20730 W PRAIRIE ST 91311
Certificate Information: 20730 W PRAIRIE ST 91311
- Application / Permit
- 19016-20000-03279
- Plan Check / Job No.
- B19VN01785
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (12) Manufacturing
- Work Description
- TI & new exterior dock door Openings & main doors & Change of use from (e) MFG / Incidental Office to Warehouse & same incidental office, all works per engineer plans/details.
- Permit Issued
- Issued on 4/25/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/11/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/4/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 2/14/2019 | ABDUL CHEGENI |
| Corrections Issued | 2/19/2019 | ABDUL CHEGENI |
| Quality Review Completed | 2/21/2019 | STEVEN KIM |
| Building Plans Picked Up | 2/27/2019 | APPLICANT |
| Green Plans Picked Up | 2/27/2019 | APPLICANT |
| Disabled Access Plans Picked Up | 3/26/2019 | APPLICANT |
| Plan Check Approved | 4/10/2019 | ABDUL CHEGENI |
| Issued | 4/25/2019 | LADBS |
| TCO Issued (Expire Date: 05-24-2021) | 11/25/2020 | HENRY BAGHDASSARIAN |
| TCO Issued (Expire Date: 11-08-2021) | 5/12/2021 | JEFFREY DURAN |
| TCO Issued (Expire Date: 06-06-2022) | 12/8/2021 | JEFFREY DURAN |
| CofO in Progress | 1/7/2022 | JEFFREY FULTON |
| Permit Finaled | 1/11/2022 | JEFFREY DURAN |
| CofO Issued | 1/11/2022 | JEFFREY DURAN |
| Permit Finaled | 1/11/2022 | JEFFREY DURAN |
Permit Application Clearance Information
| Address approval | Cleared | 3/6/2019 | APEKSHYA BAJRACHARYA |
| Eng Process Fee Ord 176,300 | Cleared | 3/6/2019 | APEKSHYA BAJRACHARYA |
| Hydrant and Access approval | Cleared | 3/6/2019 | JOHN DALLAS |
| Sewer availability | Cleared | 3/6/2019 | APEKSHYA BAJRACHARYA |
| ZA Case | Cleared | 3/6/2019 | RINA LARA |
| ZA Case | Cleared | 3/6/2019 | RINA LARA |
| ZI | Cleared | 3/6/2019 | RINA LARA |
| ZI | Cleared | 3/6/2019 | RINA LARA |
| Metro Rail approval | Cleared | 3/18/2019 | ABDUL CHEGENI |
| Flood clearance | Cleared | 3/19/2019 | HENRY SISOMVANG |
| DAS Clearance | Cleared | 4/2/2019 | NORLITO MEDRANO |
| Green Code | Cleared | 4/4/2019 | MICHAEL AYERS |
Contact Information
| Architect | Coatsworth,, Calvin John; Lic. No.: C14388 | 2495 CAMPUS DRIVE SECOND FLOOR IRVINE, CA 92612 |
| Contractor | Xebec Building Company Inc; Lic. No.: 600621-B | 3010 OLD RANCH PARKWAY STE 470 SEAL BEACH, CA 90740 |
| Engineer | Bushra,, Rafeek L; Lic. No.: S4490 | 2564 W WOODLAND DR ANAHEIM, CA 92801 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/14/2019 | Approved | MILLARD ARDOIN |
| Deputy Steel/Welding | 6/14/2019 | Approved | MILLARD ARDOIN |
| Light Gage Steel Frame | 7/10/2019 | Partial Approval | MILLARD ARDOIN |
| Deputy Drilled-In Anchors | 7/15/2019 | Approved | MILLARD ARDOIN |
| Deputy Steel/Welding | 7/15/2019 | Approved | MILLARD ARDOIN |
| Structural Steel Frame | 7/15/2019 | Partial Inspection | MILLARD ARDOIN |
| Excavation/Setback/Form/Re-Bar | 8/20/2019 | Partial Approval | MILLARD ARDOIN |
| Footing/Foundation/Slab | 8/20/2019 | Partial Approval | MILLARD ARDOIN |
| Deputy Drilled-In Anchors | 8/22/2019 | Approved | MILLARD ARDOIN |
| Excavation/Setback/Form/Re-Bar | 9/4/2019 | Partial Approval | MILLARD ARDOIN |
| Deputy Reinf. Concrete | 9/12/2019 | Approved | MILLARD ARDOIN |
| Excavation/Setback/Form/Re-Bar | 9/12/2019 | Partial Approval | MILLARD ARDOIN |
| Excavation/Setback/Form/Re-Bar | 9/19/2019 | Partial Approval | MILLARD ARDOIN |
| Deputy Drilled-In Anchors | 9/25/2019 | Approved | MILLARD ARDOIN |
| Deputy Steel/Welding | 9/25/2019 | Approved | MILLARD ARDOIN |
| Excavation/Setback/Form/Re-Bar | 9/26/2019 | Partial Approval | MILLARD ARDOIN |
| Deputy Drilled-In Anchors | 10/1/2019 | Approved | MILLARD ARDOIN |
| Excavation/Setback/Form/Re-Bar | 10/8/2019 | Partial Approval | MILLARD ARDOIN |
| Deputy Steel/Welding | 4/7/2020 | Conditional Approval | JEFFREY FULTON |
| Special/Order Compliance | 10/14/2020 | Not Ready for Inspection | JEFFREY FULTON |
| Special/Order Compliance | 10/16/2020 | Not Ready for Inspection | JEFFREY FULTON |
| Drywall Nailing | 12/21/2020 | Approved | JEFFREY FULTON |
| Final | 12/21/2020 | Corrections Issued | JEFFREY FULTON |
| Green Building Final | 12/21/2020 | Not Ready for Inspection | JEFFREY FULTON |
| Green Building Rough | 12/21/2020 | Approved | JEFFREY FULTON |
| Reinforced Concrete Frame | 12/21/2020 | Approved | JEFFREY FULTON |
| Reinforced Masonry Frame | 12/21/2020 | Approved | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 12/21/2020 | SGSOV Not Ready | JEFFREY FULTON |
| Smoke Detectors | 12/21/2020 | Corrections Issued | JEFFREY FULTON |
| Final | 3/4/2021 | Conditional Approval | JEFFREY FULTON |
| Green Building Final | 3/4/2021 | Approved | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 3/4/2021 | SGSOV Approved | JEFFREY FULTON |
| Smoke Detectors | 3/4/2021 | Approved | JEFFREY FULTON |
| Special/Order Compliance | 4/28/2021 | Partial Inspection | JEFFREY FULTON |
| Pre-Inspection | 5/6/2021 | Conditional Approval | JEFFREY DURAN |
| Special/Order Compliance | 10/13/2021 | Conditional Approval | JEFFREY DURAN |
| Final | 11/1/2021 | Not Ready for Inspection | JEFFREY FULTON |
| Final | 11/4/2021 | Not Ready for Inspection | JEFFREY FULTON |
| Final | 1/3/2022 | OK to Issue CofO | JEFFREY FULTON |