11845 W VOSE ST 91605
Certificate Information: 11845 W VOSE ST 91605
- Application / Permit
- 19016-10000-39950
- Plan Check / Job No.
- B19LA26369
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (22) Warehouse
- Work Description
- TI FOR EXISTING WAREHOUSE. BUIDING STRUCTURE INSIDE EXISTING WAREHOUSE. GROUNDWATER REMEDIATION SYSTEM, TREATMENT SYSTEM, GENERAL SITE IMPROVEMENTS.
- Permit Issued
- Issued on 12/8/2020
- Issuing Office
- Current Status
- Permit Finaled on 3/14/2023
Permit Application Status History
| Submitted | 12/13/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/24/2019 | JOE VO |
| Corrections Issued | 1/6/2020 | JOE VO |
| Quality Review Completed | 1/9/2020 | KEN GILL |
| Building Plans Picked Up | 1/14/2020 | APPLICANT |
| Disabled Access Plans Picked Up | 1/14/2020 | APPLICANT |
| Applicant returned to address corrections | 6/1/2020 | JOE VO |
| Green Plans Picked Up | 7/2/2020 | APPLICANT |
| Plan Check Approved | 11/23/2020 | JOE VO |
| Issued | 12/8/2020 | APPLICANT |
| Permit Finaled | 3/10/2023 | ROBERT DAVIS |
Permit Application Clearance Information
| Green Code | Cleared | 5/28/2020 | JOE VO |
| DAS Clearance | Cleared | 6/11/2020 | JOE VO |
| Eng Process Fee Ord 176,300 | Cleared | 7/16/2020 | JOHN TRIANTAFYLLOS |
| Historic monument | Cleared | 7/22/2020 | LAMBERT GIESSINGER |
| Low Impact Development | Cleared | 10/21/2020 | IDA MEISAMI-FARD |
| Roof/Waste drainage to street | Cleared | 11/2/2020 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | American Integrated Services Inc; Lic. No.: 757133-B | PO BOX 92316 LONG BEACH, CA 90809 |
| Engineer | Blanc,, Anthony; Lic. No.: GE2615 | 17187 BLUFF VISTA CT RIVERSIDE, CA 92503 |
| Engineer | Diebold,, John William; Lic. No.: S4540 | 2066 CONTINENTAL DR NE ATLANTA, GA 30345 |
Inspector Information
| JEFFREY FULTON, (818) 374-1132 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/16/2020 | Approved | ROBERT DAVIS |
| Footing/Foundation/Slab | 5/3/2021 | Partial Approval | ROBERT DAVIS |
| Reinforced Masonry Frame | 8/26/2021 | Partial Approval | ROBERT DAVIS |
| Masonry Wall/Backfill | 9/27/2021 | Partial Approval | ROBERT DAVIS |
| Masonry Wall/Backfill | 10/5/2021 | Not Ready for Inspection | ROBERT DAVIS |
| Masonry Wall/Backfill | 10/6/2021 | Approved | ROBERT DAVIS |
| Reinforced Masonry Frame | 10/14/2021 | Conditional Approval | ROBERT DAVIS |
| Light Gage Steel Frame | 1/20/2022 | Partial Approval | ROBERT DAVIS |
| Structural Steel Frame | 1/20/2022 | Approved | ROBERT DAVIS |
| Drywall Nailing | 2/9/2022 | Partial Approval | ROBERT DAVIS |
| Drywall Nailing | 2/18/2022 | Approved | ROBERT DAVIS |
| Drywall Nailing | 3/30/2022 | Partial Approval | ROBERT DAVIS |
| Final | 1/31/2023 | Not Ready for Inspection | ROBERT DAVIS |
| Green Building Final | 1/31/2023 | Approved | ROBERT DAVIS |
| SGSOV-Seismic Gas S/O Valve | 1/31/2023 | SGSOV No Gas | ROBERT DAVIS |
| Smoke Detectors | 1/31/2023 | Not Ready for Inspection | ROBERT DAVIS |
| Final | 3/10/2023 | Permit Finaled | ROBERT DAVIS |
| Smoke Detectors | 3/10/2023 | Approved | ROBERT DAVIS |