELECTRICAL-Rough | 1/25/2021 | Approved | JOHN HAYES |
| Green Building Rough | 1/25/2021 | Approved | JOHN HAYES |
| MERV13>=Rough | 1/25/2021 | Approved | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 1/25/2021 | Approved | JOHN HAYES |
| Insulation | 3/4/2021 | Approved | JOHN HAYES |
| Shower Pan | 3/4/2021 | Approved | JOHN HAYES |
| Drywall Nailing | 4/1/2021 | Approved | JOHN HAYES |
| ELECTRICAL-Final | 10/20/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Final | 10/20/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Green Building Final | 10/20/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 10/20/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| MERV13>=Final | 10/20/2021 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 10/20/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 10/20/2021 | SGSOV Not Ready | CHRISTOPHER DELLEFIELD |
| Smoke Detectors | 10/20/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 11/15/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Final | 11/15/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Green Building Final | 11/15/2021 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 11/15/2021 | Approved | CHRISTOPHER DELLEFIELD |
| MERV13>=Final | 11/15/2021 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 11/15/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 11/15/2021 | SGSOV Approved | CHRISTOPHER DELLEFIELD |
| Smoke Detectors | 11/15/2021 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 12/2/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 12/2/2021 | OK to Issue CofO | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 12/2/2021 | Approved | CHRISTOPHER DELLEFIELD |