14062 W ALBERS ST 91401

Certificate Information: 14062 W ALBERS ST 91401

Application / Permit
19016-10001-15595
Plan Check / Job No.
B20LA22222
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
SUPPLEMENTAL TO #19016-30000-15595: REMOVING OPEN PARKING FOR ADU. REVISED FLOOR PLAN TO ADD (2) BEDROOMS AND NEW LAUNDRY ROOM. REVISE FRAMING PLANS AND FOUNDATION PLANS TO EXPAND ADU CONVERSION TO 772 SQ.FT. CHANGE ENGINEER OF RECORD. REVISE STRUCTURAL INVENTORY.
Permit Issued
Issued on 5/23/2021
Issuing Office
Current Status
Permit Finaled on 9/29/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/22/2021 APPLICANT
Assigned to Plan Check Engineer 2/1/2021 CRISTINA SALAZAR
Corrections Issued 2/2/2021 CRISTINA SALAZAR
Plan Check Approved 4/8/2021 JESSE JIMENEZ
Issued 5/23/2021 APPLICANT
Building Plans Picked Up 5/25/2021 APPLICANT
Permit Finaled 9/28/2022 GORDON ZUBER

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 3/10/2021 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 3/16/2021 JOHN TRIANTAFYLLOS

Contact Information

Contractor Owner-Builder       ,
Engineer Wu,, Harold Ping-Hung; Lic. No.: C35693 1168 SAN GABRIEL BLVD NO N      ROSEMEAD, CA 91770

Inspector Information

JOEL ORDAZ, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
PTOLEMY HILL, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVAKIAN, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
EDMOND DECKERT, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
TIMOTHY KEY, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT CHAVEZ, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/21/2021 Approved ARTHUR SARGSYAN
Underground Mechanical 6/30/2021 Approved ARTHUR SARGSYAN
BUILDING-Rough-Frame 7/9/2021 Partial Approval ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 7/9/2021 Partial Approval ARTHUR SARGSYAN
Green Building Rough 7/9/2021 Not Ready for Inspection ARTHUR SARGSYAN
Wood Frame 7/9/2021 Partial Approval ARTHUR SARGSYAN
HVAC-Rough 10/13/2021 Approved GORDON ZUBER
PLUMBING-Rough 10/13/2021 Approved GORDON ZUBER
ELECTRICAL-Rough 10/14/2021 Approved GORDON ZUBER
Green Building Rough 10/14/2021 Approved GORDON ZUBER
Interior/Exterior Lathing 11/4/2021 Approved GORDON ZUBER
Insulation 11/9/2021 Approved GORDON ZUBER
Drywall Nailing 12/13/2021 Approved JOEL WILLIAMS
Shower Pan 12/13/2021 Approved JOEL WILLIAMS
Interior/Exterior Lathing 2/7/2022 Approved GORDON ZUBER
Deck 4/8/2022 Not Ready for Inspection PIERRE VEGA
Pre-Inspection 5/24/2022 Approved GORDON ZUBER
BUILDING-Rough-Frame 9/22/2022 Approved GORDON ZUBER
ELECTRICAL-Final 9/22/2022 Corrections Issued GORDON ZUBER
Final 9/22/2022 Corrections Issued GORDON ZUBER
Footing/Foundation/Slab 9/22/2022 Approved GORDON ZUBER
Green Building Final 9/22/2022 Approved GORDON ZUBER
HVAC-Final 9/22/2022 Corrections Issued GORDON ZUBER
PLUMBING-Final 9/22/2022 Approved GORDON ZUBER
Smoke Detectors 9/22/2022 Approved GORDON ZUBER
Final 9/28/2022 Permit Finaled GORDON ZUBER