11207-11209 W BLYTHE ST 91352

Certificate Information: 11207-11209 W BLYTHE ST 91352

Application / Permit
19016-20000-00113
Plan Check / Job No.
B19VN00043
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. Comply with department order effective date 12/192018, permit will expre 3o days from issuance date
Permit Issued
Issued on 2/8/2019
Issuing Office
Valley
Current Status
CofO Issued on 4/24/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/3/2019 APPLICANT
Assigned to Plan Check Engineer 1/3/2019 ALDOUS CHIC
Corrections Issued 1/4/2019 ALDOUS CHIC
Building Plans Picked Up 1/4/2019 APPLICANT
Plan Check Approved 2/8/2019 ALDOUS CHIC
Issued 2/8/2019 LADBS
CofO in Progress 11/21/2022 MICKEY YAMASHITA
Permit Finaled 4/24/2023 DAVID JAMES
CofO Issued 4/24/2023 DAVID JAMES
Permit Finaled 4/24/2023 DAVID JAMES

Permit Application Clearance Information

Address approval Cleared 1/22/2019 APEKSHYA BAJRACHARYA
Eng Process Fee Ord 176,300 Cleared 1/22/2019 APEKSHYA BAJRACHARYA
Sewer availability Cleared 1/22/2019 APEKSHYA BAJRACHARYA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARA SINANIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HASANTHA WEERASEKARA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
SCOTT SHUSTER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOEL GUARDADO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARIYA MIHALEVA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOSE RUBIO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID JAMES, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID HICKMAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN HAMILTON, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN STEPHENS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
PIERRE VEGA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK VAN SLOOTEN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MICKEY YAMASHITA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
RICHARD ROBLES, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HAGOP BADOSSIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
KIM BEAUCHAMP, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK DOVICO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
THOMAS WOODS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
RAUL VASQUEZ, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
AUGUSTUS ALBAS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
FELIPE PENICHE, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
LEO MILBAUER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/15/2019 Not Ready for Inspection MICKEY YAMASHITA
Underground Mechanical 4/15/2019 Corrections Issued MICKEY YAMASHITA
Deputy Drilled-In Anchors 12/4/2019 Conditional Approval MICKEY YAMASHITA
Footing/Foundation/Slab 12/5/2019 Corrections Issued MICKEY YAMASHITA
Footing/Foundation/Slab 2/19/2020 Approved MICKEY YAMASHITA
PLUMBING-Rough 2/19/2020 Partial Approval MICKEY YAMASHITA
Wood Frame 3/31/2020 Partial Approval DAVID JAMES
ELECTRICAL-Rough 8/27/2020 Partial Approval CHRISTOPHER KEY
Floor/Roof Diaphrgm/Shear Wall 8/27/2020 Corrections Issued CHRISTOPHER KEY
PLUMBING-Rough 8/27/2020 Corrections Issued CHRISTOPHER KEY
BUILDING-Rough-Frame 12/30/2020 Corrections Issued MICKEY YAMASHITA
ELECTRICAL-Rough 12/30/2020 Corrections Issued JOSEPH BRENEK
Footing/Foundation/Slab 12/30/2020 Not Ready for Inspection JOSEPH BRENEK
Gas Test 12/30/2020 Partial Approval JOSEPH BRENEK
PLUMBING-Rough 12/30/2020 Corrections Issued JOSEPH BRENEK
ELECTRICAL-Rough 1/21/2021 Partial Approval MICKEY YAMASHITA
PLUMBING-Rough 1/21/2021 Partial Inspection JOSEPH BRENEK
ELECTRICAL-Final 2/9/2021 Corrections Issued JOSEPH BRENEK
PLUMBING-Final 2/9/2021 Corrections Issued JOSEPH BRENEK
Wood Frame 2/9/2021 Approved JOSEPH BRENEK
Insulation 3/23/2021 Approved JOSEPH BRENEK
Interior/Exterior Lathing 3/23/2021 Approved JOSEPH BRENEK
PLUMBING-Rough 3/23/2021 Approved JOSEPH BRENEK
Drywall Nailing 7/13/2021 Conditional Approval MICKEY YAMASHITA
Green Building Rough 7/13/2021 Corrections Issued MICKEY YAMASHITA
HVAC-Rough 7/13/2021 Corrections Issued MICKEY YAMASHITA
Interior/Exterior Lathing 7/13/2021 Conditional Approval MICKEY YAMASHITA
Interior/Exterior Lathing 9/14/2021 Approved THOMAS WOODS
BUILDING-Rough-Frame 1/24/2022 Approved MICKEY YAMASHITA
Final 1/24/2022 Corrections Issued MICKEY YAMASHITA
Green Building Final 1/24/2022 Approved MICKEY YAMASHITA
Green Building Rough 1/24/2022 Approved MICKEY YAMASHITA
SGSOV-Seismic Gas S/O Valve 1/24/2022 SGSOV Approved MICKEY YAMASHITA
Smoke Detectors 1/24/2022 Corrections Issued MICKEY YAMASHITA
Final 5/17/2022 Conditional Approval MICKEY YAMASHITA
Smoke Detectors 5/17/2022 Approved MICKEY YAMASHITA
Final 11/21/2022 OK to Issue CofO MICKEY YAMASHITA
ELECTRICAL-Rough 1/31/2023 Corrections Issued MICKEY YAMASHITA