5121 S AVALON BLVD 90011
Certificate Information: 5121 S AVALON BLVD 90011
- Application / Permit
- 19016-20000-01708
- Plan Check / Job No.
- B19VN00934
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Architectural & Structural remodel of existing building apartment house. Convert existing 4 dwelling units on 2nd floor to 6 dwelling units. Stripe for new parking spaces. Replace existing exterior stairs to second floor to a different location.
- Permit Issued
- Issued on 12/1/2020
- Issuing Office
- Current Status
- Issued on 12/1/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/18/2019 | APPLICANT |
| Disabled Access Plans Picked Up | 1/30/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/31/2019 | SALVADOR QUINTANILLA |
| Corrections Issued | 2/4/2019 | RUDOLF KINAR MELIKOFF |
| Quality Review Completed | 2/5/2019 | STEVEN KIM |
| Applicant returned to address corrections | 5/8/2019 | RUDOLF KINAR MELIKOFF |
| Applicant returned to address corrections | 7/10/2020 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 7/14/2020 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 10/21/2020 | SALVADOR QUINTANILLA |
| Plan Check Approved | 11/25/2020 | SALVADOR QUINTANILLA |
| Issued | 12/1/2020 | APPLICANT |
| Building Plans Picked Up | 12/3/2020 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 3/6/2019 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 3/6/2019 | LEE GUILBEAUX |
| Highway dedication | Cleared | 3/6/2019 | LEE GUILBEAUX |
| Sewer availability | Cleared | 3/6/2019 | LEE GUILBEAUX |
| ZA Case | Cleared | 6/6/2019 | ANNA VIDAL |
| Project located in CRA area | Cleared | 11/14/2019 | GISELLE CORELLA |
| ZI | Cleared | 11/21/2019 | HELEN JADALI |
| Supp. Use District POD/CDO/TDO | Cleared | 12/12/2019 | HELEN JADALI |
| DAS Clearance | Cleared | 1/15/2020 | NORLITO MEDRANO |
| Fire Marshall Fire Life Safety | Cleared | 2/11/2020 | PEJMAN NOORI |
| Hydrant and Access approval | Cleared | 3/4/2020 | JOHN CONNEALLY |
| Housing rent stabilization | Cleared | 5/26/2020 | MICHAEL SOTO |
Contact Information
| Contractor | Caribe Construction Inc; Lic. No.: 878090-B | 521 S PARISH PLACE BURBANK, CA 91506 |
| Engineer | Judd,, Shane Dennis; Lic. No.: C70991 | 17 E HIGH ST STE A MOORPARK, CA 93021 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/22/2020 | Conditional Approval | LEOPOLDO MENDOZA |
| Footing/Foundation/Slab | 12/24/2020 | Corrections Issued | LEOPOLDO MENDOZA |
| Wood Frame | 2/11/2021 | Partial Approval | LANNY MERRICK |
| Wood Frame | 5/5/2021 | Partial Approval | LEOPOLDO MENDOZA |
| Deputy Wood Construction | 5/11/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 6/25/2021 | Not Ready for Inspection | DARRYL ARNOLD |
| Insulation | 6/25/2021 | Not Ready for Inspection | DARRYL ARNOLD |
| Drywall Nailing | 7/21/2021 | Partial Approval | LEOPOLDO MENDOZA |
| Drywall Nailing | 8/23/2021 | Partial Approval | DANIEL COLLINS |
| Drywall Nailing | 9/9/2021 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Final | 9/9/2021 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| SGSOV-Seismic Gas S/O Valve | 9/9/2021 | SGSOV Not Ready | LEOPOLDO MENDOZA |
| Smoke Detectors | 9/9/2021 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Wood Frame | 9/9/2021 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Pre-Inspection | 9/28/2021 | Partial Inspection | LEOPOLDO MENDOZA |
| Footing/Foundation/Slab | 2/9/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Masonry Wall/Backfill | 2/9/2022 | Approved | RUSSELL BONVOULOIR |
| Drywall Nailing | 2/16/2022 | Approved | RUSSELL BONVOULOIR |
| Final | 2/16/2022 | Not Ready for Inspection | RUSSELL BONVOULOIR |
| SGSOV-Seismic Gas S/O Valve | 2/16/2022 | SGSOV Approved | RUSSELL BONVOULOIR |
| Smoke Detectors | 2/16/2022 | Approved | RUSSELL BONVOULOIR |
| Wood Frame | 2/16/2022 | Approved | RUSSELL BONVOULOIR |