331 N MAR VISTA AVE 90744
Certificate Information: 331 N MAR VISTA AVE 90744
- Application / Permit
- 19016-10001-40527
- Plan Check / Job No.
- B20LA16259
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- SUPPLEMENTAL TO 19016-70000-40527 TO REVISE WORK DESCRIPTION: NEW ACCESSORY DWELLING UNIT AT REAR PER ORDINANCE "LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy"
- Permit Issued
- Issued on 4/25/2023
- Issuing Office
- San Pedro
- Current Status
- Permit Finaled on 9/12/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/25/2020 | STARR CHEN |
| Corrections Issued | 9/27/2020 | STARR CHEN |
| Applicant returned to address corrections | 9/30/2021 | LUKE GONZALES |
| Applicant returned to address corrections | 12/7/2021 | LUKE GONZALES |
| Building Plans Picked Up | 12/8/2021 | APPLICANT |
| Plan Check Approved | 5/5/2022 | RAHEL BEYENE |
| Issued | 4/25/2023 | APPLICANT |
| Permit Closed-Status Void | 8/10/2023 | BRIAN CHRISTIAN |
| Re-Activate Permit | 9/12/2024 | BRIAN CHRISTIAN |
| Permit Finaled | 9/12/2024 | PAUL REECE |
Permit Application Clearance Information
| Clean Up Green Up | Cleared | 12/23/2020 | RICHARD REASER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hale,, Ronald Richard; Lic. No.: C17056 | 1869 PALACIOS DR SAN PEDRO, CA 90732 |
Inspector Information
| KELLY WARNER, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL BECKER, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
| KEITH EDGHILL, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
| DANIEL GONZALEZ, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 5/23/2023 | Not Ready for Inspection | BRIAN CHRISTIAN |
| Footing/Foundation/Slab | 5/23/2023 | Approved | BRIAN CHRISTIAN |
| METHANE-Barrier | 5/23/2023 | Approved | BRIAN CHRISTIAN |
| METHANE-Subgrade | 5/23/2023 | Approved | BRIAN CHRISTIAN |
| Wood Frame | 6/8/2023 | Partial Approval | BRIAN CHRISTIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/15/2023 | Partial Approval | BRIAN CHRISTIAN |
| Insulation | 6/15/2023 | Partial Approval | BRIAN CHRISTIAN |
| Final | 8/9/2023 | Not Ready for Inspection | BRIAN CHRISTIAN |
| BUILDING-Rough-Frame | 8/10/2023 | Not Ready for Inspection | BRIAN CHRISTIAN |
| Drywall Nailing | 8/10/2023 | Not Ready for Inspection | BRIAN CHRISTIAN |
| Final | 8/10/2023 | Not Ready for Inspection | BRIAN CHRISTIAN |
| Green Building Final | 8/10/2023 | Not Ready for Inspection | BRIAN CHRISTIAN |
| Green Building Rough | 8/10/2023 | Not Ready for Inspection | BRIAN CHRISTIAN |
| METHANE-Final | 8/10/2023 | Approved | BRIAN CHRISTIAN |
| METHANE-Rough | 8/10/2023 | Approved | BRIAN CHRISTIAN |
| Service/Power Release | 8/10/2023 | Not Ready for Inspection | BRIAN CHRISTIAN |
| Smoke Detectors | 8/10/2023 | Not Ready for Inspection | BRIAN CHRISTIAN |
| Verify Sprinkler Sign Off | 8/10/2023 | Not Ready for Inspection | BRIAN CHRISTIAN |