20801 W VENTURA BLVD 91364
Certificate Information: 20801 W VENTURA BLVD 91364
- Application / Permit
- 19016-10000-40546
- Plan Check / Job No.
- B19LA26818
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- Tenant improvement for existing 1-story Type VB retail store (Target) to remodel sale floor, restrooms, fitting rooms, guest service, offices, grocery area, stockroom and cafe. General scope of work includes fixture, wall finish, floor finish and lighting updates. Remove and replace a portion of the concrete slab. Work in cafe area includes beverage bar closure with addition of snack bar.
- Permit Issued
- Issued on 1/11/2021
- Issuing Office
- Current Status
- Permit Finaled on 2/18/2022
Permit Application Status History
| Submitted | 12/19/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/7/2020 | QUAN NGHIEM |
| Disabled Access Plans Picked Up | 1/10/2020 | APPLICANT |
| Corrections Issued | 2/3/2020 | QUAN NGHIEM |
| Quality Review Completed | 2/4/2020 | ALLEN MANALANSAN |
| Building Plans Picked Up | 2/6/2020 | APPLICANT |
| Applicant returned to address corrections | 2/27/2020 | QUAN NGHIEM |
| Applicant returned to address corrections | 5/27/2020 | QUAN NGHIEM |
| Applicant returned to address corrections | 9/9/2020 | QUAN NGHIEM |
| Green Plans Picked Up | 12/28/2020 | APPLICANT |
| Plan Check Approved | 1/8/2021 | QUAN NGHIEM |
| Issued | 1/11/2021 | APPLICANT |
| Permit Finaled | 2/17/2022 | DANIEL VARNUM |
Permit Application Clearance Information
| Green Code | Cleared | 2/19/2020 | KHEDER ALRAZAA |
| DAS Clearance | Cleared | 3/2/2020 | SHINE LIN |
| Low Impact Development | Cleared | 3/2/2020 | ORVAL HERNANDEZ-MARCI |
| Miscellaneous | Cleared | 11/16/2020 | DANG NGUYEN |
| Food Service Establishment | Cleared | 12/2/2020 | JASH PATEL |
| Specific Plan | Cleared | 12/8/2020 | ANDREW JORGENSEN |
| Food establishment approval | Cleared | 1/8/2021 | LACDHS APPROVED |
Contact Information
| Architect | Klopfer,, Scott Merrill; Lic. No.: C38207 | 21145 QUAY STREET NW OAK GROVE, MN 55303 |
| Contractor | A C R Builders Inc; Lic. No.: 953670-B | 23372 MADERO STE E MISSION VIEJO, CA 92691 |
Inspector Information
| BRIAN KELLY, (818) 374-1127 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/25/2021 | Approved | HAMID PISHEHVAR |
| Deputy Steel/Welding | 1/25/2021 | Approved | HAMID PISHEHVAR |
| Deputy Other (see comments) | 2/9/2021 | Approved | HAMID PISHEHVAR |
| Deputy Other (see comments) | 2/10/2021 | Approved | HAMID PISHEHVAR |
| Deputy Other (see comments) | 2/11/2021 | Conditional Approval | CAMERON CHABAN |
| Deputy Other (see comments) | 2/12/2021 | Conditional Approval | DANIEL VARNUM |
| Deputy Reinf. Concrete | 2/16/2021 | No Result Entered | GARY EWELL |
| Footing/Foundation/Slab | 2/18/2021 | Partial Inspection | ANDREW DORSO |
| Footing/Foundation/Slab | 3/26/2021 | Partial Approval | CAMERON CHABAN |
| Deputy Drilled-In Anchors | 4/21/2021 | Conditional Approval | CAMERON CHABAN |
| Deputy Reinf. Concrete | 4/22/2021 | Conditional Approval | CAMERON CHABAN |
| Footing/Foundation/Slab | 4/22/2021 | Partial Inspection | JEFFREY FULTON |
| Deputy Reinf. Concrete | 4/26/2021 | Conditional Approval | JEFFREY DURAN |
| Deputy Reinf. Masonry | 5/3/2021 | Conditional Approval | ANDREW DORSO |
| Green Building Rough | 5/27/2021 | Not Ready for Inspection | DANIEL VARNUM |
| Verify Sprinkler Sign Off | 5/27/2021 | Not Ready for Inspection | DANIEL VARNUM |
| Wood Frame | 5/27/2021 | Not Ready for Inspection | DANIEL VARNUM |
| Green Building Rough | 6/7/2021 | Not Ready for Inspection | ANDREW DORSO |
| Light Gage Steel Frame | 6/7/2021 | Partial Inspection | ANDREW DORSO |
| Verify Sprinkler Sign Off | 6/7/2021 | Not Ready for Inspection | ANDREW DORSO |
| Drywall Nailing | 6/9/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Drywall Nailing | 6/11/2021 | Partial Approval | CAMERON CHABAN |
| Drywall Nailing | 6/14/2021 | Partial Approval | CAMERON CHABAN |
| Drywall Nailing | 6/15/2021 | Partial Inspection | ANDREW DORSO |
| Green Building Rough | 7/2/2021 | Partial Approval | CAMERON CHABAN |
| Light Gage Steel Frame | 7/2/2021 | Partial Approval | CAMERON CHABAN |
| Verify Sprinkler Sign Off | 7/2/2021 | Not Ready for Inspection | CAMERON CHABAN |
| Drywall Nailing | 7/9/2021 | Partial Inspection | ANDREW DORSO |
| Drywall Nailing | 7/15/2021 | Partial Inspection | ANDREW DORSO |
| Green Building Rough | 7/27/2021 | Not Ready for Inspection | ANDREW DORSO |
| Light Gage Steel Frame | 7/27/2021 | Partial Inspection | ANDREW DORSO |
| Verify Sprinkler Sign Off | 7/27/2021 | Not Ready for Inspection | ANDREW DORSO |
| Deputy Drilled-In Anchors | 7/28/2021 | Conditional Approval | DANIEL VARNUM |
| Drywall Nailing | 7/30/2021 | Partial Approval | DANIEL VARNUM |
| Deputy Drilled-In Anchors | 8/3/2021 | Conditional Approval | JEFFREY DURAN |
| Deputy Reinf. Concrete | 8/3/2021 | Conditional Approval | JEFFREY DURAN |
| Deputy Drilled-In Anchors | 8/4/2021 | Conditional Approval | DANIEL VARNUM |
| Partition/T-Bar Ceiling | 8/9/2021 | Not Ready for Inspection | ANDREW DORSO |
| Green Building Rough | 8/10/2021 | Approved | DANIEL VARNUM |
| T-Bar Ceiling | 8/10/2021 | Partial Approval | DANIEL VARNUM |
| Verify Sprinkler Sign Off | 8/10/2021 | Partial Approval | DANIEL VARNUM |
| Wood Frame | 8/10/2021 | Partial Approval | DANIEL VARNUM |
| Deputy Drilled-In Anchors | 8/12/2021 | Conditional Approval | ANDREW DORSO |
| Drywall Nailing | 8/13/2021 | Partial Approval | DANIEL VARNUM |
| Drywall Nailing | 8/18/2021 | Partial Inspection | ANDREW DORSO |
| Light Gage Steel Frame | 8/18/2021 | Partial Inspection | ANDREW DORSO |
| Drywall Nailing | 8/24/2021 | Partial Approval | DANIEL VARNUM |
| Floor/Roof Diaphrgm/Shear Wall | 8/25/2021 | Partial Approval | CAMERON CHABAN |
| Verify Sprinkler Sign Off | 9/10/2021 | Partial Inspection | CAMERON CHABAN |
| Wood Frame | 9/10/2021 | Conditional Approval | CAMERON CHABAN |
| Drywall Nailing | 9/16/2021 | Partial Approval | DANIEL VARNUM |
| Partition/T-Bar Ceiling | 9/17/2021 | Partial Approval | DANIEL VARNUM |
| Drywall Nailing | 10/15/2021 | Partial Approval | DANIEL VARNUM |
| Green Building Final | 11/22/2021 | Approved | DANIEL VARNUM |
| Final | 12/27/2021 | Corrections Issued | ROBERT DAVIS |
| SGSOV-Seismic Gas S/O Valve | 12/27/2021 | SGSOV Approved | ROBERT DAVIS |
| Smoke Detectors | 12/27/2021 | Approved | ROBERT DAVIS |
| Verify Sprinkler Sign Off | 12/27/2021 | Approved | ROBERT DAVIS |
| Wood Frame | 12/27/2021 | Approved | ROBERT DAVIS |
| Final | 2/17/2022 | Permit Finaled | DANIEL VARNUM |