2221 W WASHINGTON BLVD 90018

Certificate Information: 2221 W WASHINGTON BLVD 90018

Application / Permit
19016-10003-31030
Plan Check / Job No.
B20LA14948
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(18) Dance Studio or Academy
Work Description
SUPPLEMENTAL TO 19016 10000 31030 TO CAPTURE FOUNDATION REDESIGN AND METHOD OF ABC SLOT CUT TO PROVIDE LATERAL SUPPORT TO ADJACENT OFFSITE BUILDING
Permit Issued
Issued on 8/28/2020
Issuing Office
Current Status
Permit Finaled on 5/12/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/25/2020 APPLICANT
Assigned to Plan Check Engineer 8/28/2020 STARR CHEN
Plan Check Approved 8/28/2020 STARR CHEN
Issued 8/28/2020 APPLICANT
Permit Finaled 5/12/2022 KATY RAMIREZ

Permit Application Clearance Information

No Data Available.

Contact Information

Architect Herst,, Hans Robert; Lic. No.: C12001 500 S FIGUEROA AVENUE      LOS ANGELES, CA 90071
Contractor Build Group Construction Company Inc; Lic. No.: 1015855-B 1212 ABBOT KINNEY BLVD #A      LOS ANGELES, CA 90291
Engineer Cocke,, David Winbern; Lic. No.: S3005 19210 S VERMONT AVENUE BLDNG B SUITE 210      GARDENA, CA 90248
Engineer Hayrikian,, Arsham; Lic. No.: C91446 1732 CAMULOS AVE      GLENDALE, CA 91208
Engineer Minas,, Caro Jolfaie; Lic. No.: GE601 4742 SAN FERNANDO RD      GLENDALE, CA 91204

Inspector Information

IAN BLINN, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI
CHRISTOPHER BLACKWOOD, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/4/2020 Corrections Issued KATY RAMIREZ
Footing/Foundation/Slab 11/4/2020 Off-Hour Fees Due
Reinforced Concrete Frame 11/4/2020 Off-Hour Fees Due
Reinforced Concrete Frame 11/4/2020 Partial Inspection KATY RAMIREZ
Footing/Foundation/Slab 11/5/2020 Partial Approval KATY RAMIREZ
Reinforced Concrete Frame 11/5/2020 Partial Inspection KATY RAMIREZ
Footing/Foundation/Slab 11/17/2020 Not Ready for Inspection KATY RAMIREZ
Reinforced Concrete Frame 11/17/2020 Not Ready for Inspection KATY RAMIREZ
Reinforced Concrete Frame 11/23/2020 Partial Approval RUSSELL BONVOULOIR
Footing/Foundation/Slab 12/2/2020 Partial Approval KATY RAMIREZ
Footing/Foundation/Slab 12/22/2020 Partial Approval KATY RAMIREZ
Pre-Inspection 4/22/2021 Approved KATY RAMIREZ
Footing/Foundation/Slab 4/27/2021 Not Ready for Inspection KATY RAMIREZ
Footing/Foundation/Slab 4/29/2021 Not Ready for Inspection KATY RAMIREZ
Special/Order Compliance 4/30/2021 Partial Inspection KATY RAMIREZ
Footing/Foundation/Slab 5/4/2021 Partial Inspection KATY RAMIREZ
Light Gage Steel Frame 8/31/2021 Partial Approval TIMOTHY BUXTON
Final 4/15/2022 Not Ready for Inspection KATY RAMIREZ
Smoke Detectors 4/15/2022 Approved KATY RAMIREZ
Final 5/12/2022 Permit Finaled KATY RAMIREZ