12756 W MOORPARK ST 91604

Certificate Information: 12756 W MOORPARK ST 91604

Application / Permit
19016-10000-40035
Plan Check / Job No.
B19LA26416
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
EPLAN 1561 - Soft-Story seismic retrofit per LABC Chapter 93: SOFT STORY RETROFIT TO EXISTING BUILDING USING (2) SPECIAL CANTILEVER COLUMN SYSTEMS.
Permit Issued
Issued on 7/8/2020
Issuing Office
Current Status
CofC Issued on 10/29/2020

Permit Application Status History

Submitted 12/16/2019 APPLICANT
Assigned to Plan Check Engineer 1/8/2020 VARAND SARKISIAN
Corrections Issued 1/14/2020 VARAND SARKISIAN
Quality Review Completed 1/23/2020 HANS SANTIAGO
Plan Check Approved 7/7/2020 VARAND SARKISIAN
Issued 7/8/2020 APPLICANT
OK for CofC 10/1/2020 JOE VELASQUEZ
CofC Issued 10/29/2020 DAVID TSAU

Permit Application Clearance Information

Tenant Habitability Plan Cleared 6/17/2020 STEVEN HOFSTAD

Contact Information

Contractor Procon Builders Inc; Lic. No.: 977214-A 9526 TOPANGA CANYON BLVD      CHATSWORTH, CA 91311

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/17/2020 Partial Approval VAHE KELEDJIAN
Pre-Inspection 7/17/2020 Corrections Issued VAHE KELEDJIAN
Deputy Steel/Welding 8/4/2020 Approved JOE VELASQUEZ
Footing/Foundation/Slab 8/5/2020 Not Ready for Inspection JOE VELASQUEZ
Footing/Foundation/Slab 8/6/2020 Not Ready for Inspection JOE VELASQUEZ
Footing/Foundation/Slab 8/7/2020 Corrections Issued JOE VELASQUEZ
Footing/Foundation/Slab 8/10/2020 Approved JOE VELASQUEZ
Structural Steel Frame 8/24/2020 Not Ready for Inspection JOE VELASQUEZ
Wood Frame 8/24/2020 Not Ready for Inspection JOE VELASQUEZ
Structural Steel Frame 8/25/2020 Not Ready for Inspection JOE VELASQUEZ
Wood Frame 8/25/2020 Corrections Issued JOE VELASQUEZ
Wood Frame 8/26/2020 Not Ready for Inspection JOE VELASQUEZ
Wood Frame 8/28/2020 Approved JOE VELASQUEZ
Wood Frame 8/31/2020 Not Ready for Inspection JOE VELASQUEZ
Drywall Nailing 9/3/2020 Approved JOE VELASQUEZ
Interior/Exterior Lathing 9/3/2020 Approved JOE VELASQUEZ
Final 10/1/2020 OK for CofC JOE VELASQUEZ
SGSOV-Seismic Gas S/O Valve 10/1/2020 SGSOV Approved JOE VELASQUEZ
Smoke Detectors 10/1/2020 Approved JOE VELASQUEZ