11337-11339 N DRONFIELD AVE 91331
Certificate Information: 11337-11339 N DRONFIELD AVE 91331
- Application / Permit
- 19016-20000-04761
- Plan Check / Job No.
- B19VN02609
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT 20'-0" x 20'-0" (E) ATT. GARAGE INTO A NEW ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. WORK DONE PER WFPP.
- Permit Issued
- Issued on 2/20/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/14/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/20/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 2/20/2019 | SARKIS HARABEDIAN |
| Corrections Issued | 2/20/2019 | SARKIS HARABEDIAN |
| Plan Check Approved | 2/20/2019 | ANGELICA MARTINEZ |
| Issued | 2/20/2019 | LADBS |
| CofO in Progress | 1/16/2020 | MICHEL ABAJAN |
| Permit Finaled | 4/14/2020 | MICHAEL SMITH |
| CofO Issued | 4/14/2020 | MICHAEL SMITH |
| Permit Finaled | 4/14/2020 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 2/20/2019 | APEKSHYA BAJRACHARYA |
| Clean Up Green Up | Cleared | 2/20/2019 | TOM HENRY |
| Eng Process Fee Ord 176,300 | Cleared | 2/20/2019 | APEKSHYA BAJRACHARYA |
| Sewer availability | Cleared | 2/20/2019 | APEKSHYA BAJRACHARYA |
| ZA Case | Cleared | 2/20/2019 | TOM HENRY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/6/2019 | Approved | MICHEL ABAJAN |
| Green Building Rough | 5/9/2019 | Not Ready for Inspection | MICHEL ABAJAN |
| Pre-Inspection | 5/9/2019 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 6/18/2019 | Approved | MICHEL ABAJAN |
| Pre-Inspection | 6/18/2019 | Approved | MICHEL ABAJAN |
| Wood Frame | 6/18/2019 | Approved | MICHEL ABAJAN |
| Insulation | 7/1/2019 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 7/1/2019 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 7/8/2019 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 7/19/2019 | Approved | MICHEL ABAJAN |
| Final | 1/14/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| Green Building Final | 1/14/2020 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 1/14/2020 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 1/14/2020 | Approved | MICHEL ABAJAN |
| Final | 1/15/2020 | OK to Issue CofO | MICHEL ABAJAN |