5181-5183 N CANOGA AVE 91364
Certificate Information: 5181-5183 N CANOGA AVE 91364
- Application / Permit
- 19016-20000-06757
- Plan Check / Job No.
- B19VN03796
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT ATTACHED 1-CAR GARAGE & PORTION OF SFD INTO A (N) 35'-8" X 14'-6" IRREGULAR SHAPED ATTACHED ACCESSORY DWELLING UNIT PER AB 494 & SB 229. ALL WORK PER WFPP
- Permit Issued
- Issued on 3/26/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/17/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/11/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 3/11/2019 | RAPHAEL ROSAS |
| Corrections Issued | 3/11/2019 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 3/18/2019 | MARVEL DELACRUZ |
| Plan Check Approved | 3/26/2019 | JENNIFER LEE |
| Issued | 3/26/2019 | LADBS |
| CofO in Progress | 6/30/2021 | PETER FOLLING |
| CofO Issued | 7/17/2021 | MICHAEL SMITH |
| Permit Finaled | 7/17/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 3/18/2019 | LEE GUILBEAUX |
| City Hist. Cultural Monument | Cleared | 3/18/2019 | RINA LARA |
| Eng Process Fee Ord 176,300 | Cleared | 3/18/2019 | LEE GUILBEAUX |
| Historic monument | Cleared | 3/18/2019 | RINA LARA |
| Sewer availability | Cleared | 3/18/2019 | LEE GUILBEAUX |
| ZI | Cleared | 3/18/2019 | RINA LARA |
| Grading Pre-Inspection | Cleared | 3/26/2019 | MARVEL DELACRUZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/23/2019 | Partial Inspection | JOSEPH SAGEN |
| Footing/Foundation/Slab | 5/28/2019 | Corrections Issued | JOSEPH SAGEN |
| BUILDING-Rough-Frame | 2/19/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| Final | 2/19/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| Green Building Final | 2/19/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| Green Building Rough | 2/19/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| SGSOV-Seismic Gas S/O Valve | 2/19/2020 | SGSOV Not Ready | DAVID STEPANYAN |
| Smoke Detectors | 2/19/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| Verify Sprinkler Sign Off | 2/19/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 5/15/2020 | Corrections Issued | MICHAEL TEMPLE |
| Final | 5/15/2020 | Not Ready for Inspection | MICHAEL TEMPLE |
| Green Building Final | 5/15/2020 | Not Ready for Inspection | MICHAEL TEMPLE |
| Green Building Rough | 5/15/2020 | Not Ready for Inspection | MICHAEL TEMPLE |
| SGSOV-Seismic Gas S/O Valve | 5/15/2020 | SGSOV Not Ready | MICHAEL TEMPLE |
| Smoke Detectors | 5/15/2020 | Not Ready for Inspection | MICHAEL TEMPLE |
| Verify Sprinkler Sign Off | 5/15/2020 | Not Ready for Inspection | MICHAEL TEMPLE |
| Special/Order Compliance | 1/12/2021 | Partial Inspection | PAUL CHOPP |
| Pre-Inspection | 1/27/2021 | Corrections Issued | PAUL CHOPP |
| Insulation | 5/5/2021 | Corrections Issued | STEPHANIE SWANSON |
| Pre-Inspection | 5/5/2021 | Partial Approval | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 5/11/2021 | Approved | DAVID SANDOVAL |
| Green Building Rough | 5/11/2021 | Approved | DAVID SANDOVAL |
| Insulation | 5/11/2021 | Approved | DAVID SANDOVAL |
| Rough-Elec/Plmb/HVAC | 5/11/2021 | Approved | DAVID SANDOVAL |
| Verify Sprinkler Sign Off | 5/11/2021 | Approved | DAVID SANDOVAL |
| Drywall Nailing | 5/17/2021 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 5/17/2021 | Corrections Issued | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 5/24/2021 | Approved | SHAVONNE ESPINOZA |
| ELECTRICAL-Final | 6/1/2021 | Corrections Issued | HENRY KIM |
| Final | 6/1/2021 | Corrections Issued | HENRY KIM |
| Green Building Final | 6/1/2021 | Approved | HENRY KIM |
| HVAC-Final | 6/1/2021 | Corrections Issued | HENRY KIM |
| PLUMBING-Final | 6/1/2021 | Corrections Issued | HENRY KIM |
| Smoke Detectors | 6/1/2021 | Corrections Issued | HENRY KIM |
| Pre-Inspection | 6/7/2021 | Not Ready for Inspection | PETER FOLLING |
| Final | 6/14/2021 | Not Ready for Inspection | PETER FOLLING |
| SGSOV-Seismic Gas S/O Valve | 6/14/2021 | SGSOV Not Ready | PETER FOLLING |
| Smoke Detectors | 6/14/2021 | Not Ready for Inspection | PETER FOLLING |
| Final | 6/25/2021 | OK to Issue CofO | PETER FOLLING |
| SGSOV-Seismic Gas S/O Valve | 6/25/2021 | SGSOV Approved | PETER FOLLING |
| Smoke Detectors | 6/25/2021 | Approved | PETER FOLLING |