14238 W DICKENS ST 91423
Certificate Information: 14238 W DICKENS ST 91423
- Application / Permit
- 19016-10000-40769
- Plan Check / Job No.
- B19LA27007
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH. 93. INSTALL 1 STEEL SPECIAL CANTILEVER COLUMN.
- Permit Issued
- Issued on 6/9/2021
- Issuing Office
- Current Status
- Issued on 6/9/2021
Permit Application Status History
| Submitted | 12/20/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/15/2020 | DANIEL SANJUAN |
| Corrections Issued | 1/29/2020 | DANIEL SANJUAN |
| Quality Review Completed | 1/30/2020 | SAI KHUM |
| Building Plans Picked Up | 1/31/2020 | APPLICANT |
| Plan Check Approved | 2/12/2020 | DANIEL SANJUAN |
| Issued | 6/9/2021 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 2/12/2020 | EMIL KYUPELYAN |
| Eng Process Fee Ord 176,300 | Cleared | 2/12/2020 | PAMELA TENEZA |
| Tenant Habitability Plan | Cleared | 2/2/2021 | PHILLIP MUNGUIA |
Contact Information
| Contractor | Potkin Brian Edward; Lic. No.: 470714-B | 14011 VENTURA BLVD #204 SHERMAN OAKS, CA 91423 |
| Engineer | , ; Lic. No.: E77182 | 15445 VENTURA BLVD 25 SHERMAN OAKS, CA 91403 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/29/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Footing/Foundation/Slab | 8/10/2021 | Corrections Issued | JOE VELASQUEZ |
| Deputy Drilled-In Anchors | 8/12/2021 | No Access for Inspection | JOE VELASQUEZ |
| Deputy Steel/Welding | 8/13/2021 | No Access for Inspection | JOE VELASQUEZ |
| Footing/Foundation/Slab | 8/17/2021 | Approved | JOE VELASQUEZ |
| Deputy Reinf. Concrete | 8/19/2021 | Conditional Approval | KENNETH ROBERTS |
| Deputy Steel/Welding | 9/9/2021 | Conditional Approval | JEFFREY DURAN |
| Wood Frame | 9/22/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 10/8/2021 | Partial Approval | PAUL DAVIDSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/28/2021 | Approved | JOE VELASQUEZ |
| Interior/Exterior Lathing | 11/8/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Interior/Exterior Lathing | 11/12/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Interior/Exterior Lathing | 11/16/2021 | Approved | JOE VELASQUEZ |