111 1/2 S WILTON PL 90004

Certificate Information: 111 1/2 S WILTON PL 90004

Application / Permit
19016-10000-39708
Plan Check / Job No.
B19LA26213
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE TO AN ACCESSORY DWELLING UNIT PER AB 494 AND SB299
Permit Issued
Issued on 9/22/2020
Issuing Office
Valley
Current Status
CofO Issued on 2/23/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/12/2019 APPLICANT
Assigned to Plan Check Engineer 12/20/2019 MONICA RAMIREZ
Corrections Issued 12/20/2019 MONICA RAMIREZ
Plan Check Approved 7/8/2020 RICARDO RAMIREZ
Building Plans Picked Up 7/10/2020 APPLICANT
Issued 9/22/2020 APPLICANT
CofO in Progress 5/4/2021 STUART CHAPMAN
Permit Finaled 2/23/2022 DEROLD HAUFF
CofO Issued 2/23/2022 DEROLD HAUFF
Permit Finaled 2/23/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/20/2019 BOK GOH
Eng Process Fee Ord 176,300 Cleared 12/20/2019 BOK GOH
Sewer availability Cleared 12/20/2019 BOK GOH
City Hist. Cultural Monument Cleared 1/6/2020 LAMBERT GIESSINGER
Historic monument Cleared 1/6/2020 LAMBERT GIESSINGER
Construction near power lines Cleared 5/2/2020 RIDWAN HARDY

Contact Information

Contractor Litman Inc; Lic. No.: 891510-B 19528 VENTURA BLVD   UNIT 242    TARZANA, CA 91356

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/8/2020 Partial Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 10/20/2020 Corrections Issued ARTHUR SARGSYAN
Footing/Foundation/Slab 10/30/2020 No Access for Inspection CHRIS CHRISTENSEN
Footing/Foundation/Slab 11/23/2020 Partial Approval CHRIS CHRISTENSEN
Sewer 11/23/2020 Partial Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 12/3/2020 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 1/11/2021 Approved CHRIS CHRISTENSEN
Green Building Rough 1/11/2021 Approved CHRIS CHRISTENSEN
Rough-Elec/Plmb/HVAC 1/11/2021 Approved CHRIS CHRISTENSEN
Insulation 1/15/2021 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 1/21/2021 Approved ROBERT VORHIS
Drywall Nailing 1/29/2021 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 1/29/2021 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 4/21/2021 Approved CHRIS CHRISTENSEN
Final 4/21/2021 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 4/21/2021 Corrections Issued CHRIS CHRISTENSEN
HVAC-Final 4/21/2021 Approved CHRIS CHRISTENSEN
PLUMBING-Final 4/21/2021 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 4/21/2021 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 4/21/2021 Approved CHRIS CHRISTENSEN
Final 5/3/2021 OK to Issue CofO STUART CHAPMAN
Green Building Final 5/3/2021 Approved STUART CHAPMAN
Special/Order Compliance 2/4/2022 Approved STUART CHAPMAN