11022 W BLIX ST 91602

Certificate Information: 11022 W BLIX ST 91602

Application / Permit
19016-20000-00122
Plan Check / Job No.
B19VN00052
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ECPC WALK IN: CONVERT (E) 52' X 22' DETACHED GARAGE TO AN ACCESSORY DWELLING UNIT. ALL WORK DONE PER WOOD FRAME PRESCRIPTIVE PROVISIONS.
Permit Issued
Issued on 1/8/2019
Issuing Office
Valley
Current Status
CofO Issued on 8/7/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/3/2019 APPLICANT
Assigned to Plan Check Engineer 1/3/2019 GURUNATH NESARAJAH
Plan Check Approved 1/8/2019 VLADIMIR ARUTYUNYAN
Issued 1/8/2019 LADBS
CofO in Progress 6/18/2021 DANIEL ORRANTE
CofO Issued 8/7/2021 MICHAEL SMITH
Permit Finaled 8/7/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 1/3/2019 APEKSHYA BAJRACHARYA
Eng Process Fee Ord 176,300 Cleared 1/3/2019 APEKSHYA BAJRACHARYA
Sewer availability Cleared 1/3/2019 APEKSHYA BAJRACHARYA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/26/2019 Partial Approval JEFFREY PARD
Footing/Foundation/Slab 7/5/2019 Approved JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 9/4/2019 Partial Approval RAYMOND KEHOE
ELECTRICAL-Rough 9/11/2019 Not Ready for Inspection JEFFREY PARD
HVAC-Rough 9/11/2019 Approved JEFFREY PARD
PLUMBING-Rough 9/11/2019 Approved JEFFREY PARD
BUILDING-Rough-Frame 9/12/2019 Corrections Issued JEFFREY PARD
Green Building Rough 9/12/2019 Approved JEFFREY PARD
Pre-Inspection 9/24/2019 Not Ready for Inspection JEFFREY PARD
BUILDING-Rough-Frame 10/1/2019 Approved JEFFREY PARD
ELECTRICAL-Rough 10/1/2019 Approved JEFFREY PARD
Insulation 10/30/2019 Corrections Issued CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 10/30/2019 Corrections Issued CHRISTOPHER DELLEFIELD
Green Building Final 11/20/2019 Approved JEFFREY PARD
Insulation 11/20/2019 Approved JEFFREY PARD
Interior/Exterior Lathing 11/20/2019 Approved JEFFREY PARD
Service/Power Release 12/27/2019 Not Ready for Inspection JEFFREY PARD
Pre-Inspection 7/6/2020 Partial Inspection THOMAS FINNILA
Wood Frame 8/4/2020 Approved THOMAS FINNILA
Interior/Exterior Lathing 8/14/2020 Not Ready for Inspection THOMAS FINNILA
Drywall Nailing 8/19/2020 Approved THOMAS FINNILA
Interior/Exterior Lathing 8/19/2020 Approved THOMAS FINNILA
ELECTRICAL-Rough 8/27/2020 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Final 3/19/2021 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Final 3/30/2021 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Final 4/7/2021 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Final 4/8/2021 No Access for Inspection DAVID MATSON
Gas Test 4/21/2021 Approved THOMAS FINNILA
PLUMBING-Final 4/28/2021 Partial Inspection THOMAS FINNILA
ELECTRICAL-Final 5/13/2021 Not Ready for Inspection JOHN HAYES
Final 5/13/2021 Corrections Issued JOHN HAYES
ELECTRICAL-Final 5/20/2021 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Final 6/3/2021 Approved THOMAS FINNILA
Service/Power Release 6/4/2021 Not Ready for Inspection THOMAS FINNILA
Final 6/10/2021 Partial Inspection THOMAS FINNILA
PLUMBING-Final 6/10/2021 Approved THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 6/10/2021 SGSOV Approved THOMAS FINNILA
Smoke Detectors 6/10/2021 Approved THOMAS FINNILA
Final 6/17/2021 Partial Approval THOMAS FINNILA