224 1/2 S PARK VIEW ST 90057
Certificate Information: 224 1/2 S PARK VIEW ST 90057
- Application / Permit
- 19016-10000-40810
- Plan Check / Job No.
- B19LA27056
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING DETACHED GARAGE INTO NEW ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. WORK PER PRESCRIPTIVE PROVISIONS.
- Permit Issued
- Issued on 1/9/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/6/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/23/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/23/2019 | GEORGE ALVAREZ |
| Corrections Issued | 12/23/2019 | GEORGE ALVAREZ |
| Plan Check Approved | 12/31/2019 | MICHAEL LOPEZ |
| Issued | 1/9/2020 | LADBS |
| CofO in Progress | 4/29/2021 | ROBERT VORHIS |
| Permit Finaled | 5/6/2021 | DEROLD HAUFF |
| CofO Issued | 5/6/2021 | DEROLD HAUFF |
| Permit Finaled | 5/6/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/23/2019 | ERIK BEASLEY |
| Roof/Waste drainage to street | Cleared | 12/23/2019 | ERIK BEASLEY |
| Sewer availability | Cleared | 12/23/2019 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 12/31/2019 | JAMES KHO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/4/2020 | Corrections Issued | SCOTT FINNILA |
| Footing/Foundation/Slab | 8/14/2020 | Corrections Issued | ROBERT VORHIS |
| Footing/Foundation/Slab | 8/18/2020 | Approved | ROBERT VORHIS |
| ELECTRICAL-Rough | 9/14/2020 | Approved | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 9/14/2020 | Partial Inspection | ROBERT VORHIS |
| PLUMBING-Rough | 9/14/2020 | Approved | ROBERT VORHIS |
| BUILDING-Rough-Frame | 9/29/2020 | Approved | ROBERT VORHIS |
| Green Building Rough | 9/29/2020 | Approved | ROBERT VORHIS |
| Insulation | 9/29/2020 | Partial Inspection | ROBERT VORHIS |
| METHANE-Rough | 9/29/2020 | Approved | ROBERT VORHIS |
| Insulation | 10/15/2020 | Approved | ROBERT VORHIS |
| Drywall Nailing | 10/27/2020 | Not Ready for Inspection | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 10/27/2020 | Not Ready for Inspection | ROBERT VORHIS |
| Interior/Exterior Lathing | 10/27/2020 | Not Ready for Inspection | ROBERT VORHIS |
| Drywall Nailing | 11/5/2020 | Approved | DONALD CRICHLOW |
| Interior/Exterior Lathing | 11/5/2020 | Approved | DONALD CRICHLOW |
| Final | 12/1/2020 | No Access for Inspection | ROBERT VORHIS |
| Green Building Final | 12/1/2020 | Not Ready for Inspection | ROBERT VORHIS |
| SGSOV-Seismic Gas S/O Valve | 12/1/2020 | SGSOV Not Ready | ROBERT VORHIS |
| Smoke Detectors | 12/1/2020 | No Access for Inspection | ROBERT VORHIS |
| Final | 12/10/2020 | Corrections Issued | ROBERT VORHIS |
| Green Building Final | 12/10/2020 | Not Ready for Inspection | ROBERT VORHIS |
| SGSOV-Seismic Gas S/O Valve | 12/10/2020 | SGSOV Not Ready | ROBERT VORHIS |
| Smoke Detectors | 12/10/2020 | Corrections Issued | ROBERT VORHIS |
| ELECTRICAL-Final | 12/22/2020 | Corrections Issued | ROBERT VORHIS |
| Final | 12/22/2020 | Not Ready for Inspection | ROBERT VORHIS |
| Gas Test | 12/22/2020 | Approved | ROBERT VORHIS |
| Green Building Final | 12/22/2020 | Approved | ROBERT VORHIS |
| HVAC-Final | 12/22/2020 | Approved | ROBERT VORHIS |
| PLUMBING-Final | 12/22/2020 | Not Ready for Inspection | ROBERT VORHIS |
| SGSOV-Seismic Gas S/O Valve | 12/22/2020 | SGSOV Not Ready | ROBERT VORHIS |
| Smoke Detectors | 12/22/2020 | Approved | ROBERT VORHIS |
| ELECTRICAL-Final | 12/30/2020 | Not Ready for Inspection | ROBERT VORHIS |
| PLUMBING-Final | 12/30/2020 | Approved | ROBERT VORHIS |
| ELECTRICAL-Final | 12/31/2020 | Not Ready for Inspection | ROBERT VORHIS |
| ELECTRICAL-Final | 1/5/2021 | Corrections Issued | ROBERT VORHIS |
| ELECTRICAL-Final | 1/20/2021 | Partial Approval | FREDDIE RIVERA |
| Final | 1/28/2021 | Corrections Issued | ROBERT VORHIS |
| SGSOV-Seismic Gas S/O Valve | 1/28/2021 | SGSOV Not Ready | ROBERT VORHIS |
| ELECTRICAL-Final | 2/23/2021 | Approved | ROBERT VORHIS |
| Final | 2/23/2021 | Not Ready for Inspection | ROBERT VORHIS |
| SGSOV-Seismic Gas S/O Valve | 2/23/2021 | SGSOV Approved | ROBERT VORHIS |
| Final | 4/21/2021 | Conditional Approval | ROBERT VORHIS |