7285-7287 N BERNADINE AVE 91307
Certificate Information: 7285-7287 N BERNADINE AVE 91307
- Application / Permit
- 19016-20000-06490
- Plan Check / Job No.
- B19VN03641
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT IRREGULAR 21'-10" X 25'-5" ATTACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK PER WFPP.
- Permit Issued
- Issued on 6/3/2020
- Issuing Office
- Current Status
- CofO Issued on 3/23/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/7/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 3/7/2019 | JENNIFER LEE |
| Corrections Issued | 3/8/2019 | JENNIFER LEE |
| Building Plans Picked Up | 3/12/2019 | APPLICANT |
| Applicant returned to address corrections | 4/19/2019 | JENNIFER LEE |
| Plan Check Approved | 6/3/2020 | JENNIFER LEE |
| Issued | 6/3/2020 | APPLICANT |
| CofO in Progress | 2/18/2022 | PETER FOLLING |
| CofO Issued | 3/23/2022 | JOHN JANSON |
| Permit Finaled | 3/23/2022 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 4/16/2019 | JOHN LIN |
| Eng Process Fee Ord 176,300 | Cleared | 4/16/2019 | JOHN LIN |
| Sewer availability | Cleared | 4/16/2019 | JOHN LIN |
| Grading Pre-Inspection | Cleared | 6/3/2020 | JENNIFER LEE |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 6/10/2020 | No Access for Inspection | DAVID STEPANYAN |
| Pre-Inspection | 6/10/2020 | Approved | DAVID STEPANYAN |
| Footing/Foundation/Slab | 7/20/2020 | Corrections Issued | DAVID STEPANYAN |
| PLUMBING-Rough | 7/20/2020 | Corrections Issued | DAVID STEPANYAN |
| Sewer | 7/20/2020 | Corrections Issued | DAVID STEPANYAN |
| Footing/Foundation/Slab | 7/27/2020 | Approved | DAVID STEPANYAN |
| PLUMBING-Rough | 7/27/2020 | Partial Approval | DAVID STEPANYAN |
| Sewer | 7/27/2020 | Corrections Issued | DAVID STEPANYAN |
| PLUMBING-Rough | 8/17/2020 | Partial Approval | DAVID STEPANYAN |
| Sewer | 8/17/2020 | Approved | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 10/2/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| ELECTRICAL-Rough | 10/2/2020 | Corrections Issued | DAVID STEPANYAN |
| Green Building Rough | 10/2/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| HVAC-Rough | 10/2/2020 | Corrections Issued | DAVID STEPANYAN |
| PLUMBING-Rough | 10/2/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| Insulation | 10/8/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| ELECTRICAL-Rough | 10/16/2020 | Approved | DAVID STEPANYAN |
| HVAC-Rough | 10/16/2020 | Approved | DAVID STEPANYAN |
| Insulation | 10/16/2020 | Partial Approval | DAVID STEPANYAN |
| PLUMBING-Rough | 10/16/2020 | Approved | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 10/19/2020 | Partial Approval | DAVID STEPANYAN |
| Green Building Rough | 10/19/2020 | Approved | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 10/26/2020 | Approved | DAVID STEPANYAN |
| Insulation | 10/26/2020 | Approved | DAVID STEPANYAN |
| Interior/Exterior Lathing | 10/26/2020 | Partial Approval | DAVID STEPANYAN |
| Drywall Nailing | 11/16/2020 | Approved | DAVID STEPANYAN |
| Interior/Exterior Lathing | 11/16/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| Interior/Exterior Lathing | 12/10/2020 | Approved | DAVID STEPANYAN |
| ELECTRICAL-Final | 1/11/2022 | Not Ready for Inspection | PETER FOLLING |
| Final | 1/11/2022 | Corrections Issued | PETER FOLLING |
| Green Building Final | 1/11/2022 | Not Ready for Inspection | PETER FOLLING |
| HVAC-Final | 1/11/2022 | Not Ready for Inspection | PETER FOLLING |
| PLUMBING-Final | 1/11/2022 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 1/11/2022 | SGSOV Approved | PETER FOLLING |
| Smoke Detectors | 1/11/2022 | Not Ready for Inspection | PETER FOLLING |
| ELECTRICAL-Final | 2/14/2022 | Not Ready for Inspection | PETER FOLLING |
| Final | 2/14/2022 | Not Ready for Inspection | PETER FOLLING |
| Green Building Final | 2/14/2022 | Approved | PETER FOLLING |
| HVAC-Final | 2/14/2022 | Approved | PETER FOLLING |
| PLUMBING-Final | 2/14/2022 | Approved | PETER FOLLING |
| Service/Power Release | 2/14/2022 | Not Ready for Inspection | PETER FOLLING |
| Smoke Detectors | 2/14/2022 | Approved | PETER FOLLING |
| ELECTRICAL-Final | 2/17/2022 | Approved | PETER FOLLING |
| Final | 2/17/2022 | OK to Issue CofO | PETER FOLLING |
| PLUMBING-Final | 2/17/2022 | Approved | PETER FOLLING |