19510 W VENTURA BLVD 91356

Certificate Information: 19510 W VENTURA BLVD 91356

Application / Permit
19016-10000-40781
Plan Check / Job No.
B19LA27023
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
INTERIOR AND EXTERIOR T.I. OF (E) OFFICE & BANK. NEW ALUMINUM SCREEN WALL AT FRONT FACADE. DEMOLISH (E) CANOPY
Permit Issued
Issued on 10/23/2020
Issuing Office
Current Status
Issued on 10/23/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/23/2019 APPLICANT
Assigned to Plan Check Engineer 1/9/2020 LAMAR DAVIS
Corrections Issued 1/13/2020 LAMAR DAVIS
Quality Review Completed 1/17/2020 HERNAN ARREOLA
Building Plans Picked Up 1/21/2020 APPLICANT
Disabled Access Plans Picked Up 2/5/2020 APPLICANT
Applicant returned to address corrections 6/24/2020 LAMAR DAVIS
Green Plans Picked Up 10/15/2020 APPLICANT
Plan Check Approved 10/21/2020 LAMAR DAVIS
Issued 10/23/2020 APPLICANT

Permit Application Clearance Information

"D" conditions Cleared 6/9/2020 KENTON TRINH
Miscellaneous Cleared 6/9/2020 KENTON TRINH
Miscellaneous Cleared 6/9/2020 KENTON TRINH
Miscellaneous Cleared 6/9/2020 KENTON TRINH
Miscellaneous Cleared 6/9/2020 KENTON TRINH
Green Code Cleared 6/23/2020 KHEDER ALRAZAA
Fire Marshall Fire Life Safety Cleared 7/16/2020 ANDREW KO
"Q" conditions Cleared 8/3/2020 KENTON TRINH
Miscellaneous Cleared 8/28/2020 LAMAR DAVIS
Specific Plan Cleared 9/22/2020 MARIANNE KING
DAS Clearance Cleared 9/23/2020 EDDIE GARIN

Contact Information

Architect Miller,, Brent Todd; Lic. No.: C30535 10918 WAGNER STREET      CULVER CITY, CA 90230
Contractor J M I Construction Inc; Lic. No.: 993077-B P O BOX 70756      PASADENA, CA 91117
Engineer Tanouye,, Russell; Lic. No.: S2850 888 S FIGUEROA ST 18TH FLOOR      LOS ANGELES, CA 90017

Inspector Information

BRIAN KELLY, (818) 374-1127 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/18/2020 Partial Approval DANIEL VARNUM
Green Building Rough 6/21/2021 Approved HAMID PISHEHVAR
Wood Frame 6/21/2021 Partial Approval HAMID PISHEHVAR
Drywall Nailing 6/30/2021 Partial Approval DANIEL VARNUM
Drywall Nailing 8/23/2021 Partial Approval CAMERON CHABAN
Drywall Nailing 3/23/2022 Partial Approval DANIEL VARNUM
Drywall Nailing 5/3/2022 Approved CAMERON CHABAN
Final 6/28/2022 Not Ready for Inspection DANIEL VARNUM
Green Building Final 6/28/2022 Not Ready for Inspection DANIEL VARNUM
SGSOV-Seismic Gas S/O Valve 6/28/2022 SGSOV Not Ready DANIEL VARNUM
Smoke Detectors 6/28/2022 Not Ready for Inspection DANIEL VARNUM
Wood Frame 6/28/2022 Not Ready for Inspection DANIEL VARNUM
Final 9/8/2022 Not Ready for Inspection GREGORY POMISH
Green Building Final 9/8/2022 Not Ready for Inspection GREGORY POMISH
SGSOV-Seismic Gas S/O Valve 9/8/2022 SGSOV Not Ready GREGORY POMISH
Smoke Detectors 9/8/2022 Approved GREGORY POMISH
Wood Frame 9/8/2022 Approved GREGORY POMISH
SGSOV-Seismic Gas S/O Valve 12/5/2023 SGSOV Not Ready STEVEN LEVITT
Final 12/4/2025 Corrections Issued JOHN KITCKO
Green Building Final 12/4/2025 Not Ready for Inspection JOHN KITCKO
SGSOV-Seismic Gas S/O Valve 12/4/2025 SGSOV Not Ready JOHN KITCKO
Final 12/9/2025 Corrections Issued BRIAN KELLY
Green Building Final 12/9/2025 Not Ready for Inspection BRIAN KELLY
SGSOV-Seismic Gas S/O Valve 12/9/2025 SGSOV Not Ready BRIAN KELLY
Final 12/15/2025 Not Ready for Inspection BRIAN KELLY
Green Building Final 12/15/2025 Not Ready for Inspection BRIAN KELLY
SGSOV-Seismic Gas S/O Valve 12/15/2025 SGSOV Not Ready BRIAN KELLY