5349 W HOMESIDE AVE 90016
Certificate Information: 5349 W HOMESIDE AVE 90016
- Application / Permit
- 19016-10001-15678
- Plan Check / Job No.
- B19LA21080
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- SUPPLEMENTAL TO PERMIT # 19016-10000-15678 TO REVISE SCOPE OF WORK TO NEW 1-STORY SINGLE FAMILY DWELLING. ***SEE COMMENTS***
- Permit Issued
- Issued on 11/5/2020
- Issuing Office
- Current Status
- Permit Finaled on 12/23/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/3/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/7/2019 | MICHAEL LOPEZ |
| Corrections Issued | 10/8/2019 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 12/9/2019 | MICHAEL LOPEZ |
| Plan Check Approved | 2/6/2020 | MICHAEL LOPEZ |
| Issued | 11/5/2020 | APPLICANT |
| Building Plans Picked Up | 11/6/2020 | APPLICANT |
| Permit Finaled | 12/22/2021 | JOSE AVILA |
Permit Application Clearance Information
| CPC | Cleared | 1/22/2020 | SARAHI ORTEGA |
| Address approval | Cleared | 1/27/2020 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 1/27/2020 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 1/27/2020 | GILBERT URREA |
| Low Impact Development | Cleared | 1/27/2020 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 1/27/2020 | JEANIE LAM |
| Sewer availability | Cleared | 1/27/2020 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| FLOOD-Elevation Certificate | 11/30/2020 | Not Ready for Inspection | DAVID CHAN |
| Footing/Foundation/Slab | 11/30/2020 | Corrections Issued | DAVID CHAN |
| FLOOD-Elevation Certificate | 12/15/2020 | Approved | DAVID CHAN |
| Footing/Foundation/Slab | 12/15/2020 | Approved | DAVID CHAN |
| BUILDING-Rough-Frame | 1/5/2021 | Partial Approval | DAVID CHAN |
| BUILDING-Rough-Frame | 1/21/2021 | Not Ready for Inspection | DAVID FEILER |
| PLUMBING-Rough | 1/21/2021 | Corrections Issued | DAVID FEILER |
| Verify Sprinkler Sign Off | 1/21/2021 | Not Ready for Inspection | DAVID FEILER |
| FLOOD-Proofing Certificate | 2/2/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/2/2021 | Partial Approval | STUART CHAPMAN |
| Verify Sprinkler Sign Off | 2/2/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Insulation | 2/4/2021 | Partial Approval | STUART CHAPMAN |
| FLOOD-Proofing Certificate | 3/15/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/15/2021 | Approved | STUART CHAPMAN |
| Verify Sprinkler Sign Off | 3/15/2021 | Not Ready for Inspection | STUART CHAPMAN |
| ELECTRICAL-Rough | 4/6/2021 | Corrections Issued | DAVID FEILER |
| Rough-Elec/Plmb/HVAC | 4/6/2021 | Partial Approval | DAVID FEILER |
| Underground Mechanical | 4/6/2021 | Approved | DAVID FEILER |
| BUILDING-Rough-Frame | 4/16/2021 | Corrections Issued | DAVID FEILER |
| Rough-Elec/Plmb/HVAC | 4/16/2021 | Approved | DAVID FEILER |
| Verify Sprinkler Sign Off | 4/16/2021 | Not Ready for Inspection | DAVID FEILER |
| BUILDING-Rough-Frame | 6/14/2021 | Conditional Approval | STUART CHAPMAN |
| FLOOD-Proofing Certificate | 6/14/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Interior/Exterior Lathing | 6/14/2021 | Partial Approval | STUART CHAPMAN |
| Verify Sprinkler Sign Off | 6/14/2021 | Approved | STUART CHAPMAN |
| Insulation | 7/8/2021 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 7/15/2021 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 8/9/2021 | Approved | WILLIAM WREN |
| Shower Pan | 8/9/2021 | Approved | WILLIAM WREN |
| Gas Test | 8/18/2021 | Approved | CALEB MEISTER |
| BUILDING-Rough-Frame | 11/9/2021 | Approved | JOSE AVILA |
| FLOOD-Proofing Certificate | 11/9/2021 | Approved | JOSE AVILA |
| Final | 11/9/2021 | Corrections Issued | JOSE AVILA |
| Service/Power Release | 11/9/2021 | Corrections Issued | JOSE AVILA |
| Smoke Detectors | 11/9/2021 | Approved | JOSE AVILA |
| Final | 11/16/2021 | Corrections Issued | JOSE AVILA |
| Service/Power Release | 11/16/2021 | Corrections Issued | JOSE AVILA |
| Service/Power Release | 11/23/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Service/Power Release | 12/3/2021 | Approved | JOSE AVILA |
| Final | 12/22/2021 | Permit Finaled | JOSE AVILA |