517 1/2 W 56TH ST 90037

Certificate Information: 517 1/2 W 56TH ST 90037

Application / Permit
19016-10000-41077
Plan Check / Job No.
B19LA27289
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Conversion of (E) detached garage into an Accessory Dwelling Unit per AB 494 and SB 229. All works per Wood Frame Prescriptive Provisions. ** COMPLY WITH DEPARTMENT ORDER effective date 11/18/2019. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE**
Permit Issued
Issued on 2/13/2020
Issuing Office
Metro
Current Status
CofO Issued on 2/2/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/26/2019 APPLICANT
Assigned to Plan Check Engineer 12/30/2019 MONICA RAMIREZ
Corrections Issued 12/30/2019 MONICA RAMIREZ
Applicant returned to address corrections 1/30/2020 HELEN NGUYEN
Plan Check Approved 2/12/2020 GEORGE ALVAREZ
Issued 2/13/2020 LADBS
CofO in Progress 1/14/2021 MEL KHACHATOURIAN
CofO Issued 2/2/2022 BRUCE TODD
Permit Finaled 2/2/2022 BRUCE TODD

Permit Application Clearance Information

Address approval Cleared 1/30/2020 JEANIE LAM
CPC Cleared 1/30/2020 TERRI OSBORNE
Eng Process Fee Ord 176,300 Cleared 1/30/2020 JEANIE LAM
Low Impact Development Cleared 1/30/2020 JORGE MEJIA LEMUS
Sewer availability Cleared 1/30/2020 JEANIE LAM
Redevelopment Project Area Cleared 2/12/2020 JASON CHAN
ZI Cleared 2/12/2020 JASON CHAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/4/2020 Approved MEL KHACHATOURIAN
BUILDING-Rough-Frame 3/17/2020 Not Ready for Inspection MEL KHACHATOURIAN
Final 3/17/2020 Not Ready for Inspection MEL KHACHATOURIAN
Green Building Final 3/17/2020 Not Ready for Inspection MEL KHACHATOURIAN
Green Building Rough 3/17/2020 Not Ready for Inspection MEL KHACHATOURIAN
MERV13>=Final 3/17/2020 Not Ready for Inspection MEL KHACHATOURIAN
MERV13>=Rough 3/17/2020 Not Ready for Inspection MEL KHACHATOURIAN
SGSOV-Seismic Gas S/O Valve 3/17/2020 SGSOV Not Ready MEL KHACHATOURIAN
Smoke Detectors 3/17/2020 Not Ready for Inspection MEL KHACHATOURIAN
Excavation/Setback/Form/Re-Bar 6/17/2020 Not Ready for Inspection MEL KHACHATOURIAN
Footing/Foundation/Slab 6/17/2020 Partial Inspection MEL KHACHATOURIAN
Excavation/Setback/Form/Re-Bar 6/26/2020 Not Ready for Inspection MEL KHACHATOURIAN
Footing/Foundation/Slab 6/26/2020 Not Ready for Inspection MEL KHACHATOURIAN
Excavation/Setback/Form/Re-Bar 6/30/2020 Not Ready for Inspection MEL KHACHATOURIAN
Excavation/Setback/Form/Re-Bar 7/1/2020 Approved MEL KHACHATOURIAN
BUILDING-Rough-Frame 9/8/2020 Not Ready for Inspection MEL KHACHATOURIAN
ELECTRICAL-Rough 9/8/2020 Not Ready for Inspection MEL KHACHATOURIAN
Green Building Rough 9/8/2020 Not Ready for Inspection MEL KHACHATOURIAN
MERV13>=Rough 9/8/2020 Not Ready for Inspection MEL KHACHATOURIAN
PLUMBING-Rough 9/8/2020 Not Ready for Inspection MEL KHACHATOURIAN
BUILDING-Rough-Frame 9/9/2020 Corrections Issued MEL KHACHATOURIAN
Green Building Rough 9/9/2020 Corrections Issued MEL KHACHATOURIAN
MERV13>=Rough 9/9/2020 Corrections Issued MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 9/22/2020 Partial Approval MEL KHACHATOURIAN
Green Building Rough 9/22/2020 Not Ready for Inspection MEL KHACHATOURIAN
MERV13>=Rough 9/22/2020 Not Ready for Inspection MEL KHACHATOURIAN
ELECTRICAL-Rough 10/9/2020 Corrections Issued MARIO CUEVAS
HVAC-Rough 10/9/2020 Corrections Issued MARIO CUEVAS
PLUMBING-Rough 10/9/2020 Corrections Issued MARIO CUEVAS
ELECTRICAL-Rough 10/15/2020 Not Ready for Inspection MEL KHACHATOURIAN
HVAC-Rough 10/15/2020 Not Ready for Inspection MEL KHACHATOURIAN
Insulation 10/15/2020 Not Ready for Inspection MEL KHACHATOURIAN
Insulation 10/20/2020 Not Ready for Inspection MEL KHACHATOURIAN
PLUMBING-Rough 10/29/2020 Partial Approval MEL KHACHATOURIAN
PLUMBING-Rough 11/2/2020 Approved MEL KHACHATOURIAN
Drywall Nailing 11/13/2020 Partial Approval MEL KHACHATOURIAN
Interior/Exterior Lathing 11/18/2020 Partial Approval MEL KHACHATOURIAN
Sewer 11/18/2020 Approved MEL KHACHATOURIAN
Shower Pan 11/18/2020 Approved MEL KHACHATOURIAN
Interior/Exterior Lathing 11/24/2020 Approved MEL KHACHATOURIAN
BUILDING-Rough-Frame 12/23/2020 Approved MEL KHACHATOURIAN
Final 12/23/2020 Not Ready for Inspection MEL KHACHATOURIAN
Green Building Final 12/23/2020 Approved MEL KHACHATOURIAN
Green Building Rough 12/23/2020 Approved MEL KHACHATOURIAN
MERV13>=Final 12/23/2020 Approved MEL KHACHATOURIAN
MERV13>=Rough 12/23/2020 Approved MEL KHACHATOURIAN
SGSOV-Seismic Gas S/O Valve 12/23/2020 SGSOV Not Ready MEL KHACHATOURIAN
Smoke Detectors 12/23/2020 Not Ready for Inspection MEL KHACHATOURIAN
Final 1/4/2021 Conditional Approval MARIO CUEVAS
SGSOV-Seismic Gas S/O Valve 1/4/2021 SGSOV Approved MARIO CUEVAS
Smoke Detectors 1/4/2021 Approved MARIO CUEVAS