5910 N FIGUEROA ST 90042

Certificate Information: 5910 N FIGUEROA ST 90042

Application / Permit
19016-10000-40240
Plan Check / Job No.
B19LA26567
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Retail
Work Description
TENANT IMPROVEMENT TO AN (E) RETAIL SPACE. COMBINE 3 RETAIL SPACE TO ONE RETAIL SPACE .PROPOSED WORK INCLUDES, NEW INTERIOR PARTITIONS, RESTROOMS, LIGHTING AND NEW ROOF FINISH. ADD ROOF-TOP EQUIPMENT.
Permit Issued
Issued on 5/12/2020
Issuing Office
Current Status
Permit Finaled on 3/17/2021

Permit Application Status History

Submitted 12/20/2019 APPLICANT
Green Plans Picked Up 1/7/2020 APPLICANT
Assigned to Plan Check Engineer 1/9/2020 ARSALAN SHABESTARI
Corrections Issued 1/13/2020 ARSALAN SHABESTARI
Disabled Access Plans Picked Up 1/14/2020 APPLICANT
Quality Review Completed 1/19/2020 YOUNG KIM
Building Plans Picked Up 1/23/2020 APPLICANT
Plan Check Approved 3/2/2020 ARSALAN SHABESTARI
Issued 5/12/2020 APPLICANT
Permit Finaled 3/16/2021 RONALD PACHECO

Permit Application Clearance Information

"D" conditions Cleared 2/13/2020 TERRI OSBORNE
DAS Clearance Cleared 2/13/2020 SHINE LIN
Green Code Cleared 2/13/2020 VIVIAN LAO
Specific Plan Cleared 2/13/2020 TERRI OSBORNE
HPOZ Cleared 2/25/2020 KATIE DEBIASE

Contact Information

Architect Corona,, Victor M; Lic. No.: C25767 25725 WALLACE PLACE      STEVENSON RANCH, CA 91381
Contractor J N N General Contractors Inc; Lic. No.: 1019980-B 2915 STOCKBRIDGE AVENUE      LOS ANGELES, CA 90032
Engineer Tuchscher,, James Todd; Lic. No.: C77649 5503 E 2ND ST      LONG BEACH, CA 90803

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 9/18/2020 Partial Approval RONALD PACHECO
Excavation/Setback/Form/Re-Bar 11/4/2020 Partial Approval RONALD PACHECO
Floor/Roof Diaphrgm/Shear Wall 11/4/2020 Partial Approval RONALD PACHECO
Insulation 11/13/2020 Partial Approval RONALD PACHECO
Floor/Roof Diaphrgm/Shear Wall 11/20/2020 Not Ready for Inspection RONALD PACHECO
Wood Frame 11/20/2020 Not Ready for Inspection RONALD PACHECO
Floor/Roof Diaphrgm/Shear Wall 11/23/2020 Partial Approval NICK DANERI
Final 12/28/2020 Not Ready for Inspection LANNY MERRICK
Green Building Final 12/28/2020 Not Ready for Inspection LANNY MERRICK
SGSOV-Seismic Gas S/O Valve 12/28/2020 SGSOV Not Ready LANNY MERRICK
Smoke Detectors 12/28/2020 Not Ready for Inspection LANNY MERRICK
Green Building Rough 12/30/2020 Not Ready for Inspection LANNY MERRICK
Final 1/6/2021 Not Ready for Inspection LANNY MERRICK
Green Building Final 1/6/2021 Not Ready for Inspection LANNY MERRICK
SGSOV-Seismic Gas S/O Valve 1/6/2021 SGSOV Not Ready LANNY MERRICK
Smoke Detectors 1/6/2021 Not Ready for Inspection LANNY MERRICK
Final 1/8/2021 Not Ready for Inspection LANNY MERRICK
Green Building Final 1/8/2021 Not Ready for Inspection LANNY MERRICK
SGSOV-Seismic Gas S/O Valve 1/8/2021 SGSOV Not Ready LANNY MERRICK
Smoke Detectors 1/8/2021 Not Ready for Inspection LANNY MERRICK
Final 1/15/2021 Not Ready for Inspection LANNY MERRICK
Green Building Final 1/15/2021 Not Ready for Inspection LANNY MERRICK
SGSOV-Seismic Gas S/O Valve 1/15/2021 SGSOV Approved LANNY MERRICK
Smoke Detectors 1/15/2021 Not Ready for Inspection LANNY MERRICK
Deputy Steel/Welding 1/26/2021 Conditional Approval RONALD PACHECO
Deputy Steel/Welding 1/27/2021 Conditional Approval RONALD PACHECO
Final 3/5/2021 Not Ready for Inspection RONALD PACHECO
Green Building Final 3/5/2021 Not Ready for Inspection RONALD PACHECO
Smoke Detectors 3/5/2021 Not Ready for Inspection RONALD PACHECO
Final 3/12/2021 Not Ready for Inspection RONALD PACHECO
Green Building Final 3/12/2021 Not Ready for Inspection RONALD PACHECO
Smoke Detectors 3/12/2021 Not Ready for Inspection RONALD PACHECO
Final 3/16/2021 Permit Finaled RONALD PACHECO
Green Building Final 3/16/2021 Approved RONALD PACHECO
Smoke Detectors 3/16/2021 Approved RONALD PACHECO