111 1/2 S WILTON PL 90004
Certificate Information: 111 1/2 S WILTON PL 90004
- Application / Permit
- 19016-10000-39708
- Plan Check / Job No.
- B19LA26213
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE TO AN ACCESSORY DWELLING UNIT PER AB 494 AND SB299
- Permit Issued
- Issued on 9/22/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/23/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/12/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/20/2019 | MONICA RAMIREZ |
| Corrections Issued | 12/20/2019 | MONICA RAMIREZ |
| Plan Check Approved | 7/8/2020 | RICARDO RAMIREZ |
| Building Plans Picked Up | 7/10/2020 | APPLICANT |
| Issued | 9/22/2020 | APPLICANT |
| CofO in Progress | 5/4/2021 | STUART CHAPMAN |
| Permit Finaled | 2/23/2022 | DEROLD HAUFF |
| CofO Issued | 2/23/2022 | DEROLD HAUFF |
| Permit Finaled | 2/23/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/20/2019 | BOK GOH |
| Eng Process Fee Ord 176,300 | Cleared | 12/20/2019 | BOK GOH |
| Sewer availability | Cleared | 12/20/2019 | BOK GOH |
| City Hist. Cultural Monument | Cleared | 1/6/2020 | LAMBERT GIESSINGER |
| Historic monument | Cleared | 1/6/2020 | LAMBERT GIESSINGER |
| Construction near power lines | Cleared | 5/2/2020 | RIDWAN HARDY |
Contact Information
| Contractor | Litman Inc; Lic. No.: 891510-B | 19528 VENTURA BLVD UNIT 242 TARZANA, CA 91356 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/8/2020 | Partial Approval | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 10/20/2020 | Corrections Issued | ARTHUR SARGSYAN |
| Footing/Foundation/Slab | 10/30/2020 | No Access for Inspection | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 11/23/2020 | Partial Approval | CHRIS CHRISTENSEN |
| Sewer | 11/23/2020 | Partial Approval | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 12/3/2020 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 1/11/2021 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 1/11/2021 | Approved | CHRIS CHRISTENSEN |
| Rough-Elec/Plmb/HVAC | 1/11/2021 | Approved | CHRIS CHRISTENSEN |
| Insulation | 1/15/2021 | Approved | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 1/21/2021 | Approved | ROBERT VORHIS |
| Drywall Nailing | 1/29/2021 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 1/29/2021 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 4/21/2021 | Approved | CHRIS CHRISTENSEN |
| Final | 4/21/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 4/21/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| HVAC-Final | 4/21/2021 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 4/21/2021 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 4/21/2021 | SGSOV Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 4/21/2021 | Approved | CHRIS CHRISTENSEN |
| Final | 5/3/2021 | OK to Issue CofO | STUART CHAPMAN |
| Green Building Final | 5/3/2021 | Approved | STUART CHAPMAN |
| Special/Order Compliance | 2/4/2022 | Approved | STUART CHAPMAN |