10538 W EDGELEY PL 90024
Certificate Information: 10538 W EDGELEY PL 90024
- Application / Permit
- 19016-10000-40726
- Plan Check / Job No.
- B19LA26964
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL EXISTING 2-STORY SINGLE FAMILY DWELLING. CHANGE OUT ALL WINDOWS AND PATIO DOORS. EXISTING BUILDING FOOTPRINT - NO ADDITION.
- Permit Issued
- Issued on 6/29/2020
- Issuing Office
- Current Status
- Permit Finaled on 3/3/2022
Permit Application Status History
| Submitted | 12/20/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/7/2020 | EMMANUEL MARTINEZ |
| Corrections Issued | 1/9/2020 | EMMANUEL MARTINEZ |
| Quality Review Completed | 1/15/2020 | ARMEN JIVALAGIAN |
| Building Plans Picked Up | 1/17/2020 | APPLICANT |
| Applicant returned to address corrections | 4/6/2020 | SERGIO GUTIERREZ |
| Applicant returned to address corrections | 4/16/2020 | SERGIO GUTIERREZ |
| Plan Check Approved | 5/5/2020 | SERGIO GUTIERREZ |
| Issued | 6/29/2020 | APPLICANT |
| Permit Finaled | 3/1/2022 | OGANES TARAKHCHYAN |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 2/4/2020 | THOMAS LANG |
| Grading Pre-Inspection | Cleared | 3/9/2020 | KIRK LINKLATER |
| Eng Process Fee Ord 176,300 | Cleared | 4/15/2020 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 4/15/2020 | ANTHONY MAINEZ |
| Miscellaneous | Cleared | 4/21/2020 | NIKTA MOUSAVI |
Contact Information
| Contractor | Prestige Contracting; Lic. No.: 543415-B | P O BOX 775 ACTON, CA 93510 |
| Engineer | Guzman,, Martin; Lic. No.: C79193 | 4054 W 165TH STREET LAWNDALE, CA 90260 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/22/2020 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 11/16/2020 | Approved | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Rough | 4/5/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 4/5/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 4/5/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 4/5/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Underground Mechanical | 4/16/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Deputy Wood Construction | 4/22/2021 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Rough | 4/28/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 5/11/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 5/26/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Special/Order Compliance | 5/26/2021 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 5/27/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Wood Frame | 5/27/2021 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 6/1/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 6/1/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Interior/Exterior Lathing | 6/23/2021 | Partial Inspection | AMY COLIN |
| BUILDING-Rough-Frame | 7/6/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Drywall Nailing | 7/6/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Rough | 7/6/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 7/6/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Insulation | 7/6/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Shower Pan | 7/6/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Interior/Exterior Lathing | 7/9/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Gas Test | 1/6/2022 | Partial Approval | CHRISTOPHER WILSON |
| Final | 2/23/2022 | Corrections Issued | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 2/23/2022 | SGSOV Approved | BRENDAN LOONEY |
| Smoke Detectors | 2/23/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| Final | 3/1/2022 | Permit Finaled | OGANES TARAKHCHYAN |
| Smoke Detectors | 3/1/2022 | Approved | OGANES TARAKHCHYAN |