1507-1541 S MIRASOL ST 90023

Certificate Information: 1507-1541 S MIRASOL ST 90023

Application / Permit
19016-10002-03019
Plan Check / Job No.
B19LA26094
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(12) Candy Manufacturing
Work Description
Supplemental to permit 19016-10k-03019 to add new walls to enclose existing rollup doors in the loading dock and add exterior walls for 2 equipment rooms. Add interior partitions on the mezzanine level for storage spaces. Relocate stair access and correct interior walls per site condition.
Permit Issued
Issued on 5/7/2025
Issuing Office
Metro
Current Status
Issued on 5/7/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/10/2023 APPLICANT
Assigned to Plan Check Engineer 4/10/2023 SAM CHANG
Corrections Issued 4/10/2023 SAM CHANG
Plan Check Approved 3/28/2025 SAM CHANG
Issued 5/7/2025 APPLICANT

Permit Application Clearance Information

Redevelopment Project Area Cleared 7/31/2023 YASMINE BASHIRI
Hydrant and Access approval Cleared 3/18/2025 WILLIAM JOHNS

Contact Information

Architect Zane,, Jonathan Leonard; Lic. No.: C11046 958 NORTH LA CADENA DRIVE      COLTON, CA 92324
Contractor Decar Construction; Lic. No.: 906259-B 8780 19TH STREET #252      ALTA LOMA, CA 91701

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/8/2025 Corrections Issued RAFAEL ESPINOZA
Special/Order Compliance 5/8/2025 Not Ready for Inspection RONALD JIMENEZ
Wood Frame 7/10/2025 Corrections Issued ALFREDO LOPEZ
Drywall Nailing 7/14/2025 Not Ready for Inspection RONALD JIMENEZ
Light Gage Steel Frame 8/7/2025 Partial Approval RONALD JIMENEZ
Special/Order Compliance 8/7/2025 Partial Inspection RAFAEL ESPINOZA
Drywall Nailing 8/19/2025 Partial Approval RONALD JIMENEZ
Insulation 8/19/2025 Partial Approval RONALD JIMENEZ
Insulation 9/5/2025 Partial Approval RONALD JIMENEZ
Light Gage Steel Frame 9/5/2025 Partial Approval RONALD JIMENEZ
Wood Frame 10/14/2025 Partial Inspection RONALD JIMENEZ
Insulation 10/29/2025 Partial Approval RONALD JIMENEZ
Pre-Inspection 5/20/2026 Corrections Issued RONALD JIMENEZ