1375 N VINE ST BLDG. A-2ND-4TH FL 90028
Certificate Information: 1375 N VINE ST BLDG. A-2ND-4TH FL 90028
- Application / Permit
- 19016-10001-28216
- Plan Check / Job No.
- B19LA27193
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- SUPPLEMENTAL TO 19016-10000-28216. INTERIOR TI TO EXISTING OFFICE (NETFLIX) LEVELS 2-6. NEW PARTITIONS, SUSPENDED CEILING SYSTEM FOR OFFICE SPACES, MEETING ROOMS, AND PANTRY AREA. 2 NEW INTERCONNECTING STAIRS PROPOSED (LEVELS 1-2 & 5-6). NEW SHADING STRUCTURE PROPOSED AT LEVEL 6 TERRACE.
- Permit Issued
- Issued on 4/24/2020
- Issuing Office
- Current Status
- CofO Issued on 1/12/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/24/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/23/2020 | JOE VO |
| Disabled Access Plans Picked Up | 1/24/2020 | APPLICANT |
| Green Plans Picked Up | 1/24/2020 | APPLICANT |
| Corrections Issued | 1/28/2020 | JOE VO |
| Quality Review Completed | 2/3/2020 | KEN GILL |
| Applicant returned to address corrections | 3/10/2020 | JOE VO |
| Plan Check Approved | 4/13/2020 | JOE VO |
| Issued | 4/24/2020 | APPLICANT |
| TCO Issued (Expire Date: 01-17-2022) | 7/21/2021 | ERNESTO CORRAL |
| CofO in Progress | 1/11/2022 | DAVID BURKHEAD |
| CofO in Progress | 1/12/2022 | DAVID BURKHEAD |
| CofO Issued | 1/12/2022 | ERNESTO CORRAL |
| Permit Finaled | 1/12/2022 | ERNESTO CORRAL |
Permit Application Clearance Information
| Green Code | Cleared | 2/24/2020 | VIVIAN LAO |
| DAS Clearance | Cleared | 2/26/2020 | JOE VO |
| "D" conditions | Cleared | 2/27/2020 | ANNA VIDAL |
| Redevelopment Project Area | Cleared | 3/4/2020 | GRACIELA ACOSTA |
| Fire Marshall Fire Life Safety | Cleared | 3/31/2020 | WILLIAM JOHNS |
Contact Information
| Contractor | Clune Construction Company L P; Lic. No.: 732107-B | 350 SOUTH GRAND AVE #1600 LOS ANGELES, CA 90071 |
Inspector Information
| DAVID BURKHEAD, (213) 482-7294 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/19/2020 | Partial Approval | DAVID BURKHEAD |
| Footing/Foundation/Slab | 6/26/2020 | Partial Approval | DAVID BURKHEAD |
| Light Gage Steel Frame | 7/8/2020 | Partial Approval | DAVID BURKHEAD |
| Insulation | 7/13/2020 | Partial Approval | DAVID BURKHEAD |
| Light Gage Steel Frame | 7/13/2020 | Partial Approval | DAVID BURKHEAD |
| Drywall Nailing | 7/20/2020 | Partial Approval | DAVID BURKHEAD |
| Insulation | 7/20/2020 | Partial Approval | DAVID BURKHEAD |
| Drywall Nailing | 7/22/2020 | Partial Approval | DAVID BURKHEAD |
| Drywall Nailing | 7/28/2020 | Partial Approval | DAVID BURKHEAD |
| Light Gage Steel Frame | 8/26/2020 | Partial Approval | DAVID BURKHEAD |
| Drywall Nailing | 8/31/2020 | Partial Approval | DAVID BURKHEAD |
| Light Gage Steel Frame | 8/31/2020 | Partial Approval | DAVID BURKHEAD |
| Light Gage Steel Frame | 9/2/2020 | Partial Approval | DAVID BURKHEAD |
| Drywall Nailing | 9/4/2020 | Not Ready for Inspection | DAVID BURKHEAD |
| Light Gage Steel Frame | 9/16/2020 | Not Ready for Inspection | EDWIN GREGORYONA |
| Light Gage Steel Frame | 9/25/2020 | Partial Approval | DAVID BURKHEAD |
| Light Gage Steel Frame | 10/1/2020 | Partial Approval | DAVID BURKHEAD |
| Drywall Nailing | 10/14/2020 | Partial Approval | DAVID BURKHEAD |
| T-Bar Ceiling | 10/20/2020 | Partial Approval | DAVID BURKHEAD |
| Deputy Drilled-In Anchors | 10/23/2020 | Conditional Approval | DAVID BURKHEAD |
| Deputy Steel/Welding | 10/23/2020 | Conditional Approval | DAVID BURKHEAD |
| Drywall Nailing | 11/2/2020 | Partial Approval | DAVID BURKHEAD |
| T-Bar Ceiling | 11/2/2020 | Partial Approval | DAVID BURKHEAD |
| Deputy Steel/Welding | 11/4/2020 | Conditional Approval | DAVID BURKHEAD |
| Deputy Steel/Welding | 11/5/2020 | Conditional Approval | DAVID BURKHEAD |
| Smoke Detectors | 12/29/2020 | Partial Inspection | DAVID BURKHEAD |
| Final | 6/9/2021 | Conditional Approval | DAVID BURKHEAD |
| Green Building Final | 6/9/2021 | Approved | DAVID BURKHEAD |
| Green Building Rough | 6/9/2021 | Approved | DAVID BURKHEAD |
| Reinforced Concrete Frame | 6/9/2021 | Approved | DAVID BURKHEAD |
| Smoke Detectors | 6/9/2021 | Approved | DAVID BURKHEAD |
| Special/Order Compliance | 12/23/2021 | Approved | DAVID BURKHEAD |
| Final | 1/10/2022 | OK to Issue CofO | DAVID BURKHEAD |