4211 N VERDUGO ROAD 90065

Certificate Information: 4211 N VERDUGO ROAD 90065

Application / Permit
19016-10000-40552
Plan Check / Job No.
B19LA26823
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT
Permit Issued
Issued on 2/14/2020
Issuing Office
Metro
Current Status
CofO Issued on 12/18/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/19/2019 APPLICANT
Assigned to Plan Check Engineer 1/2/2020 MONICA RAMIREZ
Corrections Issued 1/2/2020 MONICA RAMIREZ
Plan Check Approved 2/14/2020 FARSHAD ALIMOHAMADI
Issued 2/14/2020 LADBS
CofO in Progress 8/25/2021 CRAIG VAUGHAN
Permit Finaled 12/18/2021 DEROLD HAUFF
CofO Issued 12/18/2021 DEROLD HAUFF
Permit Finaled 12/18/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/2/2020 ERIK BEASLEY
BHO/Hillside ordinance Cleared 1/2/2020 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 1/2/2020 ERIK BEASLEY
Grading Pre-Inspection Cleared 1/2/2020 KIRK LINKLATER
Sewer availability Cleared 1/2/2020 ERIK BEASLEY
Supp. Use District POD/CDO/TDO Cleared 2/10/2020 ADRINEH MELKONIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Santos,, Michael Fernandez; Lic. No.: C77657 16202 ORION AVE      CHINO, CA 91708

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/26/2020 Corrections Issued BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 3/2/2020 Approved COREY HUPP
BUILDING-Rough-Frame 2/24/2021 Not Ready for Inspection BRIAN SULLIVAN
ELECTRICAL-Rough 2/24/2021 Not Ready for Inspection BRIAN SULLIVAN
Green Building Rough 2/24/2021 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Rough 2/24/2021 Corrections Issued BRIAN SULLIVAN
Underground Mechanical 2/24/2021 Corrections Issued BRIAN SULLIVAN
ELECTRICAL-Rough 3/2/2021 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 3/2/2021 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 3/8/2021 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 3/8/2021 Corrections Issued CRAIG VAUGHAN
Green Building Rough 3/8/2021 Approved CRAIG VAUGHAN
HVAC-Rough 3/8/2021 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 3/8/2021 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 3/9/2021 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 3/9/2021 Approved CRAIG VAUGHAN
PLUMBING-Rough 3/9/2021 Approved CRAIG VAUGHAN
Insulation 3/12/2021 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 3/12/2021 Approved CRAIG VAUGHAN
Drywall Nailing 3/17/2021 Approved BRIAN SULLIVAN
ELECTRICAL-Final 8/11/2021 Corrections Issued CRAIG VAUGHAN
Final 8/11/2021 Not Ready for Inspection CRAIG VAUGHAN
Gas Test 8/11/2021 Approved CRAIG VAUGHAN
Green Building Final 8/11/2021 Approved CRAIG VAUGHAN
HVAC-Final 8/11/2021 Approved CRAIG VAUGHAN
PLUMBING-Final 8/11/2021 Corrections Issued CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 8/11/2021 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 8/11/2021 Approved CRAIG VAUGHAN
ELECTRICAL-Final 8/24/2021 Approved CRAIG VAUGHAN
Final 8/24/2021 OK to Issue CofO CRAIG VAUGHAN
PLUMBING-Final 8/24/2021 Approved CRAIG VAUGHAN