17045-17047 W LASSEN ST 91325
Certificate Information: 17045-17047 W LASSEN ST 91325
- Application / Permit
- 19016-20000-03071
- Plan Check / Job No.
- B19VN01658
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ECPC WALK IN: CONVERT THE (E) GARAGE INTO A (N) ADU PER AB 494 AND SB 229 FOR ACCESSORY DWELLING UNITS. WORK PER WFPP.
- Permit Issued
- Issued on 2/1/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/7/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/1/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 2/1/2019 | NIKTA MOUSAVI |
| Corrections Issued | 2/1/2019 | NIKTA MOUSAVI |
| Plan Check Approved | 2/1/2019 | VLADIMIR ARUTYUNYAN |
| Issued | 2/1/2019 | LADBS |
| CofO in Progress | 1/6/2020 | MARK JOHNSON |
| CofO Issued | 3/7/2020 | MICHAEL SMITH |
| Permit Finaled | 3/7/2020 | MICHAEL SMITH |
Permit Application Clearance Information
| "T" removal | Cleared | 2/1/2019 | HERMINIGILDO AGUSTIN |
| Address approval | Cleared | 2/1/2019 | MARKOS PEREZ-BRAN |
| Eng Process Fee Ord 176,300 | Cleared | 2/1/2019 | MARKOS PEREZ-BRAN |
| Grading Pre-Inspection | Cleared | 2/1/2019 | NIKTA MOUSAVI |
| Sewer availability | Cleared | 2/1/2019 | MARKOS PEREZ-BRAN |
| ZA Case | Cleared | 2/1/2019 | HERMINIGILDO AGUSTIN |
| ZI | Cleared | 2/1/2019 | HERMINIGILDO AGUSTIN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/5/2019 | Approved | MARK JOHNSON |
| PLUMBING-Rough | 8/9/2019 | Partial Approval | MARK JOHNSON |
| PLUMBING-Rough | 8/20/2019 | Partial Approval | MARK JOHNSON |
| BUILDING-Rough-Frame | 9/10/2019 | Not Ready for Inspection | MARK JOHNSON |
| ELECTRICAL-Rough | 9/10/2019 | Approved | MARK JOHNSON |
| PLUMBING-Rough | 9/10/2019 | Approved | MARK JOHNSON |
| BUILDING-Rough-Frame | 10/4/2019 | Partial Approval | MARK JOHNSON |
| ELECTRICAL-Rough | 10/4/2019 | Approved | MARK JOHNSON |
| Green Building Rough | 10/4/2019 | Approved | MARK JOHNSON |
| HVAC-Rough | 10/4/2019 | Approved | MARK JOHNSON |
| Insulation | 10/9/2019 | No Access for Inspection | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 10/15/2019 | Approved | MARK JOHNSON |
| Insulation | 10/15/2019 | Approved | MARK JOHNSON |
| Service/Power Release | 10/15/2019 | Not Required | MARK JOHNSON |
| Drywall Nailing | 10/28/2019 | Approved | MARK JOHNSON |
| ELECTRICAL-Rough | 10/28/2019 | Approved | MARK JOHNSON |
| Interior/Exterior Lathing | 10/28/2019 | Approved | MARK JOHNSON |
| Interior/Exterior Lathing | 11/18/2019 | Approved | MARK JOHNSON |
| Shower Pan | 11/18/2019 | Approved | MARK JOHNSON |
| Final | 12/17/2019 | Corrections Issued | MARK JOHNSON |
| Green Building Final | 12/17/2019 | Approved | MARK JOHNSON |
| SGSOV-Seismic Gas S/O Valve | 12/17/2019 | SGSOV Approved | MARK JOHNSON |
| Smoke Detectors | 12/17/2019 | Approved | MARK JOHNSON |
| Final | 12/23/2019 | OK to Issue CofO | MARK JOHNSON |
| PLUMBING-Final | 12/23/2019 | Approved | MARK JOHNSON |