2974 N SUNNYNOOK DR 90039

Certificate Information: 2974 N SUNNYNOOK DR 90039

Application / Permit
19016-20000-07153
Plan Check / Job No.
B19VN04008
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) IRREGULAR 23' X 28' DETACHED GARAGE/STORAGE TO (N) ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK PER DESIGN.
Permit Issued
Issued on 10/11/2019
Issuing Office
Valley
Current Status
CofO Issued on 6/20/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/13/2019 APPLICANT
Assigned to Plan Check Engineer 3/13/2019 RAPHAEL ROSAS
Corrections Issued 3/13/2019 RAPHAEL ROSAS
Plan Check Approved 10/8/2019 JENNIFER LEE
Issued 10/11/2019 LADBS
CofO in Progress 6/16/2020 HAMIK HARTOUNIAN
Permit Finaled 6/20/2020 DEROLD HAUFF
CofO Issued 6/20/2020 DEROLD HAUFF
Permit Finaled 6/20/2020 DEROLD HAUFF

Permit Application Clearance Information

Miscellaneous Cleared 9/25/2019 DALE WILLIAMS
Address approval Cleared 10/2/2019 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 10/2/2019 ADRIAN CASTRO
Sewer availability Cleared 10/2/2019 ADRIAN CASTRO

Contact Information

Architect Dembsky,, Amit; Lic. No.: C30383 5739 KANAN ROAD # 133      AGOURA HILLS, CA 91301
Contractor Pearl Remodeling; Lic. No.: 955824-B 6803 YARMOUTH AVENUE      RESEDA, CA 91335

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/7/2019 Approved HAMIK HARTOUNIAN
Pre-Inspection 11/25/2019 Approved HAMIK HARTOUNIAN
Underground Mechanical 12/5/2019 Partial Approval HAMIK HARTOUNIAN
Deputy Drilled-In Anchors 12/10/2019 Conditional Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 12/13/2019 Approved HAMIK HARTOUNIAN
Sewer 12/19/2019 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 1/8/2020 Not Ready for Inspection HAMIK HARTOUNIAN
HVAC-Rough 1/8/2020 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 1/8/2020 Conditional Approval HAMIK HARTOUNIAN
ELECTRICAL-Rough 1/16/2020 Conditional Approval HAMIK HARTOUNIAN
PLUMBING-Rough 1/16/2020 Conditional Approval HAMIK HARTOUNIAN
Green Building Rough 1/27/2020 Approved SCOTT FINNILA
MERV13>=Rough 1/27/2020 Approved SCOTT FINNILA
Rough-Elec/Plmb/HVAC 1/27/2020 Corrections Issued SCOTT FINNILA
Wood Frame 1/27/2020 Corrections Issued SCOTT FINNILA
ELECTRICAL-Rough 1/30/2020 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Rough 1/30/2020 Approved HAMIK HARTOUNIAN
Wood Frame 2/5/2020 Partial Approval HAMIK HARTOUNIAN
ELECTRICAL-Rough 2/10/2020 Corrections Issued HAMIK HARTOUNIAN
Insulation 2/10/2020 Conditional Approval HAMIK HARTOUNIAN
Interior/Exterior Lathing 2/10/2020 Partial Approval HAMIK HARTOUNIAN
Wood Frame 2/10/2020 Conditional Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 3/18/2020 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 3/18/2020 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 3/18/2020 Approved HAMIK HARTOUNIAN
Wood Frame 3/18/2020 Approved HAMIK HARTOUNIAN
Drywall Nailing 3/23/2020 Approved CHRISTOPHER DELLEFIELD
Final 6/3/2020 Corrections Issued HAMIK HARTOUNIAN
Gas Test 6/3/2020 Approved HAMIK HARTOUNIAN
Green Building Final 6/3/2020 Corrections Issued HAMIK HARTOUNIAN
MERV13>=Final 6/3/2020 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 6/3/2020 SGSOV Not Ready HAMIK HARTOUNIAN
Smoke Detectors 6/3/2020 Approved HAMIK HARTOUNIAN
Final 6/10/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Green Building Final 6/10/2020 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 6/10/2020 SGSOV Approved HAMIK HARTOUNIAN
Final 6/15/2020 OK to Issue CofO HAMIK HARTOUNIAN