2540 S 3RD AVE 90018
Certificate Information: 2540 S 3RD AVE 90018
- Application / Permit
- 19016-10000-40252
- Plan Check / Job No.
- B19LA26574
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft-Story seismic retrofit per LABC Chapter 93: SOFT STORY SEISMIC REINFORCEMENT AT BUILDING PARKING GARAGE USING (2) STEEL SPECIAL CANTILEVERED COLUMNS WITH GRADE BEAMS.
- Permit Issued
- Issued on 2/24/2021
- Issuing Office
- Current Status
- CofC Issued on 4/20/2021
Permit Application Status History
| Submitted | 12/18/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/8/2020 | DANIEL SANJUAN |
| Corrections Issued | 1/24/2020 | DANIEL SANJUAN |
| Quality Review Completed | 2/3/2020 | HANS SANTIAGO |
| Plan Check Approved | 5/6/2020 | DANIEL SANJUAN |
| Issued | 2/24/2021 | APPLICANT |
| OK for CofC | 4/12/2021 | DARRYL ARNOLD |
| CofC Issued | 4/20/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| HPOZ | Cleared | 4/16/2020 | DEEPEAKA DHALIWAL |
| Tenant Habitability Plan | Cleared | 2/22/2021 | STEVEN HOFSTAD |
Contact Information
| Contractor | Cal - Quake Construction Inc; Lic. No.: 759817-B | 636 NORTH FORMOSA AVENUE LOS ANGELES, CA 90036 |
| Engineer | Ni,, Zhang Yuan; Lic. No.: C68149 | 743 S SIERRA VISTA AVE C ALHAMBRA, CA 91801 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/4/2021 | Approved | DARRYL ARNOLD |
| Deputy Steel/Welding | 3/12/2021 | Conditional Approval | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 3/16/2021 | Conditional Approval | DARRYL ARNOLD |
| Excavation/Setback/Form/Re-Bar | 3/17/2021 | Approved | DARRYL ARNOLD |
| Structural Steel Frame | 3/17/2021 | Approved | DARRYL ARNOLD |
| Wood Frame | 3/17/2021 | Approved | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 3/18/2021 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 3/26/2021 | Corrections Issued | MARK FERRARI |
| Final | 4/6/2021 | Not Ready for Inspection | DARRYL ARNOLD |
| METHANE-Final | 4/6/2021 | Not Ready for Inspection | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 4/6/2021 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 4/6/2021 | Not Ready for Inspection | DARRYL ARNOLD |
| Final | 4/12/2021 | OK for CofC | DARRYL ARNOLD |
| METHANE-Final | 4/12/2021 | Approved | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 4/12/2021 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 4/12/2021 | Approved | DARRYL ARNOLD |