400 S LA BREA AVE 90036
Certificate Information: 400 S LA BREA AVE 90036
- Application / Permit
- 19016-10003-04485
- Plan Check / Job No.
- B21LA20004
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (8) Car Sales - new
- Work Description
- SUPPLEMENTAL TO PERMIT # 19016-10000-04485 FOR THE CONSTRUCTION OF A 12 SQ.FT. EXTENSION AT SECOND FLOOR. THIS EXTENSION OF THE 2ND FLOOR EXTENDS INTO THE VOID SPACE OF THE FREIGHT ELEVATOR THAT HAS BEEN PERMITTED UNDER THE PREVIOUS PERMIT. THE EXTENSION IS NEEDED SO THE LOADING WINDOW OF THE VERTICAL LIFT UNIT (PARTS STORAGE, UNDER SEPARATE PERMIT APPLICATIONS 21016-10000-15302/01357/ 03062)
- Permit Issued
- Issued on 3/3/2022
- Issuing Office
- Current Status
- CofO Issued on 7/28/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
Submitted | 10/25/2021 | APPLICANT |
Assigned to Plan Check Engineer | 10/28/2021 | SAM CHANG |
Corrections Issued | 11/4/2021 | SAM CHANG |
Quality Review Completed | 11/8/2021 | EUGENE BARBEAU |
Disabled Access Plans Picked Up | 12/23/2021 | APPLICANT |
Green Plans Picked Up | 12/23/2021 | APPLICANT |
Plan Check Approved | 1/27/2022 | SAM CHANG |
Issued | 3/3/2022 | APPLICANT |
Building Plans Picked Up | 3/8/2022 | APPLICANT |
CofO in Progress | 7/26/2023 | KATY RAMIREZ |
Permit Finaled | 7/28/2023 | ERNESTO CORRAL |
CofO Issued | 7/28/2023 | ERNESTO CORRAL |
Permit Finaled | 7/28/2023 | ERNESTO CORRAL |
Permit Application Clearance Information
Green Code | Cleared | 12/7/2021 | AARON COSTA |
DAS Clearance | Cleared | 1/27/2022 | SAM CHANG |
Contact Information
Architect | Bard,, Anna Marie; Lic. No.: C30859 | 1213 RUTLAND ROAD NEWPORT BEACH, CA 92660 |
Contractor | Sauers Lopez Construction Inc; Lic. No.: 736915-B | 26072 MERIT CIR STE 112 LAGUNA HILLS, CA 92653 |
Engineer | Christian,, Dale Alan; Lic. No.: S2705 | 1744 W KATELLA AVENUE SUITE 107 ORANGE, CA 92867 |
Inspector Information
KATY RAMIREZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
PAUL BAZERKANIAN, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
No Data Available. |
Inspection Request History
Final | 3/28/2023 | Not Ready for Inspection | VAHE KELEDJIAN |
Footing/Foundation/Slab | 3/28/2023 | Not Ready for Inspection | VAHE KELEDJIAN |
Green Building Final | 3/28/2023 | Not Ready for Inspection | VAHE KELEDJIAN |
Green Building Rough | 3/28/2023 | Not Ready for Inspection | VAHE KELEDJIAN |
METHANE-Barrier | 3/28/2023 | Not Ready for Inspection | VAHE KELEDJIAN |
METHANE-Final | 3/28/2023 | Not Ready for Inspection | VAHE KELEDJIAN |
METHANE-Rough | 3/28/2023 | Not Ready for Inspection | VAHE KELEDJIAN |
METHANE-Subgrade | 3/28/2023 | Not Ready for Inspection | VAHE KELEDJIAN |
Reinforced Masonry Frame | 3/28/2023 | Not Ready for Inspection | VAHE KELEDJIAN |
Smoke Detectors | 3/28/2023 | Not Ready for Inspection | VAHE KELEDJIAN |
Final | 5/30/2023 | Not Ready for Inspection | MARTIN TAVITIAN |
Footing/Foundation/Slab | 5/30/2023 | Partial Approval | MARTIN TAVITIAN |
Green Building Final | 5/30/2023 | Not Ready for Inspection | MARTIN TAVITIAN |
Green Building Rough | 5/30/2023 | Partial Approval | MARTIN TAVITIAN |
METHANE-Barrier | 5/30/2023 | Partial Approval | MARTIN TAVITIAN |
METHANE-Final | 5/30/2023 | Partial Approval | MARTIN TAVITIAN |
METHANE-Rough | 5/30/2023 | Partial Approval | MARTIN TAVITIAN |
METHANE-Subgrade | 5/30/2023 | Partial Approval | MARTIN TAVITIAN |
Reinforced Masonry Frame | 5/30/2023 | Partial Approval | MARTIN TAVITIAN |
Smoke Detectors | 5/30/2023 | Partial Approval | MARTIN TAVITIAN |
Final | 7/26/2023 | OK to Issue CofO | KATY RAMIREZ |
Footing/Foundation/Slab | 7/26/2023 | Approved | KATY RAMIREZ |
Green Building Final | 7/26/2023 | Approved | KATY RAMIREZ |
Green Building Rough | 7/26/2023 | Approved | KATY RAMIREZ |
METHANE-Barrier | 7/26/2023 | Approved | KATY RAMIREZ |
METHANE-Final | 7/26/2023 | Approved | KATY RAMIREZ |
METHANE-Rough | 7/26/2023 | Approved | KATY RAMIREZ |
METHANE-Subgrade | 7/26/2023 | Approved | KATY RAMIREZ |
Smoke Detectors | 7/26/2023 | Approved | KATY RAMIREZ |