16325 W VENTURA BLVD 91436
Certificate Information: 16325 W VENTURA BLVD 91436
- Application / Permit
- 19016-10000-40928
- Plan Check / Job No.
- B19LA27162
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- TENANT IMPROVEMENT TO (E) RETAIL GROCERY STORE, ANCHORAGE FOR ROOFTOP EQUIPMENT, REROOFING, & RESTRIPING
- Permit Issued
- Issued on 6/23/2020
- Issuing Office
- Current Status
- Permit Finaled on 3/23/2021
Permit Application Status History
| Submitted | 12/26/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/16/2020 | LAMAR DAVIS |
| Corrections Issued | 1/22/2020 | LAMAR DAVIS |
| Quality Review Completed | 1/30/2020 | HERNAN ARREOLA |
| Applicant returned to address corrections | 2/21/2020 | LAMAR DAVIS |
| Applicant returned to address corrections | 3/18/2020 | LAMAR DAVIS |
| Disabled Access Plans Picked Up | 4/16/2020 | APPLICANT |
| Green Plans Picked Up | 6/2/2020 | APPLICANT |
| Plan Check Approved | 6/15/2020 | LAMAR DAVIS |
| Issued | 6/23/2020 | APPLICANT |
| Permit Finaled | 3/23/2021 | CAMERON CHABAN |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/11/2020 | JEANETTE VONG |
| Green Code | Cleared | 3/16/2020 | VIVIAN LAO |
| Encroachment in public way | Cleared | 4/16/2020 | GUILLERMO PETRA |
| Food Service Establishment | Cleared | 4/27/2020 | KENNETH BROWNE |
| Miscellaneous | Cleared | 4/29/2020 | LAMAR DAVIS |
| DAS Clearance | Cleared | 5/15/2020 | EDDIE GARIN |
| Specific Plan | Cleared | 5/22/2020 | OLGA AYALA |
| Food establishment approval | Cleared | 6/12/2020 | LACDHS APPROVED |
Contact Information
| Architect | Meyer,, Mariah B; Lic. No.: C37440 | 6700 ANTIOCH PLAZA, SUITE 300 MERRIAM, KS 66204 |
| Contractor | Engineered Structures Inc; Lic. No.: 696242-B | 3330 E LOUISE DRIVE STE 300 MERIDIAN, ID 83642 |
| Engineer | Flanagan,, Joseph Neil; Lic. No.: C58349 | 930 CENTRAL KANSAS CITY, MO 64105 |
Inspector Information
| SEAN GRIFFITH, (818) 374-1102 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/10/2020 | Corrections Issued | ANDREW DORSO |
| Footing/Foundation/Slab | 7/17/2020 | Partial Approval | DANIEL VARNUM |
| Deputy Other (see comments) | 7/20/2020 | Conditional Approval | ANDREW DORSO |
| Footing/Foundation/Slab | 7/31/2020 | Partial Approval | DANIEL VARNUM |
| Footing/Foundation/Slab | 8/6/2020 | Partial Inspection | ANDREW DORSO |
| Deputy Drilled-In Anchors | 8/7/2020 | Conditional Approval | JEFFREY DURAN |
| Deputy Other (see comments) | 8/7/2020 | Conditional Approval | ANDREW DORSO |
| Deputy Reinf. Concrete | 8/7/2020 | Conditional Approval | JEFFREY DURAN |
| Deputy Drilled-In Anchors | 8/13/2020 | Conditional Approval | DANIEL VARNUM |
| Deputy Reinf. Concrete | 8/14/2020 | Conditional Approval | ANDREW DORSO |
| Light Gage Steel Frame | 8/14/2020 | Not Ready for Inspection | DANIEL VARNUM |
| Footing/Foundation/Slab | 8/18/2020 | Partial Inspection | ANDREW DORSO |
| Light Gage Steel Frame | 8/18/2020 | Partial Inspection | ANDREW DORSO |
| Insulation | 8/19/2020 | Partial Inspection | ANDREW DORSO |
| Light Gage Steel Frame | 8/19/2020 | Partial Inspection | ANDREW DORSO |
| Drywall Nailing | 8/21/2020 | Partial Approval | JONATHAN QUACH |
| Light Gage Steel Frame | 8/21/2020 | Partial Approval | JONATHAN QUACH |
| Drywall Nailing | 8/25/2020 | Partial Inspection | ANDREW DORSO |
| Light Gage Steel Frame | 8/25/2020 | Partial Inspection | ANDREW DORSO |
| Insulation | 8/27/2020 | Approved | HAMID PISHEHVAR |
| Drywall Nailing | 8/31/2020 | Partial Approval | DANIEL VARNUM |
| Insulation | 9/4/2020 | Partial Approval | JOHN DODGE |
| Insulation | 9/9/2020 | Partial Approval | ROBERT DAVIS |
| Light Gage Steel Frame | 9/9/2020 | Partial Approval | ROBERT DAVIS |
| Drywall Nailing | 9/15/2020 | Approved | HAMID PISHEHVAR |
| Light Gage Steel Frame | 9/24/2020 | Approved | HAMID PISHEHVAR |
| Structural Steel Frame | 9/24/2020 | Approved | HAMID PISHEHVAR |
| Light Gage Steel Frame | 9/28/2020 | Partial Approval | ROBERT DAVIS |
| Drywall Nailing | 9/30/2020 | Not Ready for Inspection | DANIEL VARNUM |
| Drywall Nailing | 10/5/2020 | Partial Inspection | ANDREW DORSO |
| Light Gage Steel Frame | 10/5/2020 | Partial Inspection | ANDREW DORSO |
| Drywall Nailing | 10/7/2020 | Partial Inspection | ANDREW DORSO |
| Insulation | 10/20/2020 | Partial Approval | DANIEL VARNUM |
| Light Gage Steel Frame | 10/20/2020 | Partial Approval | DANIEL VARNUM |
| Deputy Drilled-In Anchors | 10/28/2020 | Conditional Approval | ROBERT DAVIS |
| Footing/Foundation/Slab | 10/30/2020 | Not Ready for Inspection | ROBERT DAVIS |
| Reinforced Concrete Frame | 12/8/2020 | Partial Approval | ROBERT DAVIS |
| Structural Steel Frame | 12/8/2020 | Conditional Approval | ROBERT DAVIS |
| Final | 3/5/2021 | Not Ready for Inspection | HAMID PISHEHVAR |
| Green Building Final | 3/5/2021 | Approved | HAMID PISHEHVAR |
| SGSOV-Seismic Gas S/O Valve | 3/5/2021 | SGSOV Approved | HAMID PISHEHVAR |
| Smoke Detectors | 3/5/2021 | Partial Approval | HAMID PISHEHVAR |
| Final | 3/23/2021 | Permit Finaled | CAMERON CHABAN |
| Smoke Detectors | 3/23/2021 | Approved | CAMERON CHABAN |