9672 N SANDUSKY AVE 91331
Certificate Information: 9672 N SANDUSKY AVE 91331
- Application / Permit
- 19016-20000-07740
- Plan Check / Job No.
- B19VN04308
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 18' X 20' DETACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK PER WFPP.
- Permit Issued
- Issued on 5/25/2021
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/25/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/19/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 3/27/2019 | JENNIFER LEE |
| Corrections Issued | 3/27/2019 | JENNIFER LEE |
| Applicant returned to address corrections | 3/30/2021 | TSE MING HUANG |
| Applicant returned to address corrections | 4/1/2021 | TSE MING HUANG |
| Plan Check Approved | 5/4/2021 | TSE MING HUANG |
| Building Plans Picked Up | 5/11/2021 | APPLICANT |
| Issued | 5/25/2021 | APPLICANT |
| CofO in Progress | 8/19/2021 | JENNIFER RABUCHIN |
| CofO Issued | 9/25/2021 | MICHAEL SMITH |
| Permit Finaled | 9/25/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 6/10/2019 | RIDWAN HARDY |
| Address approval | Cleared | 2/26/2021 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 2/26/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 2/26/2021 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| SGSOV-Seismic Gas S/O Valve | 6/21/2021 | SGSOV Not Ready | ARTHUR SARGSYAN |
| Sewer | 6/21/2021 | Approved | ARTHUR SARGSYAN |
| Underground Mechanical | 6/21/2021 | Approved | ARTHUR SARGSYAN |
| Deputy Drilled-In Anchors | 6/24/2021 | No Access for Inspection | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 6/28/2021 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 7/12/2021 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/12/2021 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 7/12/2021 | Partial Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 7/12/2021 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 7/15/2021 | Approved | MICHEL ABAJAN |
| Green Building Rough | 7/15/2021 | Approved | MICHEL ABAJAN |
| Insulation | 7/19/2021 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 7/19/2021 | Partial Approval | AMY COLIN |
| Drywall Nailing | 7/23/2021 | Approved | ALAN MORELOS |
| Interior/Exterior Lathing | 7/23/2021 | Approved | ALAN MORELOS |
| ELECTRICAL-Final | 8/16/2021 | Approved | JENNIFER RABUCHIN |
| Final | 8/16/2021 | OK to Issue CofO | JENNIFER RABUCHIN |
| Green Building Final | 8/16/2021 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 8/16/2021 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 8/16/2021 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 8/16/2021 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 8/16/2021 | Approved | JENNIFER RABUCHIN |