910 E ROSE AVE 90291
Certificate Information: 910 E ROSE AVE 90291
- Application / Permit
- 19016-10000-40528
- Plan Check / Job No.
- B19LA26798
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED CONVERSION OF GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229; ALL WORK PER WFPP
- Permit Issued
- Issued on 3/12/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/21/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/19/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/19/2019 | SINA KHOSRAVI |
| Corrections Issued | 12/19/2019 | SINA KHOSRAVI |
| Plan Check Approved | 2/13/2020 | ADAM HEGAZI |
| Issued | 3/12/2020 | LADBS |
| CofO in Progress | 3/26/2021 | JOHNNY MIRANDA |
| Permit Finaled | 4/21/2022 | DANIEL ORRANTE |
| CofO Issued | 4/21/2022 | DANIEL ORRANTE |
| Permit Finaled | 4/21/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 12/23/2019 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 12/23/2019 | THOMAS LANG |
| Sewer availability | Cleared | 12/23/2019 | THOMAS LANG |
| Specific Plan | Cleared | 12/23/2019 | COLLINS ALLAN |
| ZA Case | Cleared | 12/23/2019 | SOPHIE GABEL-SCHEINBAU |
| Construction near power lines | Cleared | 2/12/2020 | RIDWAN HARDY |
Contact Information
| Contractor | Construction Plus; Lic. No.: 878320-B | P O BOX 261695 SAN DIEGO, CA 92196 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/25/2020 | Partial Approval | DAVID HEINE |
| Footing/Foundation/Slab | 3/27/2020 | Approved | DAVID HEINE |
| BUILDING-Rough-Frame | 4/21/2020 | Partial Approval | DAVID HEINE |
| ELECTRICAL-Rough | 4/21/2020 | Not Ready for Inspection | DAVID HEINE |
| Green Building Rough | 4/21/2020 | Not Ready for Inspection | DAVID HEINE |
| PLUMBING-Rough | 4/21/2020 | Not Ready for Inspection | DAVID HEINE |
| ELECTRICAL-Rough | 4/23/2020 | Not Ready for Inspection | DAVID HEINE |
| PLUMBING-Rough | 4/23/2020 | Approved | DAVID HEINE |
| BUILDING-Rough-Frame | 4/24/2020 | Approved | DAVID HEINE |
| ELECTRICAL-Rough | 4/24/2020 | Approved | DAVID HEINE |
| Green Building Rough | 4/24/2020 | Approved | DAVID HEINE |
| Insulation | 4/29/2020 | Approved | DAVID HEINE |
| Drywall Nailing | 5/15/2020 | Approved | DAVID HEINE |
| Final | 6/12/2020 | Not Ready for Inspection | DAVID HEINE |
| Interior/Exterior Lathing | 6/12/2020 | Approved | DAVID HEINE |
| SGSOV-Seismic Gas S/O Valve | 6/12/2020 | SGSOV Not Ready | DAVID HEINE |
| Smoke Detectors | 6/12/2020 | Not Ready for Inspection | DAVID HEINE |
| Final | 10/7/2020 | Conditional Approval | DAVID HEINE |
| Green Building Final | 10/7/2020 | Corrections Issued | DAVID HEINE |
| SGSOV-Seismic Gas S/O Valve | 10/7/2020 | SGSOV Approved | DAVID HEINE |
| Smoke Detectors | 10/7/2020 | Approved | DAVID HEINE |
| Final | 3/2/2021 | Corrections Issued | JOHNNY MIRANDA |
| Green Building Final | 3/2/2021 | Corrections Issued | JOHNNY MIRANDA |
| ELECTRICAL-Final | 3/4/2021 | Approved | JOHNNY MIRANDA |
| HVAC-Final | 3/4/2021 | Corrections Issued | JOHNNY MIRANDA |
| PLUMBING-Final | 3/4/2021 | Approved | JOHNNY MIRANDA |
| Service/Power Release | 3/4/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| Final | 3/26/2021 | OK to Issue CofO | JOHNNY MIRANDA |
| Green Building Final | 3/26/2021 | Approved | JOHNNY MIRANDA |
| HVAC-Final | 3/26/2021 | Approved | JOHNNY MIRANDA |
| Service/Power Release | 3/26/2021 | Approved | JOHNNY MIRANDA |