1828 E CESAR E CHAVEZ AVE #6300-6400 90033

Certificate Information: 1828 E CESAR E CHAVEZ AVE #6300-6400 90033

Application / Permit
19016-20000-07254
Plan Check / Job No.
B19VN04064
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Medical Clinic
Work Description
CHANGE OF USE FROM EX. MEDICAL OFFICE (3763 SF) TO MEDICAL CLINIC. CREATE A DEMISING WALL TO CREATE (2) MEDICAL CLINICS.
Permit Issued
Issued on 5/27/2020
Issuing Office
Current Status
CofO Issued on 3/12/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/14/2019 APPLICANT
Assigned to Plan Check Engineer 3/21/2019 JEFFREY TANGONAN
Disabled Access Plans Picked Up 3/26/2019 APPLICANT
Corrections Issued 3/28/2019 JEFFREY TANGONAN
Quality Review Completed 3/28/2019 STEVEN KIM
Building Plans Picked Up 3/28/2019 APPLICANT
Plan Check Approved 4/16/2019 JEFFREY TANGONAN
Issued 5/27/2020 APPLICANT
CofO in Progress 3/12/2021 DAVID TSAU
CofO Issued 3/12/2021 DAVID TSAU
Permit Finaled 3/12/2021 DAVID TSAU

Permit Application Clearance Information

DAS Clearance Cleared 4/5/2019 NORLITO MEDRANO
ZA Case Cleared 4/5/2019 RICK TORRES
Eng Process Fee Ord 176,300 Cleared 4/16/2019 APEKSHYA BAJRACHARYA
Sewer availability Cleared 4/16/2019 APEKSHYA BAJRACHARYA
Project located in CRA area Cleared 5/2/2019 JIM URQUHART
Comm Cor/Mini-Mall Cleared 10/8/2019 HERMINIGILDO AGUSTIN

Contact Information

Architect Dong,, Heney; Lic. No.: C9770 22900 VENTURA BLVD #120      WOODLAND HILLS, CA 91364
Contractor D & H Building Systems Inc; Lic. No.: 747803-B 1322 BELL AVE #1-F      TUSTIN, CA 92780

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Wood Frame 7/2/2020 Conditional Approval LANNY MERRICK
Wood Frame 7/7/2020 Approved LANNY MERRICK
Drywall Nailing 7/16/2020 Partial Inspection RONALD PACHECO
Drywall Nailing 7/17/2020 Partial Approval LANNY MERRICK
Partition/T-Bar Ceiling 9/24/2020 Conditional Approval LANNY MERRICK
T-Bar Ceiling 9/24/2020 Conditional Approval LANNY MERRICK
Final 11/9/2020 Conditional Approval LANNY MERRICK
Reinforced Masonry Frame 11/9/2020 Approved LANNY MERRICK
SGSOV-Seismic Gas S/O Valve 11/9/2020 SGSOV Approved LANNY MERRICK
Smoke Detectors 11/9/2020 Approved LANNY MERRICK
Final 2/11/2021 Conditional Approval RONALD PACHECO