6909 N NESTLE AVE 91335

Certificate Information: 6909 N NESTLE AVE 91335

Application / Permit
19016-20000-04205
Plan Check / Job No.
B19VN02339
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE AND REC ROOM TO NEW ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. WORK PER WFPP.
Permit Issued
Issued on 9/11/2019
Issuing Office
Metro
Current Status
CofO Issued on 9/8/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/13/2019 APPLICANT
Assigned to Plan Check Engineer 2/13/2019 JOHNNY WU
Corrections Issued 2/13/2019 JOHNNY WU
Building Plans Picked Up 2/15/2019 APPLICANT
Plan Check Approved 9/11/2019 JOHNNY WU
Issued 9/11/2019 LADBS
CofO in Progress 8/2/2025 ROBERT GOLD
Permit Finaled 9/8/2025 MICHAEL PELHAM
CofO Issued 9/8/2025 MICHAEL PELHAM
Permit Finaled 9/8/2025 MICHAEL PELHAM

Permit Application Clearance Information

Address approval Cleared 6/6/2019 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 6/6/2019 MARKOS PEREZ-BRAN
Sewer availability Cleared 6/6/2019 MARKOS PEREZ-BRAN
Construction near power lines Cleared 7/31/2019 RIDWAN HARDY

Contact Information

Contractor Ochoa Victor Manuel; Lic. No.: 908306-B 13700 FOOTHILL BLVD #920151      SYLMAR, CA 91342

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/17/2019 Corrections Issued DAVID SANDOVAL
Sewer 10/31/2019 Approved DAVID SANDOVAL
Underground Mechanical 10/31/2019 Partial Approval DAVID SANDOVAL
Footing/Foundation/Slab 11/25/2019 Corrections Issued DAVID SANDOVAL
Footing/Foundation/Slab 12/6/2019 Approved DAVID SANDOVAL
BUILDING-Rough-Frame 2/5/2020 Corrections Issued VINCENT HANLEY
ELECTRICAL-Rough 2/5/2020 Corrections Issued VINCENT HANLEY
HVAC-Rough 2/5/2020 Corrections Issued VINCENT HANLEY
PLUMBING-Rough 2/5/2020 Not Ready for Inspection VINCENT HANLEY
ELECTRICAL-Rough 2/10/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
PLUMBING-Rough 2/10/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 2/13/2020 Approved VINCENT HANLEY
ELECTRICAL-Rough 2/13/2020 Approved VINCENT HANLEY
PLUMBING-Rough 2/13/2020 Approved VINCENT HANLEY
Insulation 2/28/2020 Approved VINCENT HANLEY
Interior/Exterior Lathing 2/28/2020 Not Ready for Inspection VINCENT HANLEY
Drywall Nailing 3/10/2020 Approved VINCENT HANLEY
Interior/Exterior Lathing 3/10/2020 Partial Approval VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 5/22/2020 SGSOV Not Ready VINCENT HANLEY
Final 5/26/2020 Corrections Issued VINCENT HANLEY
ELECTRICAL-Final 5/29/2020 Corrections Issued VINCENT HANLEY
Final 5/29/2020 Not Ready for Inspection VINCENT HANLEY
HVAC-Final 5/29/2020 Approved VINCENT HANLEY
PLUMBING-Final 5/29/2020 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 5/29/2020 SGSOV Approved VINCENT HANLEY
Smoke Detectors 5/29/2020 Approved VINCENT HANLEY
Final 6/25/2020 Partial Inspection VINCENT HANLEY
Final 8/2/2025 OK to Issue CofO ROBERT GOLD