3819 W SUNSET DR 90027
Certificate Information: 3819 W SUNSET DR 90027
- Application / Permit
- 19016-10001-35443
- Plan Check / Job No.
- B20LA18267
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- SUPPLEMENTAL TO PERMIT #19016-10000-35443 TO ENLARGE EXISTING BASEMENT & ADD A NEW UNCOVERED DECK (4'9" x 16'11")
- Permit Issued
- Issued on 5/25/2021
- Issuing Office
- Current Status
- Permit Finaled on 4/24/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/15/2020 | PRANITA SHAH |
| Corrections Issued | 11/17/2020 | PRANITA SHAH |
| Quality Review Completed | 11/18/2020 | WING SUEN |
| Building Plans Picked Up | 11/19/2020 | APPLICANT |
| Plan Check Approved | 5/24/2021 | PRANITA SHAH |
| Issued | 5/25/2021 | APPLICANT |
| Permit Finaled | 4/23/2024 | JEFFREY MEAD |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 5/13/2021 | PRANITA SHAH |
Contact Information
| Contractor | Progressive Environmental Concepts; Lic. No.: 543710-B | 9049 LEMORAN AVENUE DOWNEY, CA 90240 |
| Engineer | Benavides,, Jose Alexander; Lic. No.: C72968 | 644 N POPLAR ST UNIT B ORANGE, CA 92868 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/17/2021 | Partial Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 8/17/2021 | Partial Approval | JOSEPH MCGARRY |
| Sewer | 8/17/2021 | Approved | JOSEPH MCGARRY |
| Special/Order Compliance | 8/17/2021 | Corrections Issued | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 8/18/2021 | Partial Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 8/18/2021 | Partial Approval | JOSEPH MCGARRY |
| Masonry Wall/Backfill | 10/12/2021 | Partial Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 10/12/2021 | Partial Approval | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 11/19/2021 | Partial Approval | JOSEPH MCGARRY |
| Masonry Wall/Backfill | 11/19/2021 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 6/29/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 6/29/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 6/29/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| HVAC-Rough | 6/29/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| PLUMBING-Rough | 6/29/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 7/27/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 7/27/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| Verify Sprinkler Sign Off | 7/27/2022 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 8/12/2022 | Conditional Approval | JOSEPH MCGARRY |
| Rough-Elec/Plmb/HVAC | 8/12/2022 | Approved | JOSEPH MCGARRY |
| Insulation | 9/22/2022 | Partial Approval | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 9/22/2022 | Partial Approval | JOSEPH MCGARRY |
| Drywall Nailing | 10/18/2022 | Partial Approval | JOSEPH MCGARRY |
| Insulation | 1/3/2023 | Approved | JOSEPH MCGARRY |
| Drywall Nailing | 1/19/2023 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 1/19/2023 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Final | 3/16/2023 | Corrections Issued | JOSEPH MCGARRY |
| Pre-Inspection | 10/3/2023 | Corrections Issued | JOSEPH MCGARRY |
| Underground Mechanical | 10/3/2023 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 4/23/2024 | Approved | JEFFREY MEAD |
| Final | 4/23/2024 | Permit Finaled | JEFFREY MEAD |
| Smoke Detectors | 4/23/2024 | Approved | JEFFREY MEAD |