1152 W 48TH ST 90037
Certificate Information: 1152 W 48TH ST 90037
- Application / Permit
- 19016-10000-40690
- Plan Check / Job No.
- B19LA26926
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ADU AT REAR OF LOT.
- Permit Issued
- Issued on 1/26/2021
- Issuing Office
- Current Status
- CofO Issued on 12/21/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/20/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/20/2019 | ADAM HEGAZI |
| Corrections Issued | 12/20/2019 | ADAM HEGAZI |
| Applicant returned to address corrections | 4/21/2020 | JESSE ARELLANO |
| Applicant returned to address corrections | 6/5/2020 | LUKE GONZALES |
| Applicant returned to address corrections | 8/25/2020 | RICARDO RAMIREZ |
| Plan Check Approved | 12/17/2020 | RICARDO RAMIREZ |
| Issued | 1/26/2021 | APPLICANT |
| Building Plans Picked Up | 1/28/2021 | APPLICANT |
| CofO in Progress | 11/17/2021 | SABAS ALONSO |
| Permit Finaled | 12/21/2021 | RONALD MYRICK |
| CofO Issued | 12/21/2021 | RONALD MYRICK |
| Permit Finaled | 12/21/2021 | RONALD MYRICK |
Permit Application Clearance Information
| Address approval | Cleared | 1/31/2020 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 2/7/2020 | AVALYN KAMACHI |
| Hydrant and Access approval | Cleared | 9/30/2020 | KURT CORRAL |
| Community Plan Implem. Overlay | Cleared | 12/1/2020 | HELEN JADALI |
| Roof/Waste drainage to street | Cleared | 12/9/2020 | THOMAS LANG |
| Sewer availability | Cleared | 12/9/2020 | THOMAS LANG |
Contact Information
| Contractor | Perfitt John; Lic. No.: 1034808-B | 180 SOUTH CITRUS LOS ANGELES, CA 90036 |
| Engineer | Mahlow,, Elizabeth Joy Johnson; Lic. No.: C80463 | 4215 TOLAND WAY LOS ANGELES, CA 90065 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/19/2021 | Partial Approval | ALEJANDRO DE ARTOLA |
| Sewer | 3/19/2021 | Approved | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 3/19/2021 | Approved | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 3/25/2021 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 3/30/2021 | Approved | ROBERT MCDOWELL |
| Excavation/Setback/Form/Re-Bar | 3/31/2021 | No Access for Inspection | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 3/31/2021 | Off-Hour Fees Due | |
| Excavation/Setback/Form/Re-Bar | 4/5/2021 | Approved | ROBERT MCDOWELL |
| Excavation/Setback/Form/Re-Bar | 4/7/2021 | Not Ready for Inspection | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 4/16/2021 | Approved | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 5/4/2021 | Conditional Approval | ROBERT MCDOWELL |
| ELECTRICAL-Rough | 5/4/2021 | Approved | ROBERT MCDOWELL |
| HVAC-Rough | 5/4/2021 | Not Ready for Inspection | ROBERT MCDOWELL |
| PLUMBING-Rough | 5/4/2021 | Approved | ROBERT MCDOWELL |
| Insulation | 5/10/2021 | Approved | ROBERT MCDOWELL |
| Drywall Nailing | 5/21/2021 | No Access for Inspection | FREDDIE RIVERA |
| Green Building Rough | 5/21/2021 | No Access for Inspection | FREDDIE RIVERA |
| Service/Power Release | 5/21/2021 | No Access for Inspection | FREDDIE RIVERA |
| Drywall Nailing | 5/28/2021 | Conditional Approval | SABAS ALONSO |
| Green Building Rough | 5/28/2021 | Not Ready for Inspection | SABAS ALONSO |
| Service/Power Release | 5/28/2021 | Not Ready for Inspection | SABAS ALONSO |
| Gas Test | 6/25/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Gas Test | 6/29/2021 | Partial Approval | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 7/7/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 7/9/2021 | Partial Approval | HORACE FULTZ |
| ELECTRICAL-Final | 10/4/2021 | Not Ready for Inspection | SABAS ALONSO |
| HVAC-Final | 10/4/2021 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Final | 10/4/2021 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 10/13/2021 | Not Ready for Inspection | SABAS ALONSO |
| HVAC-Final | 10/13/2021 | Approved | SABAS ALONSO |
| PLUMBING-Final | 10/13/2021 | Approved | SABAS ALONSO |
| Service/Power Release | 10/15/2021 | Approved | SABAS ALONSO |
| Final | 10/21/2021 | Corrections Issued | SABAS ALONSO |
| Gas Test | 10/21/2021 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 10/21/2021 | SGSOV Approved | SABAS ALONSO |
| Verify Sprinkler Sign Off | 10/21/2021 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 11/16/2021 | Approved | SABAS ALONSO |
| Drywall Nailing | 11/16/2021 | Approved | SABAS ALONSO |
| Final | 11/16/2021 | OK to Issue CofO | SABAS ALONSO |
| Green Building Final | 11/16/2021 | Approved | SABAS ALONSO |
| Green Building Rough | 11/16/2021 | Approved | SABAS ALONSO |
| Smoke Detectors | 11/16/2021 | Approved | SABAS ALONSO |