1216-1218 S SPAULDING AVE 90019

Certificate Information: 1216-1218 S SPAULDING AVE 90019

Application / Permit
19016-10000-41033
Plan Check / Job No.
B19LA27256
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
REMODEL OF EXISTING TWO STORY DUPLEX.
Permit Issued
Issued on 3/23/2021
Issuing Office
West Los Angeles
Current Status
Issued on 3/23/2021

Permit Application Status History

Submitted 12/26/2019 APPLICANT
Assigned to Plan Check Engineer 1/7/2020 MANUEL MONTUFAR
Corrections Issued 1/27/2020 MANUEL MONTUFAR
Quality Review Completed 1/28/2020 JASON HEALEY
Building Plans Picked Up 1/31/2020 APPLICANT
Plan Check Approved 5/29/2020 MANUEL MONTUFAR
Issued 3/23/2021 APPLICANT

Permit Application Clearance Information

No Data Available.

Contact Information

Architect Adams,, Lauren Amanda; Lic. No.: C30146 8695 WASHINGTON BLVD SUITE 205      CULVER CITY, CA 90232
Contractor Letter Four Inc; Lic. No.: 1028949-B 8659 WASHINGTON BLVD #205      CULVER CITY, CA 90232
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 8916 LONGDON AVE #C      TEMPLE CITY, CA 91780

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/5/2021 Corrections Issued STUART CHAPMAN
Footing/Foundation/Slab 4/30/2021 Not Ready for Inspection STUART CHAPMAN
Footing/Foundation/Slab 5/4/2021 Approved STUART CHAPMAN
PLUMBING-Rough 6/15/2021 Approved STUART CHAPMAN
Insulation 6/28/2021 Partial Approval CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 7/12/2021 Not Ready for Inspection BRAD BESCOS
ELECTRICAL-Rough 7/12/2021 Not Ready for Inspection BRAD BESCOS
HVAC-Rough 7/12/2021 Not Ready for Inspection BRAD BESCOS
BUILDING-Rough-Frame 7/16/2021 Not Ready for Inspection CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 7/16/2021 Approved CHRISTOPHER DELLEFIELD
HVAC-Rough 7/16/2021 Not Ready for Inspection CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 7/21/2021 Corrections Issued CHRISTOPHER DELLEFIELD
HVAC-Rough 7/21/2021 Not Ready for Inspection CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 8/24/2021 Corrections Issued KATHRYN BUTTERWORTH
HVAC-Rough 8/24/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 10/7/2021 Approved JUSTIN HAWLEY
HVAC-Rough 10/7/2021 Approved JUSTIN HAWLEY
Special/Order Compliance 10/7/2021 Approved STUART CHAPMAN
Insulation 10/14/2021 Approved JUSTIN HAWLEY
Shower Pan 11/3/2021 Approved JOSE AVILA
Drywall Nailing 11/8/2021 Approved JOSE AVILA
Interior/Exterior Lathing 11/8/2021 Approved JOSE AVILA
Gas Test 3/31/2022 Corrections Issued JOSE AVILA