3958 S EAST BLVD 90066

Certificate Information: 3958 S EAST BLVD 90066

Application / Permit
19016-20000-07099
Plan Check / Job No.
B19VN03949
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE (49'-6" X 42') INTO (N) ACCESSORY DWELLING UNIT PER AB 494 & SB 229, ALL WORK PER WFPP
Permit Issued
Issued on 10/7/2019
Issuing Office
San Pedro
Current Status
CofO Issued on 1/25/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/13/2019 APPLICANT
Assigned to Plan Check Engineer 3/13/2019 NILOOFAR MEHRAIN
Corrections Issued 3/13/2019 NILOOFAR MEHRAIN
Plan Check Approved 8/1/2019 RARES BODEA
Issued 10/7/2019 LADBS
CofO in Progress 1/6/2021 ENRIQUE MIRELES
CofO Issued 1/25/2021 VINCENT COTTON
Permit Finaled 1/25/2021 VINCENT COTTON

Permit Application Clearance Information

Address approval Cleared 3/13/2019 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 3/13/2019 LEE GUILBEAUX
Sewer availability Cleared 3/13/2019 LEE GUILBEAUX
CPC Cleared 5/2/2019 SHEILA GERSHON
Eng Process Fee Ord 176,300 Cleared 5/2/2019 JOHN LIN
Hydrant and Access approval Cleared 6/17/2019 GEORGE SUCHAND
Construction near power lines Cleared 7/30/2019 RIDWAN HARDY
Construction within easement Cleared 7/30/2019 RIDWAN HARDY

Contact Information

Contractor Gaudenti & Sons Corporation; Lic. No.: 283650-B 231 VISTA DEL MAR      REDONDO BEACH, CA 90277

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 10/15/2019 Corrections Issued JOHNNY MIRANDA
Underground Mechanical 10/17/2019 Partial Approval KENNETH NAGLE
HVAC-Rough 2/4/2020 Corrections Issued JOHNNY MIRANDA
BUILDING-Rough-Frame 3/3/2020 Corrections Issued DAVID FEILER
ELECTRICAL-Rough 3/3/2020 Not Ready for Inspection DAVID FEILER
Green Building Rough 3/3/2020 Not Ready for Inspection DAVID FEILER
HVAC-Rough 3/3/2020 Not Ready for Inspection DAVID FEILER
BUILDING-Rough-Frame 3/10/2020 Not Ready for Inspection JUAN VALENZUELA
ELECTRICAL-Rough 3/10/2020 Corrections Issued JUAN VALENZUELA
Green Building Rough 3/10/2020 Not Ready for Inspection JUAN VALENZUELA
HVAC-Rough 3/10/2020 Corrections Issued JUAN VALENZUELA
PLUMBING-Rough 3/11/2020 Corrections Issued DAVID FEILER
PLUMBING-Rough 3/12/2020 Approved DAVID FEILER
BUILDING-Rough-Frame 3/16/2020 Not Ready for Inspection DAVID FEILER
ELECTRICAL-Final 3/16/2020 Not Ready for Inspection DAVID FEILER
Green Building Rough 3/16/2020 Not Ready for Inspection DAVID FEILER
HVAC-Final 3/16/2020 Not Ready for Inspection DAVID FEILER
BUILDING-Rough-Frame 3/25/2020 Not Ready for Inspection CRAIG DAVIS
ELECTRICAL-Rough 3/25/2020 Corrections Issued CRAIG DAVIS
Green Building Rough 3/25/2020 Not Ready for Inspection CRAIG DAVIS
HVAC-Rough 3/25/2020 Corrections Issued CRAIG DAVIS
Interior/Exterior Lathing 4/8/2020 Corrections Issued DAVID FEILER
Interior/Exterior Lathing 4/13/2020 Partial Approval JOHNNY MIRANDA
BUILDING-Rough-Frame 7/10/2020 Corrections Issued CRAIG DAVIS
Green Building Rough 7/10/2020 Partial Approval CRAIG DAVIS
BUILDING-Rough-Frame 7/16/2020 Partial Approval JOHNNY MIRANDA
ELECTRICAL-Rough 7/16/2020 Approved JOHNNY MIRANDA
Green Building Rough 7/16/2020 Not Ready for Inspection JOHNNY MIRANDA
HVAC-Rough 7/16/2020 Approved JOHNNY MIRANDA
Insulation 7/20/2020 Approved DAVID HEINE
Drywall Nailing 7/31/2020 Not Ready for Inspection JOHNNY MIRANDA
Drywall Nailing 8/4/2020 Corrections Issued CRAIG DAVIS
BUILDING-Rough-Frame 8/5/2020 Approved CRAIG DAVIS
Drywall Nailing 8/5/2020 Approved CRAIG DAVIS
Green Building Rough 8/5/2020 Approved CRAIG DAVIS
Interior/Exterior Lathing 8/11/2020 Approved CRAIG DAVIS
HVAC-Final 12/2/2020 Not Ready for Inspection ENRIQUE MIRELES
ELECTRICAL-Final 12/17/2020 Approved ENRIQUE MIRELES
Final 12/17/2020 Corrections Issued ENRIQUE MIRELES
HVAC-Final 12/17/2020 Approved ENRIQUE MIRELES
PLUMBING-Final 12/17/2020 Approved ENRIQUE MIRELES
ELECTRICAL-Final 12/21/2020 Approved ENRIQUE MIRELES
Final 12/21/2020 Corrections Issued ENRIQUE MIRELES
HVAC-Final 12/21/2020 Approved ENRIQUE MIRELES
PLUMBING-Final 12/21/2020 Approved ENRIQUE MIRELES
Final 1/6/2021 OK to Issue CofO ENRIQUE MIRELES
Green Building Final 1/6/2021 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 1/6/2021 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 1/6/2021 Approved ENRIQUE MIRELES
Service/Power Release 1/8/2021 Approved ENRIQUE MIRELES