700 N ALAMEDA ST 90012
Certificate Information: 700 N ALAMEDA ST 90012
- Application / Permit
- 19016-10000-41023
- Plan Check / Job No.
- B19LA27241
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- BUILDING BOARDROOM TECHNOLOGY IMPROVEMENTS: 1. UPGRADING AUDIO VISUAL LCD AND DEVICES AT BOARDROOM AND THREE COMMITTEE ROOMS. 2. LED LIGHTING IMPROVEMENT AT BOARDROOM. 3. UPGRADING AUDIO VISUAL AND LIGHTING CONTROL'S EQUIPMENT RACKS IN FOUR AUDIO VISUAL STORAGE ROOMS.
- Permit Issued
- Issued on 12/22/2020
- Issuing Office
- Current Status
- Issued on 12/22/2020
Permit Application Status History
| Submitted | 12/26/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/23/2020 | ZAW HAN |
| Corrections Issued | 1/27/2020 | ZAW HAN |
| Quality Review Completed | 2/19/2020 | HERNAN ARREOLA |
| Disabled Access Plans Picked Up | 2/24/2020 | APPLICANT |
| Applicant returned to address corrections | 4/27/2020 | ZAW HAN |
| Applicant returned to address corrections | 5/21/2020 | ZAW HAN |
| Applicant returned to address corrections | 9/3/2020 | ZAW HAN |
| Green Plans Picked Up | 11/10/2020 | APPLICANT |
| Plan Check Approved | 12/2/2020 | ZAW HAN |
| Issued | 12/22/2020 | APPLICANT |
| Building Plans Picked Up | 1/28/2021 | APPLICANT |
Permit Application Clearance Information
| Green Code | Cleared | 10/2/2020 | VIVIAN LAO |
| DAS Clearance | Cleared | 11/4/2020 | ZAW HAN |
Contact Information
| Contractor | Bernards Bros Inc; Lic. No.: 302007-A | 555 FIRST STREET SAN FERNANDO, CA 91340 |
| Engineer | Rich,, Tracy Robert; Lic. No.: S4831 | 455 CAMINO HERMOSO SAN MARCOS, CA 92078 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| T-Bar Ceiling | 2/22/2021 | Partial Approval | RAFAEL ESPINOZA |
| Drywall Nailing | 3/5/2021 | Partial Approval | RONALD PACHECO |
| Final | 3/22/2023 | Partial Inspection | GREGORY POMISH |
| Green Building Final | 3/22/2023 | Approved | GREGORY POMISH |
| SGSOV-Seismic Gas S/O Valve | 3/22/2023 | SGSOV Approved | GREGORY POMISH |
| Smoke Detectors | 3/22/2023 | Approved | GREGORY POMISH |